Home / Browse projects / Raigarh, Maharashtra / Ashtavinayak Ultramodern Township Phase 1

Registration lapsed No litigation declared Residential / Group Housing project

Ashtavinayak Ultramodern Township Phase 1

By Shankheshwar Realty

RG-MH-58829 · RERA P52000006950 · Last updated on MahaRERA portal: 4 Jul 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 42 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
29 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 10%
60 of 112Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

Ashtavinayak Ultramodern Township Phase 1 is a Residential / Group Housing project by Shankheshwar Realty in Raigarh, Maharashtra, registered with MahaRERA as P52000006950 on 16 Aug 2017. Possession was promised by 30 Jun 2022 and is now 52 months past that date. The completion date has moved by 42 months from the original filing. 52 of the 112 units on this registration are recorded sold or booked, and 29 of 44 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameAshtavinayak Ultramodern Township Phase 1
  • TypeResidential / Group Housing
  • Location
    • Pali
    • Asthavinayak Ballaleshwar Temple
    • Sudhagad
    • Raigarh
    • 410205
  • Pincode410205
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000006950
  • ReraGenie IDRG-MH-58829

Builder

  • NameShankheshwar Realty
  • Entity typePartnership
  • PartnersKISHOR OTERMAL JAIN, SANGITA KISHOR JAIN

Key dates

52 months past promisethis monthRegisteredAug 2017First promiseDec 2018Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Dec 2018)
  • Buildings4 building records
  • Documents filed22 files

Current status

46%52 of 112 units booked

Figures as on 4 Jul 2019, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MayureshwarNA5048048
SiddhivinayakNA6032032
VaradvinayakNA6032032
Club HouseNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 4 Jul 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 10%.

Mayureshwar91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Siddhivinayak46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Varadvinayak46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Club House82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 4 Jul 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes50%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes30%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
Siddhivinayak11
Varadvinayak11

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,719 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI4248.99
Proposed, not sanctioned4,249 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAt Po Nagothane Opp Railway Station Tal Roha Dist Raigad 402106

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDeepan Gohil
PartnerRole in project
Shankheshwar Realty-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000005334Dec 2018 → Dec 2021

Reason as filed by the promoterAshtavinayak Ultra modern township project is in a village and did not get expected response which resulted in financial paucity . furthermore it became difficult to procure sand and cement at this remote location on time which also resulted in delay in construction . promoter further states that in spite of adverse conditions promoter completed his first building and got occupation certificate as well . the mistake which promoters committed is of registering all the three buildings together as he was going to construct building one after another.Even in covid Pandemic our work dint stoped 1 m

EXT52000000967Dec 2018 → Dec 2019

Reason as filed by the promoterThere is shortage of sand in this area and due to this the constuction of buidings had slow down. we are trying our best to resolve the issue and wi;; complete the construction.

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000375192Sachin CHANDRAKANT PatankarSHANKHESHWAR REALTY09/04/2023
CC006000000192268Vidya Ravindra SagvekarShankheshwar Realty22/01/2020
CC006000000375189Amit Nandkumar PradhanSHANKHESHWAR REALTY09/04/2023
CC006000000375190Ketan Nandkumar PradhanSHANKHESHWAR REALTY16/04/2023
CC006000000396078JAYPRAKASH GAVALIM/S SHANKHESHWAR REALTY05/09/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Aug 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Proforma of Allotment letterFile: Mayureshwar Draft amanedment.pdf4 Jul 2019
Proforma of Allotment letterFile: SIDDHIVINAYAK AND VARDVINAYAK AGREEMENT DRAFT.pdf4 Jul 2019
Certificates of CA (Form 5)File: 78023c84-43a6-4cc8-9735-76f7752ee627.pdf6 Jan 2019
Certificates of CA (Form 5)File: 87fcfb84-5ab0-4d12-a635-a074aa191440.pdf6 Jan 2019
Building plan approvalFile: 1.pdf2 Aug 2017
Building plan approvalFile: 2.pdf2 Aug 2017
Layout approvalFile: All Details.pdf2 Aug 2017
Copy of the legal title reportFile: Title Report.pdf2 Aug 2017
Details of encumbrancesFile: SHANKESHWARNon-Encumbramce Certificate 2 .pdf2 Aug 2017
Copy of Layout Approval (in case of layout)File: All Details.pdf2 Aug 2017
Building Plan Approval (IOD)File: 1.pdf2 Aug 2017
Building Plan Approval (IOD)File: 2.pdf2 Aug 2017
Declaration in FORM BFile: SHANKESHWARDeclaration Letter.pdf2 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf2 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf2 Aug 2017
Certificates of CA (Form 3)File: CA Certificate.PDF2 Aug 2017
Certificates of CA (Form 3)File: Sankheswar_-_sold_unit.PDF2 Aug 2017
Certificates of CA (Form 3)File: Sankheswar_-_unsold_unit.PDF2 Aug 2017
Proforma of Allotment letterFile: Allotment Letter Proforma - Ashtavinayak Siddhivinayak-Varadvinayak .pdf2 Aug 2017
Declaration in FORM BFile: Affidavit Paper.pdf31 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Proforma RERA-Ashtavinayak - Mayureshwar .pdf31 Jul 2017

How this compares with Raigarh

46%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 42 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ashtavinayak Ultramodern Township Phase 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Asthavinayak Ballaleshwar Temple5,900+ in Raigarh

2 kmAshtavinayak UltramodernCompleted 1Lapsed / revoked 1Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Shankheshwar Realty

Shankheshwar Realty has 1 registration on MahaRERA, including Ashtavinayak Ultramodern Township Phase 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Ashtavinayak Ultramodern Township Phase 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Ashtavinayak Ultramodern Township Phase 1 is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ashtavinayak Ultramodern Township Phase 1?

The registered promoter entity is Shankheshwar Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ashtavinayak Ultramodern Township Phase 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ashtavinayak Ultramodern Township Phase 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ashtavinayak Ultramodern Township Phase 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ashtavinayak Ultramodern Township Phase 1?

The professionals named in the filing: Architect: Deepan Gohil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ashtavinayak Ultramodern Township Phase 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ashtavinayak Ultramodern Township Phase 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ashtavinayak Ultramodern Township Phase 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.