ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Avalon - Tower B

Registered No litigation declared Residential / Group Housing project

Avalon - Tower B

By V HOTELS LTD

RG-MH-31335 · RERA P51800079669 · Last updated on MahaRERA portal: 23 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 650.00 crore secured on the land, in favour of V HOTELS LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 39%
8 of 13Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

Avalon - Tower B is a Residential / Group Housing project by V HOTELS LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800079669 on 20 Mar 2025. Possession is promised by 30 Sep 2028. 5 of the 13 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameAvalon - Tower B
  • TypeResidential / Group Housing
  • Location
    • Juhu
    • Andheri
    • Mumbai Suburban
    • 400049
  • Pincode400049
  • RERA no.P51800079669
  • ReraGenie IDRG-MH-31335

Builder

  • NameV HOTELS LTD
  • Entity typeCompany
  • CINU55204MH2000PLC128527
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • WtdPIYUSH VORA
  • Other registrations2 more →

Key dates

this monthRegisteredMar 2025PromisedSep 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Mar 2025
  • Promised completion30 Sep 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed60 files

Current status

38%5 of 13 units booked
22.5%Work done, per cost certificate

Figures as on 23 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Composite Building - Sale Wing BNA171313013

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 39%.

Composite Building - Sale Wing B: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure39%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed26

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots26
Closed/Covered26

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,235 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofV HOTELS LIMITED
Secured amountRs 650.00 crore
CERSAI search filedYes
Declared on19 Nov 2025

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI14963.76
Proposed, not sanctioned13,603 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch.5 C/ II, MITTAL COURT,224, NARIMAN POINT,MUMBAI - 400 021
Estimated costRs 272.41 cr
Cost incurredRs 61.34 cr
Work done22.52%
BuildingWingEstimatedIncurred
Composite Building - Sale Wing BNARs 177.07 crRs 39.87 cr
-NARs 95.34 crRs 21.47 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVilas Desai & Associates
ArchitectPradeepmkamble and associates
EngineerK C Shah Consultants
EngineerVinayak Thukrul
EngineerMEHUL KAIVANT SHAH
Chartered AccountantChirag Sarvaiya & Co
Chartered AccountantM S K A & Associates
Chartered AccountantChirag Sarvaiya
PartnerRole in project
V HOTELS LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jan 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2028

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A - Avalon - Tower B - P51800079669.pdf23 Jun 2026
Withdrawal Update Form 1File: Form-1 Avalon B Dec-25.pdf20 Apr 2026
Withdrawal Update Form 2File: Avalon B Form 2.pdf20 Apr 2026
Withdrawal Update Form 3File: Avalon B Form-3.pdf20 Apr 2026
Withdrawal Update Form 1File: Form-1 Avalon B Dec-25.pdf23 Jan 2026
Withdrawal Update Form 2File: Avalon B Form 2.pdf23 Jan 2026
Withdrawal Update Form 3File: Avalon B Form-3.pdf23 Jan 2026
Form 1File: Avlon B-Form 1-Sep-25.pdf27 Oct 2025
Form 2File: Avalon Tower B - Form 2.pdf27 Oct 2025
Form 3File: Avalon Tower B Form 3.pdf27 Oct 2025
Disclosure of Sold and Booked InventoryFile: Avalon Tower B Sold Unsold-scan.pdf27 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 - P51800079669 - Avalon Tower B.pdf13 Oct 2025
Form 1File: Avalon Tower B - Form1 - June 25.pdf18 Jul 2025
Form 2File: Form 2 - Avalon B- June-25.pdf18 Jul 2025
Form 3File: Form 3_Avalon Tower B - June 25 F.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold_Avalon Tower B- june-25.pdf18 Jul 2025
Form 1File: Form 1 Avalon Tower B - Mar-25.pdf2 Jun 2025
Form 2File: Declaration Form 2 Mar-25 Avalon B.pdf2 Jun 2025
Form 3File: Declaration Form 3 Mar-25 Avalon B.pdf2 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Avalon B- Mar-25.pdf2 Jun 2025
Building plan approvalFile: 2025 01 13 - Juhu- IOA Letter With Plan sheet no 06 - Compress - A to E - Basement.pdf18 Mar 2025
Building plan approvalFile: 2025 01 13 - Juhu- IOA Letter With Plan sheet no 08 - Compress - A to E - Lower Ground Flo18 Mar 2025
Building plan approvalFile: 2025 01 13 - Juhu- IOA Letter With Plan sheet no 10 - Compress - A to E - Upper Ground and18 Mar 2025
Building plan approvalFile: 2025-01-13 - Juhu- IOA Letter With Plan sheet no 28 - Compress - Section - B C D No 4.pdf18 Mar 2025
Building plan approvalFile: 2025-01-13 - Juhu- IOA Letter With Plan sheet no 15 - Compress - B - 1 to 5 7 9 11 - No 1.18 Mar 2025
Building plan approvalFile: 2025-01-13 - Juhu- IOA Letter With Plan sheet no 16 - Compress - B - 6 8 10 12 - No 2.pdf18 Mar 2025
Building plan approvalFile: 2025-01-13 - Juhu- IOA Letter With Plan sheet no 17 - Compress - B - 13 - No 3.pdf18 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 0953_001_merged.pdf18 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025-01-13 - Juhu- IOA Letter With Plan sheet no 15 - Compress - B - 1 to 5 7 9 11 - No 1.18 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025-01-13 - Juhu- IOA Letter With Plan sheet no 17 - Compress - B - 13 - No 3.pdf18 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025-01-13 - Juhu- IOA Letter With Plan sheet no 16 - Compress - B - 6 8 10 12 - No 2.pdf18 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025 01 13 - Juhu- IOA Letter With Plan sheet no 10 - Compress - A to E - Upper Ground and18 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025 01 13 - Juhu- IOA Letter With Plan sheet no 08 - Compress - A to E - Lower Ground Flo18 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025 01 13 - Juhu- IOA Letter With Plan sheet no 06 - Compress - A to E - Basement.pdf18 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: 2025-01-13 - Juhu- IOA Letter With Plan sheet no 28 - Compress - Section - B C D No 4.pdf18 Mar 2025
Declaration in FORM BFile: Avalon Tower B.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Feb 2025
Proforma of Agreement for saleFile: AFS for Avalon B FianllyF.pdf18 Feb 2025
Disclosure for secured/unsecured finance availed for the projectFile: Secured Unsecred.pdf18 Feb 2025
Layout approvalFile: Juhu- Amended IOA Layout Plan for RERA Wing B.pdf29 Jan 2025
PAN CardFile: 1 PAN Card (11).pdf29 Jan 2025
Copy of the legal title reportFile: the legal title report.pdf29 Jan 2025
Details of encumbrances concerned to FinanceFile: Finance Encumbrance.pdf29 Jan 2025
Details of encumbrances concerned to FinanceFile: Legal Encum.pdf29 Jan 2025
Copy of Layout Approval (in case of layout)File: Juhu- Amended IOA Layout Plan for RERA Wing B.pdf29 Jan 2025
Proforma of Allotment letterFile: Allotment Letter Avalon B.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: New Form 2 V Hotel.pdf29 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: 1 Commencement Certificates _ NA Order for plotted development (10).pdf29 Jan 2025
Other - LegalFile: 1 Other - Legal (4).pdf29 Jan 2025
Declaration about Commencement CertificateFile: Format D.pdf29 Jan 2025
CERSAI detailsFile: Cersai Declara.pdf29 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format - A.pdf29 Jan 2025
Deviation Report with respect to Allotment letterFile: Finally - Allotment Letter Deviation Sheet Avalon B.pdf29 Jan 2025
Details of encumbrances concerned to LegalFile: Finance Encumbrance.pdf29 Jan 2025
Details of encumbrances concerned to LegalFile: Legal Encum.pdf29 Jan 2025
Other - TechnicalFile: Order 50.pdf29 Jan 2025
Deviation Report with respect to model copy of AgreementFile: AFS devation - Final Avalon B.pdf29 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations (15).pdf29 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Declaration - Format B.pdf29 Jan 2025

How this compares with Mumbai Suburban

38%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Avalon - Tower B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Juhu6,700+ in Mumbai Suburban

Builder: V HOTELS LTD

V HOTELS LTD has 3 registrations on MahaRERA, including Avalon - Tower A and Avalon - Tower B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Avalon - Tower B is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Avalon - Tower B?

The registered promoter entity is V HOTELS LTD, a company as per the filing. Its CIN U55204MH2000PLC128527 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Avalon - Tower B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Avalon - Tower B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Avalon - Tower B?

The professionals named in the filing: Architect: Vilas Desai & Associates; Architect: Pradeepmkamble and associates; Engineer: K C Shah Consultants; Engineer: Vinayak Thukrul; Engineer: MEHUL KAIVANT SHAH; Chartered Accountant: Chirag Sarvaiya & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Avalon - Tower B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Avalon - Tower B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Avalon - Tower B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.