ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / BADRIDHAM

Registered No litigation declared Residential / Group Housing project

BADRIDHAM

By PURVA BUILDERS & DEVELOPERS

RG-MH-19100 · RERA P52000078142 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Rs 5.00 crore secured on the land, in favour of SMFG INDIA HOME FINANCE CO LTD
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Staircases, 75%
53 of 74Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

BADRIDHAM is a Residential / Group Housing project by PURVA BUILDERS & DEVELOPERS in Raigarh, Maharashtra, registered with MahaRERA as P52000078142 on 25 Nov 2024. Possession is promised by 31 Dec 2027. 21 of the 74 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameBADRIDHAM
  • TypeResidential / Group Housing
  • Location
    • Nevali
    • Nevali Tembhode
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000078142
  • ReraGenie IDRG-MH-19100

Builder

  • NamePURVA BUILDERS & DEVELOPERS
  • Entity typePartnership
  • PartnersHitesh Shaha, Ashwini Dewang, Sandeep Sawant
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Nov 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed76 files

Current status

28%21 of 74 units booked
66.5%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BADRIDHAM A AND B WINGNA7774074

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 75%.

BADRIDHAM A AND B WING: 39% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor25%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Closed/Covered21
Open Space29

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,498 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofSMFG INDIA HOME FINANCE CO LTD
Secured amountRs 5.00 crore
CERSAI search filedYes
Declared on7 Aug 2025
LandownerVillageDistrict
BHARAT DUTTNavi Mumbai (M Corp.)Thane

Approvals and building plan

Sanctioning authorityCIDCO NAINA
Permissible FSI3606.75
Proposed, not sanctioned3,607 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR SHOP NO 1 AND 2 PRAJAPATI HOUSE PLOT NO 13 SECTOR 19 PANVEL MATHERAN ROAD NEW PANVEL NAVI MUMBAI 410206
Estimated costRs 8.92 cr
Cost incurredRs 5.93 cr
Work done66.5%
BuildingWingEstimatedIncurred
BADRIDHAM A AND B WINGNARs 8.48 crRs 5.93 cr
-NARs 44.62 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDeepak Thakare
EngineerYateesh Tare
EngineerAmol Dhangar
Chartered AccountantCap & Co
Chartered AccountantKunal Savla
PartnerRole in project
PURVA BUILDERS & DEVELOPERS-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12500226Bhakti AchrekarPURVA BUILDERS & DEVELOPERS27/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Nov 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Badridham form 1 dtd - 31-03-2026.pdf24 Apr 2026
Withdrawal Update Form 2File: Badridham From 2 dtd - 31-03-2026.pdf24 Apr 2026
Withdrawal Update Form 3File: Badridham Form- 3 dtd- 9-04-2026 March.pdf24 Apr 2026
Withdrawal Update Form 1File: Badridham Form 1 dtd- 31-12-2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Badridham Form 2 dtd- 31-12-2025.pdf20 Jan 2026
Withdrawal Update Form 3File: Badridham form 3 dtd - 12-01-2026.pdf20 Jan 2026
Withdrawal Update Form 1File: Badridham Form 1 Sept 2025.pdf14 Oct 2025
Withdrawal Update Form 2File: Badridham Form 2 Sept 2025.pdf14 Oct 2025
Withdrawal Update Form 3File: Badridham Form 3 Sept 2025.pdf14 Oct 2025
Form 5 (FY 2024-2025)File: Badridham Form 5 2024-25.pdf13 Oct 2025
Withdrawal Update Form 1File: Form 1 Badridham June 2025.pdf7 Aug 2025
Withdrawal Update Form 2File: Form 2 Badridham June 2025.pdf7 Aug 2025
Withdrawal Update Form 3File: Form 3 Badridham June 2025.pdf7 Aug 2025
Form 2A (FY 2024-2025)File: Badridham Form 2A 2024-25.pdf19 Jul 2025
Form 1File: Form 1 Badridham June 2025.pdf16 Jul 2025
Form 2File: Form 2 Badridham June 2025.pdf16 Jul 2025
Form 3File: Form 3 Badridham June 2025.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Badridham June 2025.pdf16 Jul 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Badridham Revised Format A.pdf3 May 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Badridham Revised Format B.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Badridham March 2025.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Badridham March 2025.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Badridham March 2025.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Badridham March 2025.pdf15 Apr 2025
Proforma of Agreement for saleFile: Revised AFS.pdf21 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (31-12-2024) Badridham.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Badridham Form 3 (15-01-2025).pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Badridham Form 2 (31-12-2024).pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory of Badridham 15-01-2025.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (31-12-2024) Badridham.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Badridham Form 3 (15-01-2025).pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Badridham Form 2 (31-12-2024).pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold-Unsold Inventory of Badridham 15-01-2025.pdf16 Jan 2025
Details of encumbrances concerned to FinanceFile: Revised Declaration for Financial Encumbrances.pdf9 Jan 2025
Details of encumbrances concerned to LegalFile: Revised Declaration for Financial Encumbrances.pdf9 Jan 2025
Proforma of Agreement for saleFile: Agreement_for_Sale_Final[1].pdf9 Jan 2025
Details of encumbrances concerned to FinanceFile: Revised Declaration for Financial Encumbrances.pdf9 Jan 2025
Details of encumbrances concerned to LegalFile: Revised Declaration for Financial Encumbrances.pdf9 Jan 2025
Proforma of Agreement for saleFile: Agreement_for_Sale_Final[1].pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Badridham final Form 3 (14-11-2024).pdf15 Nov 2024
Copy of the legal title reportFile: Legal Title Search Report (Badridham).pdf6 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: CC verification Mail.pdf6 Nov 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Rera Designated Bank account.pdf6 Nov 2024
Proforma of Allotment letterFile: allotment Letter.pdf14 Oct 2024
Other - LegalFile: Annexure A (1).pdf14 Oct 2024
Declaration about Commencement CertificateFile: Declaration about commencement certificate (1).pdf14 Oct 2024
Deviation Report with respect to Allotment letterFile: Deviation report for Allotment Letter.pdf14 Oct 2024
Other - TechnicalFile: Annexure A (1).pdf14 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Deviation report for agreement for sale.pdf14 Oct 2024
Proforma of Agreement for saleFile: Agreement for Sale Final (1).pdf14 Oct 2024
Building plan approvalFile: Building Plan 4.pdf11 Oct 2024
Building plan approvalFile: Building Plan 3.pdf11 Oct 2024
Building plan approvalFile: Building Plan 2.pdf11 Oct 2024
Building plan approvalFile: Building Plan 1.pdf11 Oct 2024
Layout approvalFile: Layout.pdf11 Oct 2024
PAN CardFile: Purva Builders Developers Pan Card.pdf11 Oct 2024
Details of encumbrances concerned to FinanceFile: Declaration of Financial Non-Encumbrances.pdf11 Oct 2024
Details of encumbrances concerned to FinanceFile: Declaration of Legal Non-Encumbrances .pdf11 Oct 2024
Copy of Layout Approval (in case of layout)File: Layout.pdf11 Oct 2024
Declaration in FORM BFile: Affidavit Cum Declaration Form B.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (20-09-2024) Badridham.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (23-09-2024) Badridham.pdf11 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Copy.pdf11 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 4.pdf11 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 1.pdf11 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2.pdf11 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 3.pdf11 Oct 2024
Other - LegalFile: Authority.pdf11 Oct 2024
CERSAI detailsFile: Declaration About CERSAI Report .pdf11 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A for Promoter (Rera Bank Account).pdf11 Oct 2024
Details of encumbrances concerned to LegalFile: Declaration of Financial Non-Encumbrances.pdf11 Oct 2024
Details of encumbrances concerned to LegalFile: Declaration of Legal Non-Encumbrances .pdf11 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate organisations Sandeep Sawant.pdf11 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate organisations Hitesh Shaha.pdf11 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other real estate organisations Ashwini Dewang.pdf11 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured-Unsecured .pdf11 Oct 2024

How this compares with Raigarh

28%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep BADRIDHAM on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nevali Tembhode5,900+ in Raigarh

2 kmBADRIDHAMCompleted 26Lapsed / revoked 6Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 50 registered projects within 2 km.

Builder: PURVA BUILDERS & DEVELOPERS

PURVA BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including BADRIDHAM. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if BADRIDHAM is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of BADRIDHAM?

The registered promoter entity is PURVA BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in BADRIDHAM?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against BADRIDHAM?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for BADRIDHAM?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at BADRIDHAM?

The professionals named in the filing: Architect: Deepak Thakare; Engineer: Yateesh Tare; Engineer: Amol Dhangar; Chartered Accountant: Cap & Co; Chartered Accountant: Kunal Savla. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in BADRIDHAM?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About BADRIDHAM. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save BADRIDHAM to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.