Home / Browse projects / Nashik, Maharashtra / Bhargav Business Center
Bhargav Business Center
RG-MH-13789 · RERA P51600029129 · Last updated on MahaRERA portal: 27 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 36 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Bhargav Business Center is a Commercial project by BKP Realities LLP in Nashik, Maharashtra, registered with MahaRERA as P51600029129 on 29 Apr 2021. Possession is promised by 31 Mar 2028. The completion date has moved by 36 months from the original filing. 0 of the 145 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameBhargav Business Center
- TypeCommercial
- Location
- Mumbai Naka
- Nahik Shivar
- Nashik (M Corp.)
- Nashik
- 422003
- Pincode422003
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600029129
- ReraGenie IDRG-MH-13789
Builder
- NameBKP Realities LLP
- Entity typePartnership
- PartnersLalitkumar Bhausaheb Kudale, Jaswandi Lalitkumar Kudale, Shreeniwas Sopan Londhe, Rahul Tryambak Date, Kailas Shankar Kamod, Mangala Kailas Kamod, Omkar Akrur Kudale, Niwedita Ajay Kamod, Pandharinath Dagadu Patil, Priya Sandeep Jagade, Ruhi Madar Gholap, Hiren Kailas Kamod and 2 more
- Declared earlier projects5 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on29 Apr 2021
- Promised completion31 Mar 2028
- Revised completionRevised to 31 Mar 2028 (originally 31 Mar 2025)
- Buildings1 building record
- Documents filed84 files
Current status
Figures as on 27 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Bhargav Buisness Center - Building No 2 | NA | 10 | 10 | 0 | 145 | 145 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 40%.
Bhargav Buisness Center - Building No 2: 32% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 40% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed145
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership7
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| GAJANAN SHELAR | Nashik | Nashik |
| CHANDRAMOHAM DAMODER SHELAR | Nashik | Nashik |
| PRATAP PANDURANG GAIKWAD | Nashik | Nashik |
| RAHUL SHANTARAM SHELAR | Nashik | Nashik |
| SHANTARAM DAMODER SHELAR | Nashik | Nashik |
| NILESH SHANTARAM SHELAR | Nashik | Nashik |
| VISHAL GAJANAN SHELAR | Nashik | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Bhargav Buisness Center - Building No 2 | NA | Rs 25.67 cr | Rs 17.97 cr |
| - | NA | Rs 1.93 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Studio Architectonic |
| Engineer | G A Bhilare Consultants Pvt Ltd |
| Chartered Accountant | SPCM and Associates |
| Chartered Accountant | Narendra Navandar & Co |
| Partner | Role in project |
|---|---|
| BKP Realities LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterwe request an extension of the project completion date until 31/03/2028 to successfully complete the remaining construction.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Apr 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Mar 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Mar 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2028
Documents filed84
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 27 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 26 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 26 May 2026 |
| Withdrawal Update Form 3File: Form 3_.pdf | 26 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 25 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 25 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 25 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 25 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 25 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 25 May 2026 |
| Withdrawal Update Form 3File: Form-3.pdf | 25 May 2026 |
| Withdrawal Update Form 3File: Form 3_.pdf | 25 May 2026 |
| Withdrawal Update Form 3File: Form 3_.pdf | 25 May 2026 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: BBC form 2A march 23.pdf | 2 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: BBC form 2A march 24.pdf | 2 Jun 2025 |
| Declaration in FORM BFile: Form B - BBC.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 BBC Artchitect's Certificate 31032023.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 BBC Artchitect's Certificate 30062023.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 BBC Artchitect's Certificate 30092023.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 BBC Artchitect's Certificate 30092023.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 BBC Artchitect's Certificate 30092023.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 BBC Artchitect's Certificate 31122023.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 BBC Artchitect's Certificate 31032024.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 BBC Artchitect's Certificate 30092024.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 BBC Artchitect's Certificate 31122024.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 BBC Artchitect's Certificate 31032025.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31032025_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Form 3 31122024_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 30092024_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Form 3 30062024_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Form 3 30062024_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Form 3 31122023_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Form 3 30092023_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Form 3 30062023_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form 3 31032023_11zon.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Form 3 31032024_11zon.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 BBC form 2 Dec 24.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BBC form 2 march 25.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 BBC form 2 sept 24.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 BBC form 2 june 24.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 BBC form 2 March 24.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 BBC form 2 Dec 23.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 BBC fotm 2 Sep 23.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 BBC form 2 June 23.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 BBC form 2 March 23.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: Jan- Mar 23.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: April - June 23.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: July - Sep 23.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: OCT - DEC 2023.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: Jan - Mar 24 BBC.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: April - June 24 BBC.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: July - Sep 2024 BBC.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: Oct - Dec 24 BBC.pdf | 31 May 2025 |
| Disclosure of sold/ booked inventoryFile: jan - mar 25 BBC.pdf | 31 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022 - 2023.pdf | 31 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023 - 2024.pdf | 31 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate FORM 2 2021.pdf | 29 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2-Engineer Certificates_2022.pdf | 29 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Bkp Realities LLp.pdf | 29 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Arc.pdf | 3 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-ARCHITECT Certificates_2022.pdf | 3 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer-Form 2 A-March 2021.pdf | 3 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer-Form 2 A-March 2021.pdf | 3 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Certificates-Form -2-April-2022.pdf | 3 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: BBC_RERA Form 2 A_March 2022.pdf | 3 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA-Form-3-310323_compressed.pdf | 3 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA-Form-3-310323_compressed.pdf | 3 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA-For- 5- 301222_compressed_compressed.pdf | 3 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA-For- 5- 301222_compressed_compressed.pdf | 3 Apr 2023 |
| Details of encumbrancesFile: Index II.pdf | 16 Feb 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200227355529_For_Asset_Based_Search_04_01_2022_19_27_21_278.pdf | 4 Jan 2022 |
| Copy of the legal title reportFile: RERA Form-A-Title-BCC Towers compress_.pdf | 19 Apr 2021 |
| Details of encumbrancesFile: Realities Declaration.pdf | 18 Mar 2021 |
| Declaration in FORM BFile: RERA Form-B_compressed.pdf | 18 Mar 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-BBC Nashik CA Certificate_compressed.pdf | 18 Mar 2021 |
| Proforma of Allotment letterFile: RERA UPLOADED DRAFT.pdf | 18 Mar 2021 |
| Layout approvalFile: 060321-Bhargav Realities NMC Sanction Plan 1_compressed_compressed (1).pdf | 6 Mar 2021 |
| Building plan approvalFile: BBC Towers- NA- Order.pdf | 6 Mar 2021 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| VIBHA BUILDIN 1 | Narhe Manaji Nagar | 32 | Completed | Jun 2018 | Late, Jul 2019 |
| VIVIANA | Panchavati Collage Road | 320 | Completed | Sep 2017 | Jul 2017 |
| RAMRAJYA SANKUL A AND B WING | Panchavati Nashik | 70 | Completed | Mar 2017 | Late, Jul 2017 |
| ABALONE B WING | Ambegaon BK | 64 | Completed | Mar 2016 | Jan 2016 |
| Bhargav House | Hingane Kh | 6 | Completed | Mar 2014 | Late, Mar 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 84 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Bhargav Business Center on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nahik Shivar4,100+ in Nashik
Filed coordinates, straight-line distance. 350 registered projects within 2 km.
THE PLATINUM MALL BY PARKSYDE
JAIKUMAR CONSTRUCTIONS LTD
AVADH UTOPIA
DHATRAK CONSTRUWELL
ROONGTA ELEGANTE APARTMENT
ROONGTA LANDMARKS LLP
Siddhivinayak Trade Center
Dhatrak Constructions
G SQUARE
GIRI ASSOCIATE CONSTRUCTION
SADGURU HOMES
SHREE SADGURU HOMES
See every Nashik project, with the district possession charts
Builder: BKP Realities LLP
BKP Realities LLP has 1 registration on MahaRERA, including Bhargav Business Center. Its filings disclose 5 earlier MahaRERA projects: declares 2 of 5 past projects completed on time. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Bhargav Business Center is delayed beyond 31 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Bhargav Business Center?
The registered promoter entity is BKP Realities LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Bhargav Business Center?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Bhargav Business Center?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Bhargav Business Center?
The professionals named in the filing: Architect: Studio Architectonic; Engineer: G A Bhilare Consultants Pvt Ltd; Chartered Accountant: SPCM and Associates; Chartered Accountant: Narendra Navandar & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Bhargav Business Center?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.