ARYAMAN TANISH

By ARYAMAN INFRATECH INDIA PVT LTD

RG-MH-01778 · RERA P51800012284 · Last updated on MahaRERA portal: 29 Dec 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 72 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
7 of 11Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
0 of 1Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

ARYAMAN TANISH is a Mixed project by ARYAMAN INFRATECH INDIA PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012284 on 1 Sep 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 72 months from the original filing. 1 of the 1 unit on this registration is recorded sold or booked, and 7 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameARYAMAN TANISH
  • TypeMixed
  • Location
    • OFF LINK ROAD
    • MUMBAI
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012284
  • ReraGenie IDRG-MH-01778

Builder

  • NameARYAMAN INFRATECH INDIA PVT LTD
  • Entity typeCompany
  • Managing DirectorShabbir Mohamad Shaikh
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

28 months past promisethis monthRegisteredSep 2017First promiseJun 2018Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 30 Jun 2018)
  • Buildings1 building record
  • Documents filed43 files

Current status

100%1 of 1 units booked

Figures as on 29 Dec 2023, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SBI EMPLOYEES SHIVNER CHSLNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

SBI EMPLOYEES SHIVNER CHSL64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 29 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed36

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots36
Closed/Covered32
Open Space4

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area698 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2065.0
Proposed, not sanctioned2,065 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND AND FIRST FLOOR, A1 A WING EVEREST MUMBAI 400053

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUDAY KANADIA
PartnerRole in project
ARYAMAN INFRATECH INDIA PVT LTD-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009188Jun 2018 → Dec 2021

Reason as filed by the promoterWe have applied for the CC in December,2019 but due to delay in MCGM approvals and then in MArch lockdown was started, we are not able to start our work as we get the commencement certificate on 11th February,2021 (Copy of CC enclosed).

EXT51800000474Jun 2018 → Jun 2020

Reason as filed by the promoterMCGM has not given permission in time and delayed permission for more than 7 months.

EXT51800002204Jun 2018 → Jun 2020

Reason as filed by the promoterWe Have Approached to National Company Law Board Mumbai Bench NCLT And filed company petition under section 252 of the companies act 203 bearing CP no 3947/25/NCLT/MB/MAH/2018 for restoring of the company.

EXT51800017695Jun 2018 → Jun 2024

Reason as filed by the promoter1) AFTER LOCK DOWN THE SUPPLY OF PARTS FOR LIFT WAS DELAYED BY THE LIFT COMPANY IN THE YEAR 2021, ORDER WAS PLACED AND MATERIAL WERE SUPPLIED IN JUNE 2023. 2) DUE TO ARBITRATION CASE THE SOCIETY MEMBERS HAD FILLED IN 2021, WHICH PROLONGED THE COMPLETION. THE CASE WAS FILLED FOR EXTRA FSI DISTRIBUTION BETWEEN US AND SOCIETY. 3) DELAY DUE TO NALLA APPROVAL WHICH PASSES FROM BACK WALL OF SOCIETY APPROVALS PROVIDED IN JAN 2023. 4) AFTER COVID ALL SOLD FLATS PAYMENTS WERE DELAYED FROM THE BUYERS WHICH WERE ENOUGH TO COMPLETE THE BUILDING WORK AND THE SAME WAS SORTED ONLY AFTER HIGH COURT INSTRUCTED

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000000430Sunil Shridhar MayekarARYAMAN INFRATECH INDIA PVT. LTD.12/09/2017
CC006000000056574Mr Manish Harish DesaiM/s Aryaman Infratech Pvt Ltd19/10/2018
CC006000000397745Manisha Mansing KhorateAryaman Infratech India Pvt. Ltd.07/10/2023
CC006000000397747Manisha Mansing KhorateAryaman Infratech India Pvt. Ltd.07/10/2023
CC12500468Rashmi Rajesh DahanukarARYAMAN INFRATECH INDIA PVT LTD12/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 ANNUAL AUDIT REPORT FY 2022-23.pdf29 Dec 2023
Declaration in FORM BFile: FORM B.pdf19 Dec 2023
Declaration in FORM BFile: FORM B - 30062024.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A-2020.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A-2021.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A-2022.pdf19 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A-2023.pdf19 Dec 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf1 Dec 2023
Declaration in FORM BFile: Affidavit Cum Declaration.pdf1 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2020(1).pdf1 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2021(1).pdf1 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2022(1).pdf1 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Booked Inventory.pdf1 Dec 2023
Certificates of CA (Form 3)File: Form 3 FY 20-21 SA.pdf30 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2018-19 SA.pdf30 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Certification For FY 2019-20 Sign.pdf30 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Certification For FY 2020-21 Sign.pdf30 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22 SA.pdf30 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate .pdf24 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certificate .pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2020.pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2021(1).pdf24 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2023(1).pdf24 Nov 2023
Layout approvalFile: Shivner 14 Floor Plan.pdf14 Aug 2019
Copy of Layout Approval (in case of layout)File: Shivner 14 Floor Plan.pdf14 Aug 2019
Certificates of CA (Form 5)File: Tanish.pdf30 Sep 2018
Layout approvalFile: Shivner CC Plan.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Shivner CC Plan.pdf31 Jul 2017
Declaration in FORM BFile: Shivner Notary.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shivner Engineer Certificate LH.pdf31 Jul 2017
Certificates of CA (Form 3)File: FORM 3 SHIVNER.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shivner Architect Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: Draft Allotment letter - (RERA).pdf29 Jul 2017
Building plan approval or NA orderFile: IOD Plan Low Size.pdf28 Jul 2017
Building plan approval or NA orderFile: IOD.pdf28 Jul 2017
PAN CardFile: Pan Card.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf28 Jul 2017
Details of encumbrancesFile: Shivner Non-Encumbrance Certificate.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD Plan Low Size.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Shivner CHSL Furthe CC.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Shivner CC Plan.pdf28 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale -RERA- - Draft.pdf28 Jul 2017

How this compares with Mumbai Suburban

100%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 72 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ARYAMAN TANISH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUMBAI6,700+ in Mumbai Suburban

2 kmARYAMAN TANISHCompleted 93Lapsed / revoked 58Other 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 271 registered projects within 2 km.

Builder: ARYAMAN INFRATECH INDIA PVT LTD

ARYAMAN INFRATECH INDIA PVT LTD has 3 registrations on MahaRERA, including ARYAMAN TANISH and Aryaman Marina. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that ARYAMAN TANISH shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ARYAMAN TANISH is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ARYAMAN TANISH?

The registered promoter entity is ARYAMAN INFRATECH INDIA PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ARYAMAN TANISH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ARYAMAN TANISH?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ARYAMAN TANISH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ARYAMAN TANISH?

The professionals named in the filing: Architect: UDAY KANADIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARYAMAN TANISH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARYAMAN TANISH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARYAMAN TANISH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.