Home / Browse projects / Raigarh, Maharashtra / AVANTE

Registration lapsed No litigation declared Residential / Group Housing project

AVANTE

By SWARAJ MEGA STRUCTURE PRIVATE LIMITED

RG-MH-71435 · RERA P52000016411 · Last updated on MahaRERA portal: 13 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 72 months
  • 7 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
26 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 98%
50 of 232Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 97 documents Report an error

AVANTE is a Residential / Group Housing project by SWARAJ MEGA STRUCTURE PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000016411 on 10 May 2018. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 72 months from the original filing. 182 of the 232 units on this registration are recorded sold or booked, and 26 of 44 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAVANTE
  • TypeResidential / Group Housing
  • Location
    • OPP SWAPN NAGRI
    • PANVEL
    • Vakadi
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000016411
  • ReraGenie IDRG-MH-71435

Builder

  • NameSWARAJ MEGA STRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsAMOL SAKHARAM PACHPUTE, RIYA RAJ KANDHARI

Key dates

10 months past promisethis monthRegisteredMay 2018First promiseDec 2019Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 May 2018
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2019)
  • Buildings4 building records
  • Documents filed97 files

Current status

78%182 of 232 units booked

Figures as on 13 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA5480080
BUILDING BNA5424024
BUILDING CNA5472072
BUILDING DNA5456056

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 13 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

26 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 98%.

BUILDING A85%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%
BUILDING B84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.30%
BUILDING C92%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
BUILDING D90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.58%

Progress on shared amenities15

As on 13 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes40%
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes40%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed67

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots67
Closed/Covered4
Open Space63
BuildingClosed/CoveredOpen SpaceTotal
BUILDING A11516
BUILDING B178
BUILDING C12021
BUILDING D12122

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,170 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCity and Industrial Development Corporation of Maharashtra
Permissible FSI13798.03
Proposed, not sanctioned13,798 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVASHI, SECTOR-17, NAVI MUMBAI - 400 703

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTOPATI DESIGN GROUP
EngineerHrushikesh Vilas Mindhe
Chartered AccountantCA Rutuja Narsingh & Associates
PartnerRole in project
SWARAJ MEGA STRUCTURE PRIVATE LIMITED-

Extensions applied for7

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000009875Dec 2019 → Dec 2022

Reason as filed by the promoterProject was delayed due to death of both the initial directors who were handling the project. Further there is sudden death of one of the newly appointed directors of the company and also there is petition filed by the promoter of the company in court for sale permission of flats as shares of the company was in the name of minor children of the deceased directors. This proceeding is in progress before the court and it will take some time. Afterwards, when things are getting normalised then pandemic situation of COVID-19 arises, so project was delayed because of lockdown and travel restrictions

EXT52000013496Dec 2019 → Jun 2023

Reason as filed by the promoterAS PER ATTACHED LETTER OF EXTENSION.

EXT52000001516Dec 2019 → Dec 2020

Reason as filed by the promoterDUE TO DEATH OF ONE KEY DIRECTOR, PROJECT EXTENSION APPLICATION HAS BEEN DONE.

EXT52000017100Dec 2019 → Jul 2023

Reason as filed by the promoterAS PER FORM-B.

EXT52000017261Dec 2019 → Dec 2023

Reason as filed by the promoterAS PER AFFIDAVIT

EXT52000018757Dec 2019 → Jun 2024

Reason as filed by the promoterAs Per Application For Extension Attached

EXT52000024312Dec 2019 → Dec 2025

Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P52000016411. we have attached the Order for the same from MahaRERA.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000303675Sushil JainSwaraj Megha Structure Pvt. Ltd.14/12/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed97

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCH CERTIFICATE June 24.pdf13 Jan 2026
Withdrawal Update Form 2File: FORM-2-June 24.pdf13 Jan 2026
Withdrawal Update Form 3File: FORM-3 June 24.pdf13 Jan 2026
Form 1File: Form 1 Sept 2025.pdf16 Oct 2025
Form 2File: Form 2 Sept 2025.pdf16 Oct 2025
Form 3File: Form 3 Sept 2025_.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: Information Of Sold Booked Inventory.pdf16 Oct 2025
Certificates of CA (Form 3)File: Form 3 - Avante as on March 2025.pdf19 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Avante as on March 2025.pdf19 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf27 Mar 2025
Certificates of CA (Form 3)File: Form 3 - Avante as on Dec 2024.pdf20 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Avante as on Dec 2024.pdf20 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE Mar 24.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTIFICATE June 24.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2- Mar 24.pdf17 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2-June 24.pdf17 Jul 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR-29.pdf17 Jul 2024
Certificates of CA (Form 3)File: FORM-3 Mar 24.pdf17 Jul 2024
Certificates of CA (Form 3)File: FORM-3 June 24.pdf17 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5.pdf17 Jul 2024
Declaration in FORM BFile: Affidavit - Form B.pdf20 Jan 2024
Certificates of CA (Form 3)File: FORM 3 Swaraj Mega.pdf20 Jan 2024
Declaration in FORM BFile: Affidavit - Form B.pdf16 Jan 2024
Declaration in FORM BFile: Affidavit - Form B 02.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE Form 2.pdf10 Jan 2024
Certificates of CA (Form 3)File: Form 3 Swaraj Mega Structure.pdf9 Jan 2024
Details of encumbrancesFile: Non Encumbrance Certificate.pdf8 Jan 2024
Declaration in FORM BFile: Affidavit - Form B 01.pdf8 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Signed 01.pdf8 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold and Booked Inventory 01.pdf8 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest-Annexure-A.pdf8 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration-Seperate Bank Account.pdf8 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-FY 22-23-Swaraj Mega Structure Pvt Ltd.pdf4 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1-ARCHITECT CERTIFICATE Compressed.pdf25 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE Compresseed.pdf25 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE.pdf25 Aug 2023
Certificates of CA (Form 3)File: FORM-3 Compressed.pdf25 Aug 2023
Certificates of CA (Form 3)File: Form 3 - Compressed.pdf21 Aug 2023
Details of encumbrancesFile: NON ENCUMBRANCE CERTIFICATE.pdf5 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architects Certificate.pdf5 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf5 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUALITY ASSURANCE CERTIFICATE.pdf5 Aug 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD N UNSOLD FLATS.pdf5 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION FOR SEPERATE BANK ACCOUNT.pdf5 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER Certificate Rera.pdf17 Jul 2023
Details of encumbrances concerned to FinanceFile: Non Encumbrance Certificate.pdf10 Jul 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance Certificate.pdf10 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate Form No 1.pdf10 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Flats.pdf10 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf10 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for separate Bank Account.pdf10 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report.pdf19 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-FY 21-22-Swaraj Mega Structure Pvt Ltd.pdf19 Jan 2023
Deviation Report with respect to Allotment letterFile: No Deviation Report.pdf19 Jan 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation Report.pdf19 Jan 2023
Details of encumbrances concerned to FinanceFile: No Encumbrances Certificate.pdf13 Jan 2023
Details of encumbrances concerned to LegalFile: No Encumbrances Certificate.pdf13 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate.pdf13 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Diclosure of Interest.pdf13 Jan 2023
Proforma of Agreement for saleFile: Agreement_for_Sale.pdf13 Jan 2023
Proforma of Allotment letterFile: Allotment_letter.pdf13 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account details including no encumbrances.pdf13 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf2 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf2 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold flats.pdf2 Jan 2023
Certificates of CA (Form 3)File: Form 3.pdf2 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold_ booked inventory.pdf7 Sep 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Details circuler 29.pdf20 Aug 2021
Declaration about Commencement CertificateFile: mega cc letter.pdf24 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf24 Jul 2021
OtherFile: SOLD UNSOLD (3).pdf24 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: Ammended CC-NEW.pdf25 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archt Certificate Avvante (2).pdf25 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality certificate - avante -final.pdf25 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality certificate - avante -final.pdf25 Jun 2021
Disclosure of sold/ booked inventoryFile: sold unsold details.pdf25 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Swaraj Mega 18-19.pdf25 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Swaraj Mega 19-20.pdf25 Jun 2021
OtherFile: sold unsold details.pdf25 Jun 2021

How this compares with Raigarh

78%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 72 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AVANTE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PANVEL5,900+ in Raigarh

2 kmAVANTECompleted 3Lapsed / revoked 2Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 33 registered projects within 2 km.

Builder: SWARAJ MEGA STRUCTURE PRIVATE LIMITED

SWARAJ MEGA STRUCTURE PRIVATE LIMITED has 1 registration on MahaRERA, including AVANTE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that AVANTE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AVANTE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AVANTE?

The registered promoter entity is SWARAJ MEGA STRUCTURE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AVANTE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AVANTE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AVANTE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AVANTE?

The professionals named in the filing: Architect: VASTOPATI DESIGN GROUP; Engineer: Hrushikesh Vilas Mindhe; Chartered Accountant: CA Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AVANTE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AVANTE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AVANTE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.