Home / Browse projects / Palghar, Maharashtra / AYAN RESIDENCY - PHASE - 1

Registration lapsed No litigation declared Residential / Group Housing project

AYAN RESIDENCY - PHASE - 1

By MAGNUM HOME MAKERS PVT. LTD.

RG-MH-25180 · RERA P99000006966 · Last updated on MahaRERA portal: 21 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 5 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
110 of 253Construction stages doneacross 23 buildings; furthest along: Internal walls, 99%
5Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

AYAN RESIDENCY - PHASE - 1 is a Residential / Group Housing project by MAGNUM HOME MAKERS PVT. LTD. in Palghar, Maharashtra, registered with MahaRERA as P99000006966 on 16 Aug 2017. Possession was promised by 30 Dec 2024 and is now 22 months past that date. 5 complaints are on record with the regulator.

At a glance

Project

  • NameAYAN RESIDENCY - PHASE - 1
  • TypeResidential / Group Housing
  • Location
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000006966
  • ReraGenie IDRG-MH-25180

Builder

  • NameMAGNUM HOME MAKERS PVT. LTD.
  • Entity typeCompany

Key dates

22 months past promisethis monthRegisteredAug 2017PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Aug 2017
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings23 building records
  • Documents filed74 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 1 - STILT TO 7TH FLOORNA80000
BUILDING 1 - 8TH TO 16TH FLOORSNA90000
BUILDING 2 - STILT TO 7TH FLOORSNA80000
BUILDING 2 - 8TH TO 16TH FLOORSNA90000
BUILDING 3 - STILT TO 7TH FLOORSNA80000
BUILDING 3 - 8TH TO 16TH FLOORSNA90000
BUILDING 4 - STILT TO 7TH FLOORSNA80000
BUILDING 4 - 8TH TO 16TH FLOORSNA90000
BUILDING 5 - STILT TO 7TH FLOORSNA80000
BUILDING 5 - 8TH TO 16TH FLOORSNA90000
BUILDING 6 - STILT TO 7TH FLOORSNA80000
BUILDING 6 - 8TH TO 16TH FLOORSNA90000
BUILDING 7 - STILT TO 7TH FLOORSNA80000
BUILDING 7 - 8TH TO 16TH FLOORSNA90000
BUILDING 8 - STILT TO 7TH FLOORSNA80000
BUILDING 8 - 8TH TO 16TH FLOORSNA90000
BUILDING 9 - STILT TO 7TH FLOORSNA80000
BUILDING 9 - 8TH TO 16TH FLOORSNA90000
BUILDING 10 - STILT TO 7TH FLOORSNA80000
BUILDING 10 - 8TH TO 16TH FLOORSNA90000
BUILDING 11 - STILT TO 7TH FLOORSNA80000
BUILDING 11 - 8TH TO 16TH FLOORSNA90000
BUILDING 23 -NA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 21 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 23 buildings; the table lists the first 20.

110 of 253 construction stages are filed complete across 23 buildings. The stage furthest along is Internal walls, at 99%.

BUILDING 1 - STILT TO 7TH FLOOR89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 1 - 8TH TO 16TH FLOORS66%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.54%
BUILDING 2 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 2 - 8TH TO 16TH FLOORS66%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
BUILDING 3 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 3 - 8TH TO 16TH FLOORS67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises7%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.66%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
BUILDING 4 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 4 - 8TH TO 16TH FLOORS67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.66%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
BUILDING 5 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 5 - 8TH TO 16TH FLOORS66%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
BUILDING 6 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 6 - 8TH TO 16TH FLOORS66%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
BUILDING 7 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 7 - 8TH TO 16TH FLOORS67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises7%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.66%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
BUILDING 8 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 8 - 8TH TO 16TH FLOORS67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises8%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.66%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
BUILDING 9 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 9 - 8TH TO 16TH FLOORS67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises8%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.66%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%
BUILDING 10 - STILT TO 7TH FLOORS89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
BUILDING 10 - 8TH TO 16TH FLOORS66%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.57%

Progress on shared amenities15

As on 21 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes4%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed121

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots121
Closed/Covered121
BuildingClosed/CoveredTotal
BUILDING 1 - 8TH TO 16TH FLOORS1111
BUILDING 2 - 8TH TO 16TH FLOORS1111
BUILDING 3 - 8TH TO 16TH FLOORS1111
BUILDING 4 - 8TH TO 16TH FLOORS1111
BUILDING 5 - 8TH TO 16TH FLOORS1111
BUILDING 6 - 8TH TO 16TH FLOORS1111
BUILDING 7 - 8TH TO 16TH FLOORS1111
BUILDING 8 - 8TH TO 16TH FLOORS1111
BUILDING 9 - 8TH TO 16TH FLOORS1111
BUILDING 10 - 8TH TO 16TH FLOORS1111
BUILDING 11 - 8TH TO 16TH FLOORS1111

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area42,196 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI38713.86
Proposed, not sanctioned18,529 sq m
Buildings approved23
Buildings sanctioned23

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDR NAIR ROAD OPP MUMBAI CENTRAL STATION MUMBAI - 400 008

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
MAGNUM HOME MAKERS PVT. LTD.-

Litigation declared2

CaseCourtStatus
1300844/2014VASAI COURT JMFCDISPOSED
1/2017VASAI COURT SESSION JUDGEDISPOSED

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000023033KAILASH CHAND AND PREMLATA DUSADMAGNUM HOME MAKERS PVT LTD21/01/2018
CC006000000196099Moosa Thakur HImtiyaz I Patel11/03/2021
CC006000000209540MOHAMMED FIROZ AHMED SHAIKHM/S. MAGNUM HOME MAKERS PVT LTD represented by promoter MR. IMTIYAZ IBRAHIM PATEL24/12/2021
CC006000000397460Samrin Nikhat ShaikhMagnum Home Markers Pvt Ltd12/09/2023
CC006000000397470Mohammed Anis ShaikhMagnum Home Makers Pvt Ltd12/09/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: dec 23.pdf21 Feb 2025
Certificates of CA (Form 3)File: dec 24.pdf21 Feb 2025
Certificates of CA (Form 3)File: sep 24.pdf21 Feb 2025
Certificates of CA (Form 3)File: june 24.pdf21 Feb 2025
Certificates of CA (Form 3)File: mar 24.pdf21 Feb 2025
Certificates of CA (Form 3)File: sep 23.pdf21 Feb 2025
Certificates of CA (Form 3)File: june 23.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: june 23.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: sep 23.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: dec 23.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: mar 24.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: jun 24.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: jun 24.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: sep 24.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: dec 24.pdf21 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AYAN ARCHITECT CERTIFICATE DT 30092023_compressed_compressed.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AYAN ARCHITECT CERTIFICATE DT 3122023_compressed.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AYAN ARCHITECT CERTIFICATE DT 31032024_compressed.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AYAN ARCHITECT CERTIFICATE DT 30062024_compressed.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 31122024.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 30-06-2023.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate 31-12-2024.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 30-06-2024.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-03-2024.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 31-12-2023.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate 30-09-2023.pdf6 Feb 2025
Declaration in FORM BFile: declaration - Copy 2_compressed.pdf18 Dec 2024
Declaration in FORM BFile: Declaration 1.pdf18 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate-1_compressed.pdf18 Dec 2024
Certificates of CA (Form 3)File: FORM 3 MAGNUM.pdf18 Dec 2024
Certificates of CA (Form 5)File: FORM-5.pdf18 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf18 Dec 2024
Form 2AFile: FARM-2-A.pdf18 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclousure of inventory_compressed (1).pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FARM-2-A.pdf18 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Ayan300922.pdf8 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Magnum Rera upto Sept 2022.pdf8 May 2023
Certificates of CA (Form 5)File: MHMPL_2018_19.pdf10 Apr 2023
Certificates of CA (Form 5)File: MHMPL_2019-20.pdf10 Apr 2023
Form 2AFile: Eng Certificate_Ayan_Res_2021 (1).pdf12 Dec 2022
Form 2AFile: Eng Certificate_Ayan_Res_2022 (1).pdf12 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 2021_compressed.pdf4 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate 2022_compressed.pdf4 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: mag_arch_1042020_1 (3).pdf21 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: mag_engg_10420_1.pdf21 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: magnum_arch_cert.pdf1 Feb 2020
Form 2AFile: ENGG_MAG_RERA.pdf29 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg_magnum_sept2019_compressed.pdf11 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Magnum_Arch_Cert_Sept2019 (3).pdf4 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARch_Ayan_C1.pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ayan_Engg_Cert_June19.pdf22 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch_Ayan.pdf17 Aug 2019
Form 2AFile: Engineer_Certificate_Ayan_Dt_10-04-2019-compressed.pdf17 Aug 2019
Form 2AFile: Magnum_form2-compressed.pdf29 Apr 2019
Form 2AFile: MHM CERT_compressed.pdf11 Mar 2019
Certificates of CA (Form 5)File: CA_Magnum.pdf11 Mar 2019
Proforma of Allotment letterFile: Draft-Agreement.pdf21 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate_1011--P1.pdf14 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate_1011__P2.pdf14 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_6112017.PDF14 Nov 2017
Layout approvalFile: LAYOUT APPROVED.pdf31 Jul 2017
Building plan approvalFile: NA NOC.pdf31 Jul 2017
Details of encumbrancesFile: dec non encumb.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT APPROVED.pdf31 Jul 2017
Building Plan Approval (IOD)File: NA NOC.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC-.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archc1.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERTIFICATE AYAN FORM 2.pdf31 Jul 2017
Certificates of CA (Form 3)File: ayan residency reduced.pdf31 Jul 2017
Proforma of Allotment letterFile: afs.pdf31 Jul 2017
OtherFile: annex-magnum.pdf31 Jul 2017
PAN CardFile: Magnum PAN Card.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate-magnum.pdf28 Jul 2017
Declaration in FORM BFile: form b.pdf28 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AYAN RESIDENCY - PHASE - 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vasai-Virar City (M Corp)3,200+ in Palghar

2 kmAYAN RESIDENCY - PHASE -Completed 43Lapsed / revoked 29Other 107Dot size: filed unitsN

Filed coordinates, straight-line distance. 179 registered projects within 2 km.

Builder: MAGNUM HOME MAKERS PVT. LTD.

MAGNUM HOME MAKERS PVT. LTD. has 1 registration on MahaRERA, including AYAN RESIDENCY - PHASE - 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that AYAN RESIDENCY - PHASE - 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AYAN RESIDENCY - PHASE - 1 is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AYAN RESIDENCY - PHASE - 1?

The registered promoter entity is MAGNUM HOME MAKERS PVT. LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AYAN RESIDENCY - PHASE - 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AYAN RESIDENCY - PHASE - 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AYAN RESIDENCY - PHASE - 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in AYAN RESIDENCY - PHASE - 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AYAN RESIDENCY - PHASE - 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AYAN RESIDENCY - PHASE - 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.