Home / Browse projects / Pune, Maharashtra / AVON VISTA PROJECT -1
AVON VISTA PROJECT -1
By NAIKNAVARE PROFILE CONSTRUCTIONS PVT LTD
RG-MH-09132 · RERA P52100000371 · Last updated on MahaRERA portal: 4 Oct 2023
Source: official MahaRERA filing
Red flags
- 5 complaints at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AVON VISTA PROJECT -1 is a Residential / Group Housing project by NAIKNAVARE PROFILE CONSTRUCTIONS PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100000371 on 15 Jul 2017. The registration is recorded completed; possession was promised by 29 Jun 2022. The completion date has moved by 18 months from the original filing. 5 complaints are on record with the regulator.
At a glance
Project
- NameAVON VISTA PROJECT -1
- TypeResidential / Group Housing
- Location
- PUNE
- Mahalunge
- Mulshi
- 410501
- Pincode410501
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100000371
- ReraGenie IDRG-MH-09132
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Jul 2017
- Promised completion29 Jun 2022
- Revised completionRevised to 29 Jun 2022 (originally 30 Dec 2020)
- Buildings3 building records
- Documents filed108 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1 BUILDING | NA | 24 | 0 | 0 | 0 | 0 |
| B1 BUILDING | NA | 24 | 0 | 0 | 0 | 0 |
| CLUB HOUSE | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 4 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
29 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.
A1 BUILDING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B1 BUILDING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
CLUB HOUSE64%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 4 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A1 BUILDING | 2 | 7 | 9 |
| B1 BUILDING | 2 | 7 | 9 |
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SYNERGY DEVELOPMENT CORPORATION PVT LTD | Pune (M Corp.) | Pune |
| HEMANT DATTAJI NAIKNAVARE | Pune (M Corp.) | Pune |
| SHRIKANT PURSHOTTAM PARANJAPE | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GAURI NAIKNAVARE |
| Engineer | KRUPALI KADAM |
| Partner | Role in project |
|---|---|
| NAIKNAVARE PROFILE CONSTRUCTIONS PVT LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have registered our project by the name “Avon Vista” (for Buildings A1, B1, Club house) bearing MAHARERA Registration No. P-52100000371. . The date of completion of the said project initially was 30.06.2020, which was then extended to 30.12.2020 due to the prevalent Covid-19 pandemic lock down, as per the guidelines of the Authority. It is pertinent to note that the Competent Authority i.e. PMRDA had issued the Commencement Certificate for the said Building with sanctioned Building Plan for 21 floors. Now though the said Building A1 is complete in all respect, the OC is pending only for the
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000085260 | Sameep Anand Bhogan | Anand Naiknavare | 01/03/2021 |
| CC005000000096043 | Nilesh Patil | NAIKNAVARE DEVELOPERS PVT LTD | 22/09/2021 |
| CC005000000096044 | Vaibhav Khamgaonkar | NAIKNAVRE DEVELOPS PVT LTD | 22/09/2021 |
| CC005000000096088 | Aditya Gosavi | NaikNavare Profile Construction Pvt Ltd | 04/10/2021 |
| CC005000000269451 | Amol Suryakant Gavhane | Naiknavare Profile constructions PVT LTD | 15/09/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Jun 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Dec 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 Jan 2023
Documents filed108
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Avon Vista Pro1.pdf | 4 Oct 2023 |
| Architect’s Certificate on Completion of Project (Form 4)File: Avon Vista Pro1 FORM 4 -ARCH CERTIFICATE- A1-B1-CLUBHOUSE.pdf | 10 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Avon Vista 1 - FY 31-03-2021.pdf | 15 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Avon Vista 1 FY 31-03-2022.pdf | 15 Feb 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AVON VISTA CLUB HOUSE COMPLETION CERTIFICATE 2019.pdf | 20 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Avon Vista A1,B1.pdf | 18 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AVON PRO 1 FORM 1 JUN SEPT 22.pdf | 14 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PRO 01 ARCH CERT 30042022.pdf | 4 May 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PROJ 01 ENGG CERT 15042022.pdf | 18 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PROJ 01 ARCH CERT 03012022.pdf | 6 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PROJ 01 ENGG CERT 03012022.pdf | 6 Jan 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Avon Vista Society Formation Certificate.pdf | 20 Dec 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Avon Vista A1 Bldg Compl.pdf | 8 Dec 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PROJ 01 ARCH CERT 02102021.pdf | 7 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PROJ 01 ENGG CERT 02102021.pdf | 7 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ca letter 2020-2021.pdf | 16 Aug 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PROJ 01 ENGG CERT 05082021.pdf | 11 Aug 2021 |
| Certificates of CA (Form 5)File: AvonVistaProject1.pdf | 9 Aug 2021 |
| Certificates of CA (Form 5)File: NPCPL_Project 1 Annexure.pdf | 9 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: AvonVistaProject1 2019-2020.pdf | 9 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PROJ 01 ARCH CERT 05082021.pdf | 6 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Certificate- Phase 1 2018-19.pdf | 28 Jul 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AVON VISTA B1 BLDG COMPLETION CERTIFICATE.pdf | 28 Jul 2021 |
| Layout approvalFile: Avon vista lower lvl parking.pdf | 9 Jun 2021 |
| Layout approvalFile: Avon vista sanction LAYOUT.pdf | 9 Jun 2021 |
| Layout approvalFile: Avon vista sanction layout1.pdf | 9 Jun 2021 |
| Layout approvalFile: Avon vista schmatic section.pdf | 9 Jun 2021 |
| Layout approvalFile: Avon vista upper lvl parking.pdf | 9 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: Avon vista lower lvl parking.pdf | 9 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: Avon vista sanction LAYOUT.pdf | 9 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: Avon vista sanction layout1.pdf | 9 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: Avon vista schmatic section.pdf | 9 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: Avon vista upper lvl parking.pdf | 9 Jun 2021 |
| OtherFile: Avon Vista- Society Registration Certificate.pdf | 30 Apr 2021 |
| OtherFile: AVON VISTA B1 BLDG COMPLETION CERTIFICATE 2020.pdf | 28 Apr 2021 |
| OtherFile: CHRONOLOGY.pdf | 28 Apr 2021 |
| OtherFile: avon vista.pdf | 28 Apr 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PROJ 01 ENGGCERT 27042021.pdf | 27 Apr 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PROJ 01 ARCH CERT 16042021.pdf | 19 Apr 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AVON VISTA A1 PART COMPLETION.pdf | 19 Apr 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AVON VISTA B1 BLDG COMPLETION CERTIFICATE 2020-compressed.pdf | 19 Apr 2021 |
| OtherFile: AVON VISTA A1 PART COMPLETION.pdf | 15 Apr 2021 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: A1-OC.pdf | 14 Apr 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Letter Avon Vista A1.pdf | 14 Apr 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PROJ 1 ENGG CERT 19012021.pdf | 19 Jan 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PROJ01 ARCH CERT 26062020.pdf | 7 Jul 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: PROJ01 ENGG CERT 26062020.pdf | 7 Jul 2020 |
| OtherFile: Water lifting Application.pdf | 21 Feb 2020 |
| OtherFile: Water lifting Application.pdf | 21 Feb 2020 |
| OtherFile: Nhai Bombay Office order for Avon Vista .pdf | 21 Feb 2020 |
| OtherFile: ELECTRICAL CONNECTION LINE.pdf | 21 Feb 2020 |
| Certificates of CA (Form 5)File: RERA Certificate Phase 1.pdf | 17 Feb 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch 1312020.pdf | 13 Jan 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng 1312020.pdf | 13 Jan 2020 |
| Building plan approvalFile: A1 BLDG RERA AREA.pdf | 26 Dec 2019 |
| Building plan approvalFile: B1 BLDG RERA AREA.pdf | 26 Dec 2019 |
| Building Plan Approval (IOD)File: A1 BLDG RERA AREA.pdf | 26 Dec 2019 |
| Building Plan Approval (IOD)File: B1 BLDG RERA AREA.pdf | 26 Dec 2019 |
| Proforma of Allotment letterFile: Index-II AVON VISTA PROJECT 1.pdf | 12 Nov 2019 |
| Proforma of Allotment letterFile: AVON VISTA AGREEMENT PROJECT 1.pdf | 12 Nov 2019 |
| OtherFile: CREDAINDPL MEM CERT 2020.pdf | 4 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT 15102019.pdf | 16 Oct 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGCERT 15102019.pdf | 16 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT PHASE1.pdf | 18 Jul 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERT PHASE1.pdf | 18 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH 19-4-19.pdf | 19 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG 19-4-19.pdf | 19 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch18119.pdf | 18 Jan 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng18119.pdf | 18 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arch16102018.pdf | 15 Oct 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng16102018.pdf | 15 Oct 2018 |
| Certificates of CA (Form 5)File: Naiknavareavon.pdf | 30 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHCERTIFICATEAVON.pdf | 16 Jul 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGCERTIFICATEAVON.pdf | 16 Jul 2018 |
| PAN CardFile: PAN npcpl.pdf | 25 May 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHCERTIFICATE2.pdf | 16 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGCERTIFICATE2.pdf | 16 Apr 2018 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER AND AGREEMENT TO SELL.pdf | 8 Feb 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Avon Vista-Architect Certificate 23june2017.pdf | 15 Jan 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGCERTIFICATE1512018.pdf | 15 Jan 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 108 filed documents as one ZIP, foldered, with a manifest
Keep AVON VISTA PROJECT -1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PUNE13,700+ in Pune
Filed coordinates, straight-line distance. 270 registered projects within 2 km.
DWARKA PROJECT3
NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD
SARA NILAAY
JAGRUTSARA STRUCTURES LLP
SARA CITY TOWER C3
JAGRUTSARA STRUCTURES LLP
SARA CITY TOWER C2
JAGRUTSARA STRUCTURES LLP
SARA SWAPNODAY
Jagrutsara Structures LLP
Aapla Ghar Moshi Annex Phase I
Maple Shelters Pvt. Ltd.
Builder: NAIKNAVARE PROFILE CONSTRUCTIONS PVT LTD
NAIKNAVARE PROFILE CONSTRUCTIONS PVT LTD has 2 registrations on MahaRERA, including AVON VISTA PROJECT -1 and AVON VISTA PROJECT 3. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if AVON VISTA PROJECT -1 is delayed beyond 29 Jun 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AVON VISTA PROJECT -1?
The registered promoter entity is NAIKNAVARE PROFILE CONSTRUCTIONS PVT LTD, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AVON VISTA PROJECT -1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AVON VISTA PROJECT -1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AVON VISTA PROJECT -1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AVON VISTA PROJECT -1?
The professionals named in the filing: Architect: GAURI NAIKNAVARE; Engineer: KRUPALI KADAM. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AVON VISTA PROJECT -1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback