Home / Browse projects / Mumbai Suburban, Maharashtra / Artteza

Registered No litigation declared Residential / Group Housing project

Artteza

By SUNVISION ESTATES

RG-MH-29759 · RERA P51800030554 · Last updated on MahaRERA portal: 4 Aug 2026

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 30 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 30 months from the original
29 of 44Construction stages doneacross 4 buildings; furthest along: Slabs of Super Structure, 90%
14 of 80Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 149 documents Report an error

Artteza is a Residential / Group Housing project by SUNVISION ESTATES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800030554 on 30 Aug 2021. Possession is promised by 30 Nov 2026. The completion date has moved by 30 months from the original filing. 66 of the 80 units on this registration are recorded sold or booked, and 29 of 44 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameArtteza
  • TypeResidential / Group Housing
  • Location
    • Relief Road
    • Santacruz West
    • Andheri
    • Mumbai Suburban
    • 400054
  • Pincode400054
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800030554
  • ReraGenie IDRG-MH-29759

Builder

  • NameSUNVISION ESTATES
  • Entity typePartnership
  • PartnersSuresh Menghraj Shroff, Parth Kaushik Mehta

Key dates

this monthRegisteredAug 2021First promiseMay 2024Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Aug 2021
  • Promised completion30 Nov 2026
  • Revised completionRevised to 30 Nov 2026 (originally 31 May 2024)
  • Buildings4 building records
  • Documents filed149 files

Current status

82%66 of 80 units booked
97.0%Work done, per cost certificate

Figures as on 4 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA12520020
Wing BNA13520020
Wing CNA13520020
Wing DNA12520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

Wing A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing C67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D66%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed134

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots134
Closed/Covered134
BuildingClosed/CoveredTotal
Wing A3737
Wing B3030
Wing C2929
Wing D3838

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,928 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SUNVISION ESTATESAndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI9926.0
Proposed, not sanctioned6,476 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSuncity Theatre building, Paranjpe A scheme
Estimated costRs 65.00 cr
Cost incurredRs 63.05 cr
Work done97.0%
BuildingWingEstimatedIncurred
Wing ANARs 15.75 crRs 15.51 cr
Wing BNARs 15.75 crRs 15.51 cr
Wing CNARs 15.75 crRs 15.51 cr
Wing DNARs 15.75 crRs 15.51 cr
-NARs 2.00 crRs 1.00 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJainam Shah of SpacEra Architects
ArchitectSpacERA
EngineerSunil R Shah
Chartered AccountantRohan Yadav and Co
Chartered AccountantB N Bhadricha & Co
PartnerRole in project
SUNVISION ESTATES-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800019441May 2024 → May 2025

Reason as filed by the promoterProject was registered on 30.08.2021 with MahaRERA and time for completion as mentioned under RERA is 31.05.2024. The said Project is redevelopment of co-operative housing society. The Project consists of Wing A, B, C and D each consisting of two level of basement plus ground floor plus 9 upper floors. The Promoter has completed construction of all the slabs of superstructure of Wing A and B and the finishing work is ongoing in respect of Wing A and B. The Promoter intends to apply and obtain occupancy permissions of Wing A and B on or before 31.05.2024 and shall forthwith handover possession

EXT51800028059May 2024 → May 2026

Reason as filed by the promoterThe present Project was originally being redeveloped by the erstwhile Developer. The present Developer acquired the development rights of project through consent terms dated 25.06.2021 r/w Addendum dated 18.03.2021. The Entire Project was under severe financial crunch and had to be revived by the Promoter. In doing so, the Promoter had to avail financial facility from Lender which took considerable time in arranging necessary funds for successfully commencing the construction work of the project. Apart from financial challenges, certain litigations were also initiated in the Hon’ble Bombay Hig

EA30032620461May 2024 → Nov 2026

Reason as filed by the promoterWe, SUNVISION ESTATES, the promoter of the project ARTTEZA (Registration No. P51800030554) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. The delay in completion of the project is attributable to a combination of financial, legal, and force majeure circumstances. The project was under severe financial stress, requiring restructuring and revival, which resulted in considerable time being spent in arranging financial assistance from lenders and mobilizing resources before recommencement of construction activities. The delay in completion of

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12400460Paramjit kaurSUNVISION ESTATES19/10/2024
CC12500938Joyeeta Basu KhanSUNVISION ESTATES17/03/2025
CC12501000Joyeeta Basu KhanSUNVISION ESTATES22/03/2025
CC12603779SUNVISION ESTATESSatish Raghunath Nagwekar18/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Jan 2025

Documents filed149

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 6444 Architect Certificate April-June 2026.pdf4 Aug 2026
Withdrawal Update Form 2File: Engineers CERTIFICATE Form-2 -April - June 2026.pdf4 Aug 2026
Withdrawal Update Form 3File: FORM 3 - JUN 26 (Without Sign).pdf4 Aug 2026
Withdrawal Update Form 1File: Artteza - Form 1 March 2026____.pdf24 Jun 2026
Withdrawal Update Form 2File: Artteza - Form 2 March 2026____.pdf24 Jun 2026
Withdrawal Update Form 3File: Artteza - Form 3 - March 2026____.pdf24 Jun 2026
Withdrawal Update Form 1File: Form 1 - Artteza as on Dec 2025.pdf11 Jun 2026
Withdrawal Update Form 2File: Form 2 - Artteza as on Dec 2025.pdf11 Jun 2026
Withdrawal Update Form 3File: Form 3 - Artteza as on Dec 2025.pdf11 Jun 2026
Withdrawal Update Form 1File: Form 1 - Artteza as on Dec 2025.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 - Artteza as on Dec 2025.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 - Artteza as on Dec 2025.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1 - Artteza as on June 2025.pdf30 Mar 2026
Withdrawal Update Form 1File: Form 1 - Artteza as on Sep 2025.pdf30 Mar 2026
Withdrawal Update Form 1File: Form 1 - Artteza as on Dec 2025.pdf30 Mar 2026
Withdrawal Update Form 2File: Form 2 - Artteza as on June 2025.pdf30 Mar 2026
Withdrawal Update Form 2File: Form 2 - Artteza as on Sep 2025.pdf30 Mar 2026
Withdrawal Update Form 2File: Form 2 - Artteza as on Dec 2025.pdf30 Mar 2026
Withdrawal Update Form 3File: Form 3 - Artteza as on June 2025.pdf30 Mar 2026
Withdrawal Update Form 3File: Form 3 - Artteza as on Sep 2025.pdf30 Mar 2026
Withdrawal Update Form 3File: Form 3 - Artteza as on Dec 2025.pdf30 Mar 2026
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers CERTIFICATE Form 2 Jan to Mar 25.pdf29 May 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest.pdf29 May 2025
Declaration in FORM BFile: Form B Affidavit Cum Declaration.pdf28 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2025.pdf28 May 2025
Disclosure of sold/ booked inventoryFile: Artteza Sold Unsold.pdf28 May 2025
Disclosure of sold/ booked inventoryFile: Artteza Sold Unsold.pdf28 May 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Declaration of Rera Account.pdf28 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM -5 April 2023 March 2024.pdf28 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: Form 5 April 24 to March 25.pdf28 May 2025
Disclosure of sold/ booked inventoryFile: Artteza Sold Unsold Inventory Jan March 2025.pdf20 May 2025
Details of encumbrancesFile: Declaration Encumbrance.pdf7 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Jan to March 2025.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Jun 24.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 24.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 24.pdf11 Apr 2025
Declaration in FORM BFile: Form B Affidavit Cum Declaration.pdf27 Mar 2025
Declaration about Commencement CertificateFile: Declaration about CC.pdf27 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf26 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineers CERTIFICATE Form-2 -Apr - June 2024.pdf20 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineers CERTIFICATE Form-2 -July - Sep 2024.pdf20 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - ARCHITECT CERTIFICATE April-June 2024.pdf20 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - ARCHITECT CERTIFICATE July-Sept 2024.pdf20 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -ARCHITECT CERTIFICATE Oct-Dec 2024.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers CERTIFICATE Form-2 -Apr - June 2024.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers CERTIFICATE Form-2 -July - Sep 2024.pdf20 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers CERTIFICATE Form-2 - Oct - Dec 24.pdf20 Mar 2025
Disclosure of sold/ booked inventoryFile: Artteza sold unsold till Dec 2024.pdf6 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_signed.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Artteza sold unsold till sept 2024.pdf30 Oct 2024
Disclosure of sold/ booked inventoryFile: Artteza sold unsold till june 2024.pdf5 Aug 2024
Declaration in FORM BFile: Form B Affidavit of Declaration.pdf5 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA letter - Sunvision Estates.pdf5 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Qtr ended Sept 23.pdf29 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Qtr ended Dec 23.pdf29 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Qtr ended Mar 24.pdf29 May 2024
Declaration about Commencement CertificateFile: Declaration about CC.pdf24 May 2024
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf24 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate -.pdf24 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Qtr ended Sept.pdf24 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Qtr ended Dec.pdf24 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Qtr ended Mar.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A FY 21-22.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FY 22-23.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A FY 23-24.pdf24 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf18 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf18 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Arttezza Revised CC.pdf14 May 2024
Disclosure of sold/ booked inventoryFile: Artteza sold unsold till March, 2024.pdf23 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 RERA architect certificate artezza.pdf28 Feb 2024
Disclosure of sold/ booked inventoryFile: Artteza sold unsold inventory till spet 2023.pdf28 Feb 2024
Disclosure of sold/ booked inventoryFile: Artteza sold unsold - Dec 2023.pdf28 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 march 2023 compressed.pdf4 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2023 compressed.pdf4 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf3 Oct 2023
Building plan approvalFile: Artteza-1-4.pdf22 Sep 2023
Building plan approvalFile: Artteza-5-6.pdf22 Sep 2023
Building plan approvalFile: Artteza-7-9.pdf22 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Artteza-1-4.pdf22 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Artteza-5-6.pdf22 Sep 2023

How this compares with Mumbai Suburban

82%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Artteza on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Santacruz West6,700+ in Mumbai Suburban

2 kmArttezaCompleted 129Lapsed / revoked 67Other 107Dot size: filed unitsN

Filed coordinates, straight-line distance. 303 registered projects within 2 km.

Builder: SUNVISION ESTATES

SUNVISION ESTATES has 1 registration on MahaRERA, including Artteza. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Artteza is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Artteza?

The registered promoter entity is SUNVISION ESTATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Artteza?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Artteza?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Artteza?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Artteza?

The professionals named in the filing: Architect: Jainam Shah of SpacEra Architects; Architect: SpacERA; Engineer: Sunil R Shah; Chartered Accountant: Rohan Yadav and Co; Chartered Accountant: B N Bhadricha & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Artteza?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Artteza. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Artteza to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.