Home / Browse projects / Satara, Maharashtra / AVDHOOT PLAZA
AVDHOOT PLAZA
RG-MH-27557 · RERA P52700034313 · Last updated on MahaRERA portal: 15 Apr 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AVDHOOT PLAZA is a Residential / Group Housing project by MUKESH BALASAHEB KOLEKAR in Satara, Maharashtra, registered with MahaRERA as P52700034313 on 30 Mar 2022. Possession is promised by 31 Dec 2027.
At a glance
Project
- NameAVDHOOT PLAZA
- TypeResidential / Group Housing
- Location
- KALAJ TADWALE ROAD
- KALAJ
- Phaltan
- Satara
- 415528
- Pincode415528
- RERA no.P52700034313
- ReraGenie IDRG-MH-27557
Builder
- NameMUKESH BALASAHEB KOLEKAR
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on30 Mar 2022
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed25 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AVDHOOT PLAZA | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 15 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
AVDHOOT PLAZA: 18% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MAYUR GANDHI |
| Engineer | MUKESH KOLEKAR |
| Chartered Accountant | VITTHAL JADHAV |
| Partner | Role in project |
|---|---|
| MUKESH BALASAHEB KOLEKAR | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed25
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mukesh Kolekar Mar 24.pdf | 15 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate - Avdhooth Plaza 31032024.pdf | 15 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Avdhoot Plaza Form 5 31032023.pdf | 7 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate - Avdhooth Plaza 30062023.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate - Avdhooth Plaza 30092023.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Certificate - Avdhooth Plaza 31122023.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mukesh Kolekar Jun 23.pdf | 11 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mukesh Kolekar Sep 23.pdf | 11 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mukesh Kolekar Dec 23.pdf | 11 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 22.pdf | 24 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 22.pdf | 19 Aug 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Avdhoot Plaza 3.pdf | 23 Mar 2022 |
| PAN CardFile: PAN.pdf | 22 Mar 2022 |
| Copy of the legal title reportFile: Legal Search Decalaration.pdf | 17 Mar 2022 |
| Building plan approvalFile: Building Plan.pdf | 12 Mar 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan.pdf | 12 Mar 2022 |
| Proforma of Allotment letterFile: Agreement to salE aVDHOOT pLAZ.pdf | 12 Mar 2022 |
| Layout approvalFile: Lay out.pdf | 9 Mar 2022 |
| Copy of the legal title reportFile: Legal Search.pdf | 9 Mar 2022 |
| Details of encumbrancesFile: Non encumbrance.pdf | 9 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Lay out.pdf | 9 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 9 Mar 2022 |
| Declaration about Commencement CertificateFile: Decalaration commencement.pdf | 9 Mar 2022 |
| Declaration in FORM BFile: Form B.pdf | 9 Mar 2022 |
| CERSAI detailsFile: CERSAI.pdf | 9 Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 25 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep AVDHOOT PLAZA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KALAJ1,100+ in Satara
Surwadi Park
Surawadi Park
VEDANTA LIFE SPACES - I
OM SHAKTI ASSOCIATES
SURWADI PARK
SURAWADI PARK
PRADHAN MANTRI AWAS YOJANA SATARA PHASE I
SATARA MUNICIPAL COUNCIL SATARA
LANDMARK TOWERS
KANGRALKAR INFRASTRUCTURE
Dois Hill
Vinay Ashok Chugera
See every Satara project, with the district possession charts
Builder: MUKESH BALASAHEB KOLEKAR
MUKESH BALASAHEB KOLEKAR has 1 registration on MahaRERA, including AVDHOOT PLAZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What are my rights if AVDHOOT PLAZA is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AVDHOOT PLAZA?
The registered promoter entity is MUKESH BALASAHEB KOLEKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AVDHOOT PLAZA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for AVDHOOT PLAZA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AVDHOOT PLAZA?
The professionals named in the filing: Architect: MAYUR GANDHI; Engineer: MUKESH KOLEKAR; Chartered Accountant: VITTHAL JADHAV. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AVDHOOT PLAZA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback