Home / Browse projects / Mumbai Suburban, Maharashtra / Avenue Wing B phase 2

Registered No litigation declared Residential / Group Housing project

Avenue Wing B phase 2

By Dharmesh Constructions Private Limited

RG-MH-30364 · RERA P51800031398 · Last updated on MahaRERA portal: 3 Sep 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 48 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 0%
82 of 95Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 122 documents Report an error

Avenue Wing B phase 2 is a Residential / Group Housing project by Dharmesh Constructions Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031398 on 23 Oct 2021. Possession is promised by 31 Dec 2029. The completion date has moved by 48 months from the original filing. 13 of the 95 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAvenue Wing B phase 2
  • TypeResidential / Group Housing
  • Location
    • Bhabrekar road
    • Charkop gaon
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • RERA no.P51800031398
  • ReraGenie IDRG-MH-30364

Builder

  • NameDharmesh Constructions Private Limited
  • Entity typeCompany
  • ChairpersonMunish Pravin Doshi
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live3 lapsed, de-registered or revoked

Key dates

this monthRegisteredOct 2021First promiseDec 2025Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2021
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed122 files

Current status

14%13 of 95 units booked
2.2%Work done, per cost certificate

Figures as on 3 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Avenue Wing B phase 2NA151495095

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 0%.

Avenue Wing B phase 2: 45% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed95

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots95
Closed/Covered95

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area698 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI14973.96
Proposed, not sanctioned7,564 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGanga jamna apts, gr floor opp to shoppers stop, S V road andheri west
Estimated costRs 32.61 cr
Cost incurredRs 72.44 lakh
Work done2.22%
BuildingWingEstimatedIncurred
Avenue Wing B phase 2NARs 26.09 cr-
-NARs 6.52 crRs 72.44 lakh

Certifying professionals and partners11

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr.MUKESH BAHADUR of Consultants combined
ArchitectPankaj Kumaria
ArchitectMr.RAJESH ATHA
EngineerSACPL Mr Nikhil Sanghvi
EngineerKiran Dadasaheb Mulik
EngineerSACPL, Mr Nikhil sanghvi.
EngineerSameer Kadam
Chartered AccountantA T JAIN AND CO
Chartered AccountantS. N. Katdare & Co.
Chartered AccountantManoj Shah
Chartered AccountantChampak K. Dedhia
PartnerRole in project
Dharmesh Constructions Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20082622273Dec 2025 → Dec 2029

Reason as filed by the promoter• 29 Months - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months - Till Date 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate them as per 33(38) provision of Slum Act which is to vacate their respective premises for the purpose of demolition so that further work for the project can commence, hence we have initiated 33(38) proceedings in SRA on 23/10/2018 and obtained order against few non-cooperating members on 13/03/2019. Although, in 13/03/2019 we received notice, we had to take approval

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12502301Rahul Anand PalkarDharmesh Constructions Private Limited08/07/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed122

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 122 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Mar 2026.pdf3 Sep 2026
Withdrawal Update Form 1File: Form 1 - Avenue Wing B Ph 2 - Jun 2026.pdf3 Sep 2026
Withdrawal Update Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Mar 2026.pdf3 Sep 2026
Withdrawal Update Form 2File: Form-2 Avenue Wing B Ph 2 - FY-Jun 2026.pdf3 Sep 2026
Withdrawal Update Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Mar 2026.pdf3 Sep 2026
Withdrawal Update Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Jun 2026.pdf3 Sep 2026
Form 2A (FY 2023-2024)File: Form 2A - Avenue Wing B Phase 2 - FY 2023-24.pdf19 Aug 2026
Form 2A (FY 2021-2022)File: Form 2A - Avenue Wing B Phase 2 - FY 2021-22.pdf19 Aug 2026
Form 2A (FY 2022-2023)File: Form 2A - Avenue Wing B Phase 2 - FY 2022-23.pdf19 Aug 2026
Form 2A (FY 2024-2025)File: Form 2A - Avenue Wing B Phase 2 - FY 2024-25.pdf19 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A - Avenue Wing B Phase 2 - FY 2025-26.pdf19 Aug 2026
Withdrawal Update Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Jun 2025.pdf13 Aug 2026
Withdrawal Update Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Sep 2025.pdf13 Aug 2026
Withdrawal Update Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Dec 2025.pdf13 Aug 2026
Withdrawal Update Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Jun 2025 with Declaration.pdf13 Aug 2026
Withdrawal Update Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Sep 2025 with Declaration.pdf13 Aug 2026
Withdrawal Update Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Dec 2025 with Declaration.pdf13 Aug 2026
Withdrawal Update Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Jun 2025.pdf13 Aug 2026
Withdrawal Update Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Sep 2025.pdf13 Aug 2026
Withdrawal Update Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Dec 2025.pdf13 Aug 2026
Form 5 (FY 2022-2023)File: Form 5 - Avenue Wing B Ph2 - FY 2022-23.pdf13 Aug 2026
Form 5 (FY 2023-2024)File: Form 5 - Avenue Wing B Ph2 - FY 2023-24.pdf13 Aug 2026
Form 5 (FY 2024-2025)File: Form 5 - Avenue Wing B Ph2 - FY 2024-25.pdf13 Aug 2026
Withdrawal Update Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Mar 2025.pdf22 Jul 2026
Withdrawal Update Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Mar 2025.pdf22 Jul 2026
Withdrawal Update Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Mar 2025.pdf22 Jul 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Jun 2024.pdf17 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Jun 2024.pdf17 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Jun 2024.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - June 2024.pdf17 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Sep 2024.pdf17 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Sep 2024.pdf17 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Sep 2024.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Sept 2024.pdf17 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Dec 2024.pdf17 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Dec 2024.pdf17 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Dec 2024.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Dec 2024.pdf17 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Mar 2025.pdf17 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Mar 2025.pdf17 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Mar 2025.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - March 2025.pdf17 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Mar 2022.pdf15 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Mar 2022.pdf15 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Mar 2022.pdf15 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - March 2022.pdf15 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Sep 2022.pdf15 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Sep 2022.pdf15 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Sep 2022.pdf15 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Sept 2022.pdf15 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Dec 2022.pdf15 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Dec 2022.pdf15 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Dec 2022.pdf15 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Dec 2022.pdf15 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Jun 2023.pdf15 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Jun 2023.pdf15 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Jun 2023.pdf15 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - June 2023.pdf15 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Sep 2023.pdf15 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Sep 2023.pdf15 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Sep 2023.pdf15 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Sept 2023.pdf15 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Dec 2023.pdf15 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Dec 2023.pdf15 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Dec 2023.pdf15 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Dec 2023.pdf15 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Mar 2024.pdf15 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Mar 2024.pdf15 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Mar 2024.pdf15 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - March 2024.pdf15 Jun 2026
Form 1File: Form-1 Avenue Wing B Ph-2 - FY-Dec 2021.pdf4 Jun 2026
Form 2File: Form-2 Avenue Wing B Ph-2 - FY-Dec 2021.pdf4 Jun 2026
Form 3File: Form-3 Avenue Wing B Ph-2 - FY-Jun 2021.pdf4 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Unsold Inventory - Dec 2021.pdf4 Jun 2026
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-AVENUE WING B Ph 2 - Dec 2021.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-AVENUE WING B Ph 2 - March 2022.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Avenue Wing B Ph2 - June 2022.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Avenue Wing B Ph2 - Sep 2022.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Avenue Wing B Ph2 - Dec 2022.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Avenue Wing B Ph2 - March 2023.pdf26 Oct 2023

How this compares with Mumbai Suburban

14%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Avenue Wing B phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Charkop gaon6,700+ in Mumbai Suburban

Builder: Dharmesh Constructions Private Limited

Dharmesh Constructions Private Limited has 6 registrations on MahaRERA, including AVENUE WING B and AVENUE WING A. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Avenue Wing B phase 2 is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Avenue Wing B phase 2?

The registered promoter entity is Dharmesh Constructions Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Avenue Wing B phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Avenue Wing B phase 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Avenue Wing B phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Avenue Wing B phase 2?

The professionals named in the filing: Architect: Mr.MUKESH BAHADUR of Consultants combined; Architect: Pankaj Kumaria; Architect: Mr.RAJESH ATHA; Engineer: SACPL Mr Nikhil Sanghvi; Engineer: Kiran Dadasaheb Mulik; Engineer: SACPL, Mr Nikhil sanghvi.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Avenue Wing B phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Avenue Wing B phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Avenue Wing B phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.