Home / Browse projects / Wardha, Maharashtra / ARMORS NAGAR
ARMORS NAGAR
By ARMORS DEVELOPERS PRIVATE LIMITED
RG-MH-90651 · RERA P50400051372 · Last updated on MahaRERA portal: 12 Aug 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Wardha registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARMORS NAGAR is a Residential / Group Housing project by ARMORS DEVELOPERS PRIVATE LIMITED in Wardha, Maharashtra, registered with MahaRERA as P50400051372 on 8 Jun 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date.
At a glance
Project
- NameARMORS NAGAR
- TypeResidential / Group Housing
- Location
- Revenue Survey no. 16/1
- 16/4
- 16/5
- Plot No. 89
- MOUZA JUNONA
- Ajanti
- Hinganghat
- Wardha
- 442301
- Pincode442301
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50400051372
- ReraGenie IDRG-MH-90651
Builder
- NameARMORS DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
- DirectorSHARDA ANAND KHOBRAGADE
- Managing DirectorANAND NARAYANRAO KHOBRAGADE
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on8 Jun 2023
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings2 building records
- Documents filed92 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ARMORS NAGAR BLOCK A | NA | 5 | 0 | 0 | 0 | 0 |
| ARMORS NAGAR BLOCK-B -21-BUNGLOWS | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 12 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 95%.
ARMORS NAGAR BLOCK A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
ARMORS NAGAR BLOCK-B -21-BUNGLOWS45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 95% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed40
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr. Kiran Digamber Purohit |
| Engineer | Pankaj Ashokrao Landge |
| Chartered Accountant | RITESH VIRANI |
| Partner | Role in project |
|---|---|
| ARMORS DEVELOPERS PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 May 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Apr 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 May 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1-Q1.pdf | 12 Aug 2025 |
| Form 2File: Form-2-Q1.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q2.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q2.pdf | 12 Aug 2025 |
| Form 2File: Form-2-Q2.pdf | 12 Aug 2025 |
| Form 1File: Form 1-Q2.pdf | 12 Aug 2025 |
| Form 1File: Form 1-Q3.pdf | 12 Aug 2025 |
| Form 2File: Form-2-Q3.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q3.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q3.pdf | 12 Aug 2025 |
| Form 3File: FORM 3-RERA ARMORS DEVELOPERS-Q4.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: FORM 3-RERA ARMORS DEVELOPERS-Q4.pdf | 12 Aug 2025 |
| Form 1File: Form-1-Q4.pdf | 12 Aug 2025 |
| Form 2File: Form-2-Q4.pdf | 12 Aug 2025 |
| Form 1File: FORM 1-ARMORS NAGAR-Q1-24-25.pdf | 12 Aug 2025 |
| Form 2File: Armors Nagar-Form-2.pdf | 12 Aug 2025 |
| Form 3File: Armors Nagar-Form 3.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Armors Nagar-Form 3.pdf | 12 Aug 2025 |
| Form 1File: Armors Nagar-Form-1.pdf | 12 Aug 2025 |
| Form 2File: Armors Nagar-Form-2.pdf | 12 Aug 2025 |
| Form 3File: Armors Nagar-Form 3.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Armors Nagar-Form 3.pdf | 12 Aug 2025 |
| Form 1File: Form 1.pdf | 12 Aug 2025 |
| Form 2File: Form 2.pdf | 12 Aug 2025 |
| Form 3File: Form 3.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Form 3.pdf | 12 Aug 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Armors Nagar-Form-1.pdf | 11 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 11 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Armors Nagar-Form 3.pdf | 11 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Armors Nagar-Form-2.pdf | 11 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 11 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1-ARMORS NAGAR-Q1-24-25.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-ARMORS NAGAR-Q1-24-25.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-ARMORS NAGAR-Q1-24-25.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Q4.pdf | 25 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Q4.pdf | 25 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q4.pdf | 25 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Q1.pdf | 16 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Q2.pdf | 16 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Q3.pdf | 16 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Q1.pdf | 16 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Q2.pdf | 16 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Q3.pdf | 16 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 16 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q2.pdf | 16 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q3.pdf | 16 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1 ARCHITECT'S CERTIFICATE-Q1-Armors Nagar.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1 ARCHITECT'S CERTIFICATE-Q2-Armors Nagar.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form-1 ARCHITECT'S CERTIFICATE-Q3-Armors Nagar.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q1-ARMORS NAGAR.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q2-ARMORS NAGAR.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 ENGINEER CERTIFICATE-Q3-ARMORS NAGAR.pdf | 15 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q1.pdf | 8 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q2.pdf | 8 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-RERA ARMORS DEVELOPERS-Q3.pdf | 8 Feb 2024 |
| Other - FinanceFile: DECLARATION.pdf | 25 May 2023 |
| Copy of the legal title reportFile: Annexure to Format A.pdf | 13 May 2023 |
| Other - TechnicalFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf | 13 May 2023 |
| Building plan approvalFile: Details of 32 Flats and 21 Duplexes.pdf | 6 May 2023 |
| Building plan approvalFile: Block A and B, Area Of Statement, Building wings.pdf | 6 May 2023 |
| Building plan approvalFile: Sanction plan of Floorwise.pdf | 6 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Details of 32 Flats and 21 Duplexes.pdf | 6 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Block A and B, Area Of Statement, Building wings.pdf | 6 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Sanction plan of Floorwise.pdf | 6 May 2023 |
| Copy of the legal title reportFile: Format A Title Report.pdf | 4 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A SHARDHA KHOBRAGADE.pdf | 4 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Dissclosure of Interest.pdf | 4 May 2023 |
| Other - TechnicalFile: Reply 2.pdf | 4 May 2023 |
| Other - TechnicalFile: Reply Desk 1 Authority.pdf | 14 Apr 2023 |
| Layout approvalFile: Higlited Sanction PlanPlan.pdf | 12 Apr 2023 |
| Details of encumbrances concerned to FinanceFile: Non Encumbrance certificate .pdf | 12 Apr 2023 |
| Details of encumbrances concerned to LegalFile: Non Encumbrance certificate .pdf | 12 Apr 2023 |
| Copy of Layout Approval (in case of layout)File: Higlited Sanction PlanPlan.pdf | 12 Apr 2023 |
| Declaration about Commencement CertificateFile: Format D .pdf | 12 Apr 2023 |
| CERSAI detailsFile: Undertaking for no security interest .pdf | 12 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 12 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_.pdf | 29 Mar 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Wardha
Computed across the 290+ Wardha projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ARMORS NAGAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MOUZA JUNONA290+ in Wardha
Filed coordinates, straight-line distance. 6 registered projects within 2 km.
Subhash Residency
Abhijit Subhash Bidkar and Amol Subhash Bi
Baramati City
ATUL NAMDEO WANDILE
KESARIYA PARK
RAKESH MOHANRAO MADE
baramati city
MAHESH SHANKARRAO GULHANE
SAHARA TOWN
HARE KRISHNA LAND DEVELOPERS
Omkar Nagar
A. V. Infratech
See every Wardha project, with the district possession charts
Builder: ARMORS DEVELOPERS PRIVATE LIMITED
ARMORS DEVELOPERS PRIVATE LIMITED has 2 registrations on MahaRERA, including ARMORS NAGAR and ARMORS ESTATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Wardha district page.
Frequently asked questions
What does it mean that ARMORS NAGAR shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ARMORS NAGAR is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARMORS NAGAR?
The registered promoter entity is ARMORS DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARMORS NAGAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ARMORS NAGAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARMORS NAGAR?
The professionals named in the filing: Architect: Mr. Kiran Digamber Purohit; Engineer: Pankaj Ashokrao Landge; Chartered Accountant: RITESH VIRANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARMORS NAGAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback