Home / Browse projects / Raigarh, Maharashtra / Bhagwati Gami Altair
Bhagwati Gami Altair
RG-MH-62636 · RERA PM1270002601676 · Last updated on MahaRERA portal: 5 Aug 2026
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 11 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Bhagwati Gami Altair is a Mixed project by Bhagwati Estates in Raigarh, Maharashtra, registered with MahaRERA as PM1270002601676 on 27 Aug 2026. Possession is promised by 30 Jun 2031.
At a glance
Project
- NameBhagwati Gami Altair
- TypeMixed
- Location
- Plot No. 61
- Sector - 34A
- Kharghar
- Panvel
- Raigarh
- 410210
- Pincode410210
- MapView location on Google Maps (as filed on RERA)
- RERA no.PM1270002601676
- ReraGenie IDRG-MH-62636
Builder
- NameBhagwati Estates
- Entity typePartnership
- GSTIN27ABAFB2986M1Z1
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on27 Aug 2026
- Promised completion30 Jun 2031
- Revised completionNone
- Buildings1 building record
- Documents filed11 files
Current status
Figures as on 5 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Bhagwati Gami Altair | NA | 45 | 40 | 299 | 28 | 327 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 5 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.
Bhagwati Gami Altair: 5% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 50% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 5 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | 0% |
| Solid Waste Management And Disposal | No | 0% |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | No | 0% |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | 0% |
| Open Parking | No | Not applicable |
Parking filed633
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Destination Architecture Interior Designs |
| Engineer | Associated Structural Engineers LLP |
| Chartered Accountant | H M SHAH & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Bhagwati Estates | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
Documents filed11
As listed on the registration. The files themselves are on the MahaRERA portal.
| Document | Uploaded |
|---|---|
| ANNEXURE A (7) | 5 Aug 2026 |
| Floor Plans-1 Highlighted | 4 Jul 2026 |
| Floor Plans-2 | 4 Jul 2026 |
| Floor Plans-3 | 4 Jul 2026 |
| Floor Plans-4 | 4 Jul 2026 |
| Floor Plans-5 | 4 Jul 2026 |
| Floor Plans-6 | 4 Jul 2026 |
| Floor Plans-7 | 4 Jul 2026 |
| Floor Plans-8 | 4 Jul 2026 |
| Floor Plans-9 | 4 Jul 2026 |
| Floor Plans-10 | 4 Jul 2026 |
How this compares with Raigarh
Computed across the 5,893 Raigarh projects on ReraGenie, from their own filings.
Keep Bhagwati Gami Altair on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kharghar5,893 in Raigarh
KHARGHAR HILLS
TODAY PRACHAR DEVELOPERS LLP, BHADRESH RAJ
ANANDAM - II
TODAY GLOBAL HOMES
Godrej Varanya Phase 1
Godrej Properties Limited
Sai World Empire Phase III
paradisesuperstructures
SATYAM TRINITY TOWERS
SATYAM INFRA REALTY LLP
GeeCee Emerald
GeeCee Ventures Limited
See every Raigarh project, with the district possession charts
Builder: Bhagwati Estates
Bhagwati Estates has 1 registration on MahaRERA, including Bhagwati Gami Altair. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if Bhagwati Gami Altair is delayed beyond 30 Jun 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Bhagwati Gami Altair?
The registered promoter entity is Bhagwati Estates, a partnership as per the filing. Its GSTIN 27ABAFB2986M1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Bhagwati Gami Altair?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Bhagwati Gami Altair?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Bhagwati Gami Altair?
The professionals named in the filing: Architect: Destination Architecture Interior Designs; Engineer: Associated Structural Engineers LLP; Chartered Accountant: H M SHAH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Bhagwati Gami Altair?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback