Registration approved No litigation declared Mixed Development project

ARNAVA HEIGHTS

By ARNAVA DEVELOPERS

RG-KA-17100 · RERA PRM/KA/RERA/1257/334/PR/061026/008991 · Last updated on RERA Karnataka portal: 10 Aug 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2031Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 80 documents Report an error

ARNAVA HEIGHTS is a Mixed Development project by ARNAVA DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/061026/008991 on 6 Oct 2026. Possession is promised by 31 Dec 2031.

At a glance

Project

  • NameARNAVA HEIGHTS
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/061026/008991
  • ReraGenie IDRG-KA-17100

Builder

  • NameARNAVA DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29ACBFA3914A1ZY
  • Authorized SignatoryKIRAN KUMAR SHETTY

Key dates

this monthRegisteredOct 2026PromisedDec 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on6 Oct 2026
  • Promised completion31 Dec 2031
  • Revised completionNone
  • Buildings1 building record
  • Documents filed80 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ARNAVA HEIGHTS-----53

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)-
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawings-

Progress on shared amenities40

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes-
Solid waste management and disposalYes-
Emergency Evacuation servicesYes-
Internal Roads & FootpathsYes-
Electricity supply transformer and substationYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
Piped GasNoNot applicable
Water and SanitationYes-
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners2
LandownerVillageDistrict
ARNAVA DEVELOPERS--
ARNAVA DEVELOPERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 13.13 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 13.02 cr-
On-site expenditure-Consultants FeesRs 11.54 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEEPU VARGHESE
EngineerMILAN BOLAR
Chartered AccountantBANTWAL NITHIN BALIGA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed80

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/061026/008991 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
COST ESTIMATIONFile: ARNAV COST ESTIMATION.pdf10 Aug 2026
RTC, survey 41/8B2-
Mutation, survey 41/8B2-
Encumbrance Certificate, survey 41/8B2-
Conversion/Alienation Order, survey 41/8B2-
Sale/Title/Gift Deed, survey 41/8B2-
Khatha, survey 41/8B2-
RTC, survey 41/8B1-
Mutation, survey 41/8B1-
Encumbrance Certificate, survey 41/8B1-
Conversion/Alienation Order, survey 41/8B1-
Sale/Title/Gift Deed, survey 41/8B1-
Khatha, survey 41/8B1-
Registration CertificateFile: Firm registartion certificate.pdf-
GST CertificateFile: GST.pdf-
Partnership DeedFile: partnership deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form -1 CA.pdf-
Certificate issued by Architect Form 2File: Form 2 architect certificate.pdf-
Certificate issued by Engineer Form 3File: Arnava Heights Form-3.pdf-
TDR Purchase Deed / Sale DeedFile: TDR sale deed 1 2 & 3 merge.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: affidavith-litigation.pdf-
Balance Sheet 2024 - 2025File: BS AY 2025-26.pdf-
Balance Sheet 2023 - 2024File: BS AY 2024-25.pdf-
Balance Sheet 2022 - 2023File: BS AY 2023-24.pdf-
Audited Profit and Loss Statement 2024 - 2025File: PL AY 2025-26.pdf-
Audited Profit and Loss Statement 2022 - 2023File: PL AY 2023-24.pdf-
heights building licence-
Approved plan-
single layout-
stability certiifcate with licence and declaration-
specifications-
Broucher-
relinquishment deed-
proforma AOS-
Proforma allottment letter-
Rera FormB-
Notarized Affidavit for 3(1) Voliation-
search report-
mescom noc-
water noc-
KSPCB-
Unnamed document-
FIRE-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
zonal certificate-
CDP plan-
Title deed shakoor-
Titel deed Zaheeda-
idya village map-
Village map-site highlighted-
TDR sale deed 1-
Utlization certificate 1-
TDR certificate 1-
TDR sale deed 2-
utilization certificate 2-
TDR certificate 2-
TDR sale deed 3-
utilization heights 3-
TDR certificate 3-
FIRE CHALLAN-
LOCATION MAP WITH BOUNDARY POINT-
FAR-
STP drawing-
pollution affidavit with application-
form 5 heights-
Heights Form-6-
carpet area-
declaration on borewell-
land cost sheet with guidance value-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep ARNAVA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: ARNAVA DEVELOPERS

ARNAVA DEVELOPERS has 1 registration on RERA Karnataka, including ARNAVA HEIGHTS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if ARNAVA HEIGHTS is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ARNAVA HEIGHTS?

The registered promoter entity is ARNAVA DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29ACBFA3914A1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ARNAVA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ARNAVA HEIGHTS?

The professionals named in the filing: Architect: DEEPU VARGHESE; Engineer: MILAN BOLAR; Chartered Accountant: BANTWAL NITHIN BALIGA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARNAVA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARNAVA HEIGHTS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARNAVA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.