ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / ASIL PARADISE

Completed No litigation declared Others project

ASIL PARADISE

By ASIL INFRATECH LLP

RG-MH-27748 · RERA P52000024129 · Last updated on MahaRERA portal: 9 Oct 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 16 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Apr 2024Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
0Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

ASIL PARADISE is a Others project by ASIL INFRATECH LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000024129 on 21 Jan 2020. The registration is recorded completed; possession was promised by 12 Apr 2024. The completion date has moved by 16 months from the original filing.

At a glance

Project

  • NameASIL PARADISE
  • TypeOthers
  • Location
    • Sector -19
    • TALOJA
    • Taloje Panchnad
    • Panvel
    • Raigarh
    • 410208
  • Pincode410208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000024129
  • ReraGenie IDRG-MH-27748

Builder

  • NameASIL INFRATECH LLP
  • Entity typePartnership
  • PartnersMOHD NAEEM A RASHID PATEL, ZUBAIR RAUF PATEL
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredJan 2020First promiseDec 2022Revised toApr 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on21 Jan 2020
  • Promised completion12 Apr 2024
  • Revised completionRevised to 12 Apr 2024 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ASIL PARADISENA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

ASIL PARADISE: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 9 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed7

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots7
Closed/Covered7

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area450 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on10 Sep 2024

Approvals and building plan

Sanctioning authorityCIDCO
Permissible FSI673.69
Proposed, not sanctioned674 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor shop no -22 23 24 , Plot No 5,6,7 sector -35 Kharghar Navi Mumbai -410210

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectATUL PATEL ARCHITECTS
EngineerB S SUKHTANKAR
EngineerSK Consultants & Engineers
Chartered AccountantRUTUJA SAJJAN NARSINGH
Chartered AccountantCA Rutuja Narsingh & Associates
Chartered AccountantM/S Pratiksha Tulshyan & Associates
PartnerRole in project
ASIL INFRATECH LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000013433Dec 2022 → Dec 2023

Reason as filed by the promoterThis is to inform you that we have completed the above mentioned project within stipulated period of time as mentioned in Form B for obtaining Maharera Registration No:P52000024129 and we have submitted to Cidco vide our Architect's letter for Occupancy dated 16/09/2021 for Obtaining Occupancy Cerficate. Cidco Vide its letter dated 27/9/2021 has refused to grant us Occupancy Certificate stating As per approved CZMP based on 2011 notification, the plot is affected by CRZ. Therefore, you are requested to obtain clearance/approval of MCZMA.We hereby inform you that Cidco has issued us Commencemen

EXT52000024578Dec 2022 → Apr 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We do not require consents, as we have received OC.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Jul 2024

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf9 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 Asil Paradise OC Dated.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Asil Paradise OC Dated.pdf8 Oct 2024
Disclosure of sold/ booked inventoryFile: Asil Paradise Circular 29.pdf8 Oct 2024
Declaration in FORM BFile: Form B.pdf8 Oct 2024
Declaration in FORM BFile: Form B.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 Asil Paradise OC Dated.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Asil Paradise OC Dated.pdf8 Oct 2024
Disclosure of sold/ booked inventoryFile: Asil Paradise Circular 29.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 12-04-2024.pdf7 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 12-04-2024.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -AP.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf13 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf13 Aug 2024
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 -AP.pdf13 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- AP.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23-AP.pdf13 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24-AP.pdf13 Aug 2024
Declaration in FORM BFile: Form B.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Atul Patel Architechts File.pdf6 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 Aug 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Declaration of Society.pdf31 Jul 2024
Status of ConveyanceFile: Declaration Conveyance.pdf31 Jul 2024
Declaration about Commencement CertificateFile: Format D.pdf30 Jul 2024
CERSAI detailsFile: CERSAI.pdf30 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf30 Jul 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf30 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC (1) (4).pdf25 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 19-20 FORM 5.pdf24 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Fy 20-21 Form 5.pdf24 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Fy 21-22 form 5.pdf24 Feb 2023
Declaration about Commencement CertificateFile: ASIL INFRATECH LLP CC DECLARATION.pdf18 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ASIL INFRATECH.pdf18 Feb 2023
Disclosure of sold/ booked inventoryFile: ASIL INVENTORY.pdf18 Feb 2023
Disclosure of sold/ booked inventoryFile: Ail Paradise 29.pdf10 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 17-19.pdf14 Aug 2021
Details of encumbrancesFile: encumbrance asil.pdf11 Jan 2020
Declaration in FORM BFile: form B Asil.pdf11 Jan 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 asil.pdf11 Jan 2020
Proforma of Allotment letterFile: AGREEMENT FOR SALE- ASIL INFRATECH LLP - ASIL PARADISE.pdf11 Jan 2020
Proforma of Allotment letterFile: Allotment Letter - ASIL INFRATECH LLP- ASIL PARADISE.pdf11 Jan 2020
Layout approvalFile: IOD PLAN.pdf10 Jan 2020
Building plan approvalFile: IOD PLAN.pdf10 Jan 2020
PAN CardFile: asil infratech pan card.pdf10 Jan 2020
Copy of the legal title reportFile: TITLE AND SEARCH CERTIFICATE_compressed.pdf10 Jan 2020
Copy of Layout Approval (in case of layout)File: IOD PLAN.pdf10 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: IOD PLAN.pdf10 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf10 Jan 2020

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 16 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ASIL PARADISE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near TALOJA5,900+ in Raigarh

2 kmASIL PARADISECompleted 62Lapsed / revoked 17Other 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 157 registered projects within 2 km.

Builder: ASIL INFRATECH LLP

ASIL INFRATECH LLP has 2 registrations on MahaRERA, including ASIL PARADISE and Asil Palace. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if ASIL PARADISE is delayed beyond 12 Apr 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ASIL PARADISE?

The registered promoter entity is ASIL INFRATECH LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ASIL PARADISE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ASIL PARADISE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ASIL PARADISE?

The professionals named in the filing: Architect: ATUL PATEL ARCHITECTS; Engineer: B S SUKHTANKAR; Engineer: SK Consultants & Engineers; Chartered Accountant: RUTUJA SAJJAN NARSINGH; Chartered Accountant: CA Rutuja Narsingh & Associates; Chartered Accountant: M/S Pratiksha Tulshyan & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASIL PARADISE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASIL PARADISE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASIL PARADISE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.