Home / Browse projects / Nagpur, Maharashtra / ATHARVA RESIDENCY
ATHARVA RESIDENCY
By MAYTAS INFRAVENTURES PRIVATE LIMITED
RG-MH-23398 · RERA P50500078710 · Last updated on MahaRERA portal: 23 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ATHARVA RESIDENCY is a Residential / Group Housing project by MAYTAS INFRAVENTURES PRIVATE LIMITED in Nagpur, Maharashtra, registered with MahaRERA as P50500078710 on 7 Jan 2025. Possession is promised by 31 Dec 2028. 77 of the 102 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete.
At a glance
Project
- NameATHARVA RESIDENCY
- TypeResidential / Group Housing
- Location
- NARSALA ROAD
- NARSALA
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440034
- Pincode440034
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500078710
- ReraGenie IDRG-MH-23398
Builder
- NameMAYTAS INFRAVENTURES PRIVATE LIMITED
- Entity typeCompany
- CINU45309MH2022PTC393704
- GSTIN27AAQCM3616D1ZG
- DirectorsAtul Namdeorao Shrirao, Narendra Shankarrao Mallelwar
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Jan 2025
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings2 building records
- Documents filed66 files
Current status
Figures as on 23 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING B | NA | 11 | 11 | 90 | 0 | 90 |
| WING A | NA | 2 | 2 | 6 | 6 | 12 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Plinth, at 60%.
WING B9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
WING A28%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 60% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 55% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 35% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed165
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING B | 79 | 62 | 141 |
| WING A | 21 | 3 | 24 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING B | NA | Rs 16.80 cr | Rs 7.50 cr |
| WING A | NA | Rs 15.36 cr | - |
| - | NA | Rs 50.00 lakh | Rs 3.50 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Alok Lunia |
| Engineer | Nakul Parbat |
| Engineer | Atul Namdeorao Shrirao |
| Chartered Accountant | Vijay Shankarrao Gulhane |
| Chartered Accountant | A.A. Virani & Associates |
| Partner | Role in project |
|---|---|
| MAYTAS INFRAVENTURES PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Oct 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Nov 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 JAN TO MARCH.pdf | 23 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 JAN TO MARCH.pdf | 23 Jun 2026 |
| Withdrawal Update Form 2File: FORM2 JAN TO MARCH.pdf | 23 Jun 2026 |
| Withdrawal Update Form 2File: FORM2 JAN TO MARCH.pdf | 23 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 JAN TO MARCH_compressed.pdf | 23 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 JAN TO MARCH_compressed.pdf | 23 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 JAN TO MARCH.pdf | 16 Jun 2026 |
| Withdrawal Update Form 2File: FORM2 JAN TO MARCH.pdf | 16 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 JAN TO MARCH_compressed.pdf | 16 Jun 2026 |
| Withdrawal Update Form 1File: form 1 dec 2025.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: form 2 dec 2025.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: form 3 dec 2025.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 3 Oct 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 3 Oct 2025 |
| Withdrawal Update Form 3File: FORM 3.pdf | 3 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1.pdf | 1 Oct 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 1 Oct 2025 |
| Withdrawal Update Form 3File: FORM 3.pdf | 1 Oct 2025 |
| Withdrawal Update Form 1File: FORM 1.pdf | 23 Jul 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 23 Jul 2025 |
| Withdrawal Update Form 3File: FORM 3.pdf | 23 Jul 2025 |
| Form 1File: FORM 1 OF 31-3-25.pdf | 11 Jun 2025 |
| Form 2File: FORM 2 OF 31-3-25.pdf | 11 Jun 2025 |
| Form 3File: FORM 3 OF 31-3-25.pdf | 11 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY 31-3-25.pdf | 11 Jun 2025 |
| Self-declaration of Quarterly ProgressFile: self declaration.pdf | 11 Jun 2025 |
| FORM 1 4TH QUARTER 2024 | 29 Apr 2025 |
| FORM 1 1ST QUARTER 2025 | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 4TH QUARTER 2024.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 1ST QUARTER 2025.pdf | 29 Apr 2025 |
| FORM 2 4TH QUARTER 2024 | 29 Apr 2025 |
| FORM 2 1ST QUARTER 2025 | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL MAYTAS Form 3.pdf | 26 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: utilisation certificate.pdf | 19 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: FINAL secured unsecured finance availed for the project_compressed.pdf | 19 Dec 2024 |
| Layout approvalFile: BUILDING PLAN (1) (8)-pages-3.pdf | 29 Nov 2024 |
| Layout approvalFile: BUILDING PLAN (1) (8)-pages-2.pdf | 29 Nov 2024 |
| Layout approvalFile: BUILDING PLAN (1) (8)-pages-1.pdf | 29 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: 1 a Details of encumbrances concerned to Finance_page-0001-output.pdf | 29 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: BUILDING PLAN (1) (8)-pages-1.pdf | 29 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: BUILDING PLAN (1) (8)-pages-2.pdf | 29 Nov 2024 |
| Copy of Layout Approval (in case of layout)File: BUILDING PLAN (1) (8)-pages-3.pdf | 29 Nov 2024 |
| Declaration in FORM BFile: affidavit.pdf | 29 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Verification Mail.pdf | 29 Nov 2024 |
| Details of encumbrances concerned to LegalFile: 1 a Details of encumbrances concerned to Finance_page-0001-output.pdf | 29 Nov 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B.pdf | 29 Nov 2024 |
| Proforma of Agreement for saleFile: ATS.pdf | 26 Nov 2024 |
| CERSAI detailsFile: Cersai Declaration.pdf | 23 Nov 2024 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 16 Nov 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: format A.pdf | 16 Nov 2024 |
| Other - TechnicalFile: annexure A (1).pdf | 16 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: Legal Encumbrance certificate.pdf | 30 Oct 2024 |
| Other - LegalFile: Sale Deed.pdf | 30 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Legal Encumbrance certificate.pdf | 30 Oct 2024 |
| Building plan approvalFile: 11 NA Order.pdf | 29 Oct 2024 |
| PAN CardFile: PAN CARD - Maytas.pdf | 29 Oct 2024 |
| Copy of the legal title reportFile: 7 MAYTAS legal title report (1).pdf | 29 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Arch Certificate.pdf | 29 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Eng certificate.pdf | 29 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE (1).pdf | 29 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 11 NA Order.pdf | 29 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold booked inventory.pdf | 29 Oct 2024 |
| Declaration about Commencement CertificateFile: 16 Circular 32.pdf | 29 Oct 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation for model agreement.pdf | 29 Oct 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for model agreement.pdf | 29 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser of Interest_merged.pdf | 29 Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ATHARVA RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NARSALA2,800+ in Nagpur
Filed coordinates, straight-line distance. 47 registered projects within 2 km.
BHEDE NAGARI -CHARITON
DILIP GANPATRAO BHEDE
Godrej Orchard Estate
Godrej Properties Limited
MELBOURNE CITY
M/S 4 PILLARS REALTY
GARDEN HOMES ATHARVA NAGARI VII
ATHARVA INFRASTRUCTURES
ROYAL EMPIRE
M B INFRA
Ved Vidhi Ventures
Ved Vidhi Ventures
See every Nagpur project, with the district possession charts
Builder: MAYTAS INFRAVENTURES PRIVATE LIMITED
MAYTAS INFRAVENTURES PRIVATE LIMITED has 1 registration on MahaRERA, including ATHARVA RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if ATHARVA RESIDENCY is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ATHARVA RESIDENCY?
The registered promoter entity is MAYTAS INFRAVENTURES PRIVATE LIMITED, a company as per the filing. Its CIN U45309MH2022PTC393704 and GSTIN 27AAQCM3616D1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ATHARVA RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ATHARVA RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ATHARVA RESIDENCY?
The professionals named in the filing: Architect: Alok Lunia; Engineer: Nakul Parbat; Engineer: Atul Namdeorao Shrirao; Chartered Accountant: Vijay Shankarrao Gulhane; Chartered Accountant: A.A. Virani & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ATHARVA RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback