ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / BHAKTI HOME ROYALS

Completed No litigation declared Others project

BHAKTI HOME ROYALS

By Jayantilal Dharamshibhai Parmar

RG-MH-47031 · RERA P99000011844 · Last updated on MahaRERA portal: 20 Jan 2023

Source: official MahaRERA filing

Red flags

  • 5 complaints at MahaRERA
  • Completion date moved by 72 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
177 of 396Construction stages doneacross 36 buildings; furthest along: Internal walls, 95%
5Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

BHAKTI HOME ROYALS is a Others project by Jayantilal Dharamshibhai Parmar in Palghar, Maharashtra, registered with MahaRERA as P99000011844 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 72 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameBHAKTI HOME ROYALS
  • TypeOthers
  • Location
    • VAJRESHWARI ROAD
    • SHIRSAD PHATA
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401303
  • Pincode401303
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000011844
  • ReraGenie IDRG-MH-47031

Builder

  • NameJayantilal Dharamshibhai Parmar
  • Entity typeIndividual

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
  • Buildings36 building records
  • Documents filed112 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROW HOUSE 1 AND 31NA30000
ROW HOUSE 2 AND 32NA30000
ROW HOUSE 3 AND 33NA30000
ROW HOUSE 4 AND 34NA30000
ROW HOUSE 5 AND 35NA30000
ROW HOUSE 6 AND 36NA30000
ROW HOUSE 7 AND 37NA30000
ROW HOUSE 8 AND 38NA30000
ROW HOUSE 9 AND 39NA30000
ROW HOUSE 10 AND 40NA30000
ROW HOUSE 11 AND 41NA30000
ROW HOUSE 12 AND 13NA30000
ROW HOUSE 42 AND 43NA30000
ROW HOUSE 14 AND 15NA30000
Holiday Hoe/HotelNA30000
ROW HOUSE 16NA30000
ROW HOUSE 17NA30000
ROW HOUSE 18NA30000
ROW HOUSE 19NA30000
ROW HOUSE 20NA30000
ROW HOUSE 21NA30000
ROW HOUSE 22NA30000
ROW HOUSE 23NA30000
ROW HOUSE 24NA30000
ROW HOUSE 25NA30000
ROW HOUSE 26NA30000
ROW HOUSE 27NA30000
ROW HOUSE 28NA30000
ROW HOUSE 29NA30000
ROW HOUSE 30NA30000
BUNGALOW 1NA30000
BUNGALOW 2NA30000
CLUB HOUSE 1NA20000
CLUB HOUSE 2NA20000
CFCNA30000
CLUB HOUSE 3NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 20 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 36 buildings; the table lists the first 20.

177 of 396 construction stages are filed complete across 36 buildings. The stage furthest along is Internal walls, at 95%.

ROW HOUSE 1 AND 3156%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE 2 AND 3258%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE 3 AND 3358%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE 4 AND 3458%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE 5 AND 3558%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE 6 AND 3658%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE 7 AND 3758%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
ROW HOUSE 8 AND 3888%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
ROW HOUSE 9 AND 3988%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
ROW HOUSE 10 AND 4080%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 11 AND 4180%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 12 AND 1375%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 42 AND 4380%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 14 AND 1580%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
Holiday Hoe/Hotel80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 1680%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 1780%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 1880%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 1980%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
ROW HOUSE 2080%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%

Progress on shared amenities15

As on 20 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes80%
Street LightingYes85%
Community BuildingsYes50%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes80%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed36

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots36
Closed/Covered32
Open Space4
BuildingClosed/CoveredOpen SpaceTotal
ROW HOUSE 1 AND 31101
ROW HOUSE 2 AND 32101
ROW HOUSE 3 AND 33101
ROW HOUSE 4 AND 34101
ROW HOUSE 5 AND 35101
ROW HOUSE 6 AND 36101
ROW HOUSE 7 AND 37101
ROW HOUSE 8 AND 38101
ROW HOUSE 9 AND 39101
ROW HOUSE 10 AND 40101
ROW HOUSE 11 AND 41101
ROW HOUSE 12 AND 13101
ROW HOUSE 42 AND 43101
ROW HOUSE 14 AND 15101
ROW HOUSE 16101
ROW HOUSE 17101
ROW HOUSE 18101
ROW HOUSE 19101
ROW HOUSE 20101
ROW HOUSE 21101
ROW HOUSE 22101
ROW HOUSE 23101
ROW HOUSE 24101
ROW HOUSE 25101
ROW HOUSE 26101
ROW HOUSE 27101
ROW HOUSE 28101
ROW HOUSE 29101
ROW HOUSE 30101
BUNGALOW 1101
BUNGALOW 2101
CFC145

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area7,010 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI7010.0
Proposed, not sanctioned3,995 sq m
Buildings approved36
Buildings sanctioned36

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHAVIR NAGAR KANDIVALI WEST

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectENCON
PartnerRole in project
Jayantilal Dharamshibhai Parmar-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000005202Dec 2019 → Dec 2020

Reason as filed by the promoterBecause of frequent amendments in Government Policy, especially prolonged delay in notifying the DCPR 2034, there were mandatory amendments in sanctioned plans and all further permission got delayed.

EXT99000012893Dec 2019 → Dec 2025

Reason as filed by the promoterRevision in plans as approved by the authorities.

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC12504613ANIL LABHSHANKAR OZAJayantilal Dharamshibhai Parmar24/12/2025
CC12600648ANIL VINAYAK MHATREJayantilal Dharamshibhai Parmar04/02/2026
CC12600732Maruti Shivaji JadhavJayantilal Dharamshibhai Parmar08/02/2026
CC12600848Sachin Yashwant SawantJayantilal Dharamshibhai Parmar15/02/2026
CC12602344Nitesh Chandrbhal MishraJayantilal Dharamshibhai Parmar21/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Oct 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Jul 2021

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf20 Jan 2023
Declaration about Commencement CertificateFile: BBD_Form-D_RERA.pdf2 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Mar22 - Engineers Certificate_compressed.pdf2 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20.pdf2 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21.pdf2 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2021-22.pdf2 Dec 2022
Architect’s Certificate on Completion of Project (Form 4)File: RERA_Form 4.pdf5 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: BBD_OC_29062021.pdf6 Jul 2021
Certificates of CA (Form 3)File: BBD_CA Form 3_JAN 2020.pdf20 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EN CON_ARCHITECH CERTIFICATE_JAN 2020_1 TO 15.pdf19 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EN CON_ARCHITECH CERTIFICATE_JAN 2020_15 TO 16.pdf19 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EN CON_ARCHITECH CERTIFICATE_JAN 2020_31 TO 45.pdf19 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EN CON_ARCHITECH CERTIFICATE_JAN 2020_46 TO 59.pdf19 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_JAN 2020_1 to 15.pdf19 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_JAN 2020_16 to 30.pdf19 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_JAN 2020_31 To 45.pdf19 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_JAN 2020_46 to 53.pdf19 Mar 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: BBD_RERA_CA FORM 5 with UDIN_F Y 2017-18.pdf22 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: BBD_RERA_CA FORM 5 with UDIN_F Y 2018-19.pdf22 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EN CON- Architect Certificate_Oct 2019-1-20.pdf26 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EN CON- Architect Certificate_Oct 2019-21-40.pdf26 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EN CON- Architect Certificate_Oct 2019-41-59.pdf26 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_Oct 2019_1 to 11.pdf26 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_Oct 2019_12 to 22.pdf26 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_Oct 2019_23 to 33.pdf26 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_Oct 2019_34 to 43.pdf26 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EN CON- Engineer Certificate_Oct 2019_44 to 53.pdf26 Nov 2019
Certificates of CA (Form 3)File: BBD_MahaRERA_CA Certificate3_Oct 19_.pdf26 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD RERA_Engineers Certificate_July 19_1.pdf7 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD RERA_Engineers Certificate_July 19_2.pdf7 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD RERA_Architech Certificate_July 19_1.pdf31 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD RERA_Architech Certificate_July 19_2.pdf31 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD RERA_Architech Certificate_July 19_3.pdf31 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD RERA_Architech Certificate_July 19_4.pdf31 Jul 2019
Certificates of CA (Form 3)File: BBD RERA_ CA Form 3_July 19_.pdf31 Jul 2019
Certificates of CA (Form 3)File: BBD_MahaRERA_CA Certificate3_Apr 19.pdf2 May 2019
Details of encumbrancesFile: SBI_NOC_BBD.pdf24 Apr 2019
Certificates of CA (Form 3)File: BBD_FORM 3_Jan'19_.pdf3 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_Eng Certfct_1 to 13.pdf31 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_Eng Certfct_14 to 26.pdf31 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_Eng Certfct_27 to 39.pdf31 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_Eng Certfct_40 to 51.pdf31 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD_Arch Certfct_1 to 40_Compressed.pdf24 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD_Arch Certfct_41 to 87_Compressed.pdf24 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_Eng Certfct 21 to 40_Compressed.pdf24 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_Eng Certfct 41 to 51_Compressed.pdf24 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_Engineers Certificate 1-20-compressed.pdf24 Oct 2018
Certificates of CA (Form 3)File: BBD_FORM 3.pdf24 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD Form1_Architect Certificate 1_Apr 18_Compresd.pdf2 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD Form1_Architect Certificate 2_Apr 18_Compresd.pdf2 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD Form1_Architect Certificate 4_Apr 18_Compresd.pdf2 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD Form1_Architect Certificate 5_Apr 18_Compresd.pdf2 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD Form1_Architect Certificate 6_Apr 18_Compresd.pdf2 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD Form1_Architect Certificate 7_Apr 18_Compresd.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD Form1_Architect Certificate 3_Apr 18_Compresd.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD Form2_Engineers Certificate1 1 to 8_Apr 18.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD Form2_Engineers Certificate2 9 to 15_Apr 18.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD Form2_Engineers Certificate3 16 to 23_Apr 18.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD Form2_Engineers Certificate4 24 to 30_Apr 18.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD Form2_Engineers Certificate5 31 to 38_Apr 18.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD Form2_Engineers Certificate6 39 to 45_Apr 18.pdf2 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD Form2_Engineers Certificate7 46 to 49_Apr 18.pdf2 May 2018
Certificates of CA (Form 3)File: BBD_MahaRERA_CA Certificate1_Apr18.pdf2 May 2018
Certificates of CA (Form 3)File: BBD_MahaRERA_CA Certificate2_Apr18.pdf2 May 2018
Certificates of CA (Form 3)File: BBD_MahaRERA_CA Certificate3_Apr18.pdf2 May 2018
Commencement Certificates / NA Order for plotted developmentFile: BBD_Layout_Parking.pdf31 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD_ Architech Certificate 1 to 15.pdf30 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD_ Architecht Certificate 16 to 37.pdf30 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD_ Architecht Certificate 38 to 54.pdf30 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: BBD_ Architecht Certificate 55 to 71.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_ENG CERTIFI 1 to 25_Oct 17.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_ENG CERTIF 26 to 51_Oct 17.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BBD_ENG CERTIF 52 to 71_Oct 17.pdf30 Oct 2017
Certificates of CA (Form 3)File: BBD_RERA_CA CERTFCT_OCT 17_1-compressed.pdf30 Oct 2017
Certificates of CA (Form 3)File: BBD_RERA_CA CERTFCT_OCT 17_2.pdf30 Oct 2017
Certificates of CA (Form 3)File: BBD_RERA_CA CERTFCT_OCT 17_3.pdf30 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: BBD_VVCMC TP RDP VP 0373 072 2017_1.pdf26 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: BBD_VVCMC TP RDP VP 0373 072 2017_2.pdf26 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: BBD_VVCMC TP RDP VP 0373 072 2017_2.pdf26 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: BBD_VVCMC TP RDP VP 0373 072 2017_3.pdf26 Oct 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 72 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BHAKTI HOME ROYALS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHIRSAD PHATA3,200+ in Palghar

Builder: Jayantilal Dharamshibhai Parmar

Jayantilal Dharamshibhai Parmar has 1 registration on MahaRERA, including BHAKTI HOME ROYALS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if BHAKTI HOME ROYALS is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BHAKTI HOME ROYALS?

The registered promoter entity is Jayantilal Dharamshibhai Parmar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BHAKTI HOME ROYALS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BHAKTI HOME ROYALS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BHAKTI HOME ROYALS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BHAKTI HOME ROYALS?

The professionals named in the filing: Architect: ENCON. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BHAKTI HOME ROYALS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BHAKTI HOME ROYALS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BHAKTI HOME ROYALS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.