Completed No litigation declared Plotted project

Bhartia Meadows

By BHARTIA MEADOWS

RG-MH-14765 · RERA P50500046885 · Last updated on MahaRERA portal: 8 Aug 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 25 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Apr 2026Possession promisedregistration recorded completed
69 of 70Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

Bhartia Meadows is a Plotted project by BHARTIA MEADOWS in Nagpur, Maharashtra, registered with MahaRERA as P50500046885 on 16 Sep 2022. The registration is recorded completed; possession was promised by 30 Apr 2026. The completion date has moved by 25 months from the original filing. 1 of the 70 units on this registration are recorded sold or booked.

At a glance

Project

  • NameBhartia Meadows
  • TypePlotted
  • Location
    • Kamptee Road
    • Kamptee Nagpur
    • Ranala
    • Kamptee
    • Nagpur
    • 441401
  • Pincode441401
  • RERA no.P50500046885
  • ReraGenie IDRG-MH-14765

Builder

  • NameBHARTIA MEADOWS
  • Entity typeCompany

Key dates

this monthRegisteredSep 2022First promiseMar 2024Revised toApr 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Sep 2022
  • Promised completion30 Apr 2026
  • Revised completionRevised to 30 Apr 2026 (originally 31 Mar 2024)
  • BuildingsNot stated in filing
  • Documents filed45 files

Current status

1%1 of 70 units booked

Figures as on 8 Aug 2024, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Aug 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 8 Aug 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,714 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Sameer Laxminarayan BhartiaNagpur (M Corp.)Nagpur
Sudhir Laxminarayan BhartiaNagpur (M Corp.)Nagpur
Chetan Jagdambaprasad BhartiaNagpur (M Corp.)Nagpur

Approvals and building plan

Permissible FSI15714.0
Proposed, not sanctioned15,714 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCivil Line Nagpur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAditya Indurkar
EngineerShoukat Ansari
Chartered AccountantRishi Lashkare
PartnerRole in project
BHARTIA MEADOWS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT50500019620Mar 2024 → Apr 2026

Reason as filed by the promoterv

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Mar 2024

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Bhartia Meadows.pdf8 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - March 2023.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - June 2023.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate - Sept 2023.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - Dec 2023.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect - March 2024.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - March 2023.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - June 2023.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - Sept 2023.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - Dec 2023.pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer - March 2024.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure - March 2023.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure - June 2023.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure - Sept 2023.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure - Dec 2023.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure - March 2024.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - March 2023_compressed (2).pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - June 2023_compressed.pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Sept 2023_compressed (2).pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Dec 2023_compressed (1).pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - March 2024_compressed.pdf16 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Bhartia Meadows - 1.pdf20 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Bhartia Meadows - 2.pdf20 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf13 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bhartia Meadows Format A.pdf9 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf30 Aug 2022
Details of encumbrances concerned to FinanceFile: Fianacial with Encumbrance.pdf25 Jul 2022
Deviation Report with respect to Allotment letterFile: No Deviation Form Allotment Letter.pdf21 Jul 2022
Deviation Report with respect to model copy of AgreementFile: No Deviation Form Agreement To Sale.pdf21 Jul 2022
Proforma of Allotment letterFile: AGREEMENT.pdf20 Jul 2022
Proforma of Allotment letterFile: Allotment Letter.pdf20 Jul 2022
Details of encumbrances concerned to LegalFile: Encumbrance Letter.pdf18 Jul 2022
Details of encumbrances concerned to LegalFile: Conser Letter for Ligal.pdf13 Jul 2022
CERSAI detailsFile: CERSAI Search Report.pdf5 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf21 Jun 2022
Layout approvalFile: LAYOUT APPROVAL NMRDA DRAW.pdf20 Jun 2022
Building plan approval or NA orderFile: NA ORDER PLOTTED DEVOLOPMENT.pdf20 Jun 2022
PAN CardFile: PAN CARD BHARTIA MEADOWS.pdf20 Jun 2022
Copy of the legal title reportFile: LEGAL TITLE REOPRT.pdf20 Jun 2022
Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL NMRDA DRAW.pdf20 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER PLOTTED DEVOLOPMENT.pdf20 Jun 2022
Declaration about Commencement CertificateFile: Declaration About Commencment Certificate.pdf20 Jun 2022
Declaration in FORM BFile: Affidavit Cum Declaration.pdf20 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf20 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf20 Jun 2022

How this compares with Nagpur

1%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 25 months
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Bhartia Meadows on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kamptee Nagpur2,800+ in Nagpur

Builder: BHARTIA MEADOWS

BHARTIA MEADOWS has 1 registration on MahaRERA, including Bhartia Meadows. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Bhartia Meadows is delayed beyond 30 Apr 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Bhartia Meadows?

The registered promoter entity is BHARTIA MEADOWS, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Bhartia Meadows?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Bhartia Meadows?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Bhartia Meadows?

The professionals named in the filing: Architect: Aditya Indurkar; Engineer: Shoukat Ansari; Chartered Accountant: Rishi Lashkare. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Bhartia Meadows?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Bhartia Meadows. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Bhartia Meadows to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.