Artteza
RG-MH-29759 · RERA P51800030554 · Last updated on MahaRERA portal: 4 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 4 complaints at MahaRERA
- Completion date moved by 30 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Artteza is a Residential / Group Housing project by SUNVISION ESTATES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800030554 on 30 Aug 2021. Possession is promised by 30 Nov 2026. The completion date has moved by 30 months from the original filing. 66 of the 80 units on this registration are recorded sold or booked, and 29 of 44 construction stages are filed complete. 4 complaints are on record with the regulator.
At a glance
Project
- NameArtteza
- TypeResidential / Group Housing
- Location
- Relief Road
- Santacruz West
- Andheri
- Mumbai Suburban
- 400054
- Pincode400054
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800030554
- ReraGenie IDRG-MH-29759
Builder
- NameSUNVISION ESTATES
- Entity typePartnership
- PartnersSuresh Menghraj Shroff, Parth Kaushik Mehta
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on30 Aug 2021
- Promised completion30 Nov 2026
- Revised completionRevised to 30 Nov 2026 (originally 31 May 2024)
- Buildings4 building records
- Documents filed149 files
Current status
Figures as on 4 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 12 | 5 | 20 | 0 | 20 |
| Wing B | NA | 13 | 5 | 20 | 0 | 20 |
| Wing C | NA | 13 | 5 | 20 | 0 | 20 |
| Wing D | NA | 12 | 5 | 20 | 0 | 20 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 90%.
Wing A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing B91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing C67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing D66%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed134
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 37 | 37 |
| Wing B | 30 | 30 |
| Wing C | 29 | 29 |
| Wing D | 38 | 38 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUNVISION ESTATES | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing A | NA | Rs 15.75 cr | Rs 15.51 cr |
| Wing B | NA | Rs 15.75 cr | Rs 15.51 cr |
| Wing C | NA | Rs 15.75 cr | Rs 15.51 cr |
| Wing D | NA | Rs 15.75 cr | Rs 15.51 cr |
| - | NA | Rs 2.00 cr | Rs 1.00 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Jainam Shah of SpacEra Architects |
| Architect | SpacERA |
| Engineer | Sunil R Shah |
| Chartered Accountant | Rohan Yadav and Co |
| Chartered Accountant | B N Bhadricha & Co |
| Partner | Role in project |
|---|---|
| SUNVISION ESTATES | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterProject was registered on 30.08.2021 with MahaRERA and time for completion as mentioned under RERA is 31.05.2024. The said Project is redevelopment of co-operative housing society. The Project consists of Wing A, B, C and D each consisting of two level of basement plus ground floor plus 9 upper floors. The Promoter has completed construction of all the slabs of superstructure of Wing A and B and the finishing work is ongoing in respect of Wing A and B. The Promoter intends to apply and obtain occupancy permissions of Wing A and B on or before 31.05.2024 and shall forthwith handover possession
Reason as filed by the promoterThe present Project was originally being redeveloped by the erstwhile Developer. The present Developer acquired the development rights of project through consent terms dated 25.06.2021 r/w Addendum dated 18.03.2021. The Entire Project was under severe financial crunch and had to be revived by the Promoter. In doing so, the Promoter had to avail financial facility from Lender which took considerable time in arranging necessary funds for successfully commencing the construction work of the project. Apart from financial challenges, certain litigations were also initiated in the Hon’ble Bombay Hig
Reason as filed by the promoterWe, SUNVISION ESTATES, the promoter of the project ARTTEZA (Registration No. P51800030554) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. The delay in completion of the project is attributable to a combination of financial, legal, and force majeure circumstances. The project was under severe financial stress, requiring restructuring and revival, which resulted in considerable time being spent in arranging financial assistance from lenders and mobilizing resources before recommencement of construction activities. The delay in completion of
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12400460 | Paramjit kaur | SUNVISION ESTATES | 19/10/2024 |
| CC12500938 | Joyeeta Basu Khan | SUNVISION ESTATES | 17/03/2025 |
| CC12501000 | Joyeeta Basu Khan | SUNVISION ESTATES | 22/03/2025 |
| CC12603779 | SUNVISION ESTATES | Satish Raghunath Nagwekar | 18/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Aug 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 22 Sep 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Jan 2025
Documents filed149
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 6444 Architect Certificate April-June 2026.pdf | 4 Aug 2026 |
| Withdrawal Update Form 2File: Engineers CERTIFICATE Form-2 -April - June 2026.pdf | 4 Aug 2026 |
| Withdrawal Update Form 3File: FORM 3 - JUN 26 (Without Sign).pdf | 4 Aug 2026 |
| Withdrawal Update Form 1File: Artteza - Form 1 March 2026____.pdf | 24 Jun 2026 |
| Withdrawal Update Form 2File: Artteza - Form 2 March 2026____.pdf | 24 Jun 2026 |
| Withdrawal Update Form 3File: Artteza - Form 3 - March 2026____.pdf | 24 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Artteza as on Dec 2025.pdf | 11 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Artteza as on Dec 2025.pdf | 11 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 - Artteza as on Dec 2025.pdf | 11 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 - Artteza as on Dec 2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Artteza as on Dec 2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Artteza as on Dec 2025.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 - Artteza as on June 2025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 - Artteza as on Sep 2025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 - Artteza as on Dec 2025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 - Artteza as on June 2025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 - Artteza as on Sep 2025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 - Artteza as on Dec 2025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 - Artteza as on June 2025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 - Artteza as on Sep 2025.pdf | 30 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 - Artteza as on Dec 2025.pdf | 30 Mar 2026 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers CERTIFICATE Form 2 Jan to Mar 25.pdf | 29 May 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf | 29 May 2025 |
| Declaration in FORM BFile: Form B Affidavit Cum Declaration.pdf | 28 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2025.pdf | 28 May 2025 |
| Disclosure of sold/ booked inventoryFile: Artteza Sold Unsold.pdf | 28 May 2025 |
| Disclosure of sold/ booked inventoryFile: Artteza Sold Unsold.pdf | 28 May 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Declaration of Rera Account.pdf | 28 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -5 April 2023 March 2024.pdf | 28 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5 April 24 to March 25.pdf | 28 May 2025 |
| Disclosure of sold/ booked inventoryFile: Artteza Sold Unsold Inventory Jan March 2025.pdf | 20 May 2025 |
| Details of encumbrancesFile: Declaration Encumbrance.pdf | 7 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan to March 2025.pdf | 14 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jun 24.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 24.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 24.pdf | 11 Apr 2025 |
| Declaration in FORM BFile: Form B Affidavit Cum Declaration.pdf | 27 Mar 2025 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 27 Mar 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf | 26 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineers CERTIFICATE Form-2 -Apr - June 2024.pdf | 20 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineers CERTIFICATE Form-2 -July - Sep 2024.pdf | 20 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - ARCHITECT CERTIFICATE April-June 2024.pdf | 20 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - ARCHITECT CERTIFICATE July-Sept 2024.pdf | 20 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -ARCHITECT CERTIFICATE Oct-Dec 2024.pdf | 20 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers CERTIFICATE Form-2 -Apr - June 2024.pdf | 20 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers CERTIFICATE Form-2 -July - Sep 2024.pdf | 20 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers CERTIFICATE Form-2 - Oct - Dec 24.pdf | 20 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Artteza sold unsold till Dec 2024.pdf | 6 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_signed.pdf | 18 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Artteza sold unsold till sept 2024.pdf | 30 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Artteza sold unsold till june 2024.pdf | 5 Aug 2024 |
| Declaration in FORM BFile: Form B Affidavit of Declaration.pdf | 5 Jun 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA letter - Sunvision Estates.pdf | 5 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Qtr ended Sept 23.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Qtr ended Dec 23.pdf | 29 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Qtr ended Mar 24.pdf | 29 May 2024 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 24 May 2024 |
| Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf | 24 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate -.pdf | 24 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Qtr ended Sept.pdf | 24 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Qtr ended Dec.pdf | 24 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Qtr ended Mar.pdf | 24 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A FY 21-22.pdf | 24 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FY 22-23.pdf | 24 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A FY 23-24.pdf | 24 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 18 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 18 May 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Arttezza Revised CC.pdf | 14 May 2024 |
| Disclosure of sold/ booked inventoryFile: Artteza sold unsold till March, 2024.pdf | 23 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 RERA architect certificate artezza.pdf | 28 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Artteza sold unsold inventory till spet 2023.pdf | 28 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Artteza sold unsold - Dec 2023.pdf | 28 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 march 2023 compressed.pdf | 4 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2023 compressed.pdf | 4 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 3 Oct 2023 |
| Building plan approvalFile: Artteza-1-4.pdf | 22 Sep 2023 |
| Building plan approvalFile: Artteza-5-6.pdf | 22 Sep 2023 |
| Building plan approvalFile: Artteza-7-9.pdf | 22 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Artteza-1-4.pdf | 22 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Artteza-5-6.pdf | 22 Sep 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 149 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Artteza on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Santacruz West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 303 registered projects within 2 km.
AVIARA
BALUWALA BUILDERS
Ruparel Panache
Ruparel Infra & Realty Pvt Ltd
Vascon Orchids
Vascon Engineers Ltd
COMMERZ 54
SHREE VINAYAK REALITY PRIVATE LIMITED
Vascon Onyx Residences
Vascon Engineers Ltd
REDEVELOPMENT OF SHINING STAR CHSL
PRANAV CONSTRUCTIONS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: SUNVISION ESTATES
SUNVISION ESTATES has 1 registration on MahaRERA, including Artteza. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Artteza is delayed beyond 30 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Artteza?
The registered promoter entity is SUNVISION ESTATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Artteza?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Artteza?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Artteza?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Artteza?
The professionals named in the filing: Architect: Jainam Shah of SpacEra Architects; Architect: SpacERA; Engineer: Sunil R Shah; Chartered Accountant: Rohan Yadav and Co; Chartered Accountant: B N Bhadricha & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Artteza?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback