Home / Browse projects / Pune, Maharashtra / ASPIRE AVENUE
ASPIRE AVENUE
RG-MH-88602 · RERA PM1260002501292 · Last updated on MahaRERA portal: 29 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ASPIRE AVENUE is a Mixed project by ASPIRE BUILDCON in Pune, Maharashtra, registered with MahaRERA as PM1260002501292 on 20 Oct 2025. Possession is promised by 30 Sep 2028. 0 of the 14 units on this registration are recorded sold or booked, and 3 of 18 construction stages are filed complete.
At a glance
Project
- NameASPIRE AVENUE
- TypeMixed
- Location
- DHANKAWADI -AMBEGAON SHIV ROAD
- DHANKAWADI-EXT
- Dhankawadi
- Haveli
- Pune
- 411043
- Pincode411043
- MapView location on Google Maps (as filed on RERA)
- RERA no.PM1260002501292
- ReraGenie IDRG-MH-88602
Builder
- NameASPIRE BUILDCON
- Entity typePartnership
- PartnersSARJERAO GANPAT SHILIMKAR, YOGESH POPATRAO SHILIMKAR, MAHESH SAVATA ZAGADE, HARISHCHANDRA RANGNATH ANARSE, MAYUR HANUMANT YELE, ABHIJIT SAHEBRAO SHILIMKAR
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on20 Oct 2025
- Promised completion30 Sep 2028
- Revised completionNone
- Buildings2 building records
- Documents filed12 files
Current status
Figures as on 29 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A 1 BUILDING | A WING | 3 | 2 | 6 | 4 | 10 |
| A 1 BUILDING | B WING | 3 | 1 | 4 | 0 | 4 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 50%.
A 1 BUILDING · wing A WING17%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 50% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A 1 BUILDING · wing B WING22%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 0% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | 0% |
| Water Supply | No | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | 0% |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | 0% |
| Open Parking | No | Not applicable |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Stilt / Ground | Basement | Total |
|---|---|---|---|
| A 1 BUILDING A WING | 11 | 0 | 11 |
| A 1 BUILDING B WING | 0 | 7 | 7 |
Land and ownership22
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SARJERAO GANPAT SHILIMKAR | Katraj | Pune |
| BALASAHEB MARUTI HADAKE | AMBEGAON Bk | Pune |
| ANURADHA BALASAHEB HADAKE | AMBEGAON Bk | Pune |
| MANALI VINAYAK KADAM | Pune (M Corp.) | Pune |
| VINAYAK DHANAJI KADAM | Pune (M Corp.) | Pune |
| PRASHANT PRABHAKAR MAEN | Pune (M Corp.) | Pune |
| SHANTA BALAAHEB THORAVE | Pune (M Corp.) | Pune |
| KIRAN BALASAHEB THORAVE | Pune (M Corp.) | Pune |
| NITIN ANIL KASTURE | Pune (M Corp.) | Pune |
| SAROJANI NITIN KASTURE | Pune (M Corp.) | Pune |
| SAGAR SHAMRAO SHILIMKAR | Pune (M Corp.) | Pune |
| ANANT MAHADEV DERE | Bhor (M Cl) | Pune |
| TARABAI MAHADEV DERE | Bhor (M Cl) | Pune |
| SHIRISH DATTATRAY CHAVAN | Bhor (M Cl) | Pune |
| VIKRAMADITYA VISHWAS BADADE | Kodit Bk. | Pune |
| MOHAN SHANTARAM TALEKAR | Kodit Bk. | Pune |
| SAGAR BHAGWAN LIMHAN | Pune (M Corp.) | Pune |
| UDIT APPASO JAGTAP | Mahabaleshwar wadi | Satara |
| BHAGWAN KASHINATH LIMHAN | Pune (M Corp.) | Pune |
| UMESH SUBHASH PAWAR | Pune (M Corp.) | Pune |
| RAJNIKANT HIMMATLAL PAREKH | Pune (M Corp.) | Pune |
| RAJESH HIMMATLAL PAREKH | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A 1 BUILDING | A WING | Rs 6.96 cr | Rs 1.39 cr |
| A 1 BUILDING | B WING | Rs 4.14 cr | Rs 82.83 lakh |
| - | NA | Rs 50.00 lakh | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | RUSHIKESH ZAGADE |
| Engineer | MAYUR HANUMANT YELE |
| Chartered Accountant | GANESH PRABHAKAR DHINDLE |
| Chartered Accountant | MILIND PADMAKAR TILWANKAR |
| Partner | Role in project |
|---|---|
| ASPIRE BUILDCON | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportNot on the file
A lawyer's report on who owns the land and what is registered against it.
- Layout approvalNot on the file
The planning authority's approval of how the plots and buildings sit on the land.
- Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Sep 2025 - Commencement CertificateNot on the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
- Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Sep 2028
Documents filed12
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A.pdf | 29 Jun 2026 |
| Form 5 (FY 2025-2026)File: Form 5.pdf | 20 Jun 2026 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 12 May 2026 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 12 May 2026 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf | 12 May 2026 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT CERTIFICATE.pdf | 13 Mar 2026 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf | 13 Mar 2026 |
| Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE.pdf | 13 Mar 2026 |
| Declaration and undertaking (Annexure A)File: Declaration Cum Undertaking.pdf | 25 Sep 2025 |
| Building plan approval or NA orderFile: Old NA Order.pdf | 25 Sep 2025 |
| Building plan approvalFile: PLAN 1.pdf | 23 Sep 2025 |
| Building plan approvalFile: PLAN 2.pdf | 23 Sep 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 12 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ASPIRE AVENUE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DHANKAWADI-EXT13,700+ in Pune
Filed coordinates, straight-line distance. 194 registered projects within 2 km.
4 Taljai Hills Phase 1
Shri Taljai Mata Associates LLP
CHANDRANGAN REVANTA
CHANDRANGAN BUILDCON LLP
PANORA
OM SAI DEVELOPERS
KADAM HERITAGE SURVEY NO.4/7/1 AND 4/7/2
D & T PROPERTIES
TRIDENT
Shamraj Constructions
Bhargav Stella
Bhargav Shelters
Builder: ASPIRE BUILDCON
Aspire Buildcon has 2 registrations on MahaRERA, including Aspire Park and ASPIRE AVENUE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if ASPIRE AVENUE is delayed beyond 30 Sep 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ASPIRE AVENUE?
The registered promoter entity is ASPIRE BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ASPIRE AVENUE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ASPIRE AVENUE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ASPIRE AVENUE?
The professionals named in the filing: Architect: RUSHIKESH ZAGADE; Engineer: MAYUR HANUMANT YELE; Chartered Accountant: GANESH PRABHAKAR DHINDLE; Chartered Accountant: MILIND PADMAKAR TILWANKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ASPIRE AVENUE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback