Home / Browse projects / Raigarh, Maharashtra / ARIHANT ANANT
ARIHANT ANANT
RG-MH-30233 · RERA P52000030053 · Last updated on MahaRERA portal: 17 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARIHANT ANANT is a Others project by MAHALAXMI COTTON MILLS in Raigarh, Maharashtra, registered with MahaRERA as P52000030053 on 26 Jul 2021. Possession is promised by 30 Dec 2026. 114 of the 148 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.
At a glance
Project
- NameARIHANT ANANT
- TypeOthers
- Location
- Survey No. 112/(11)/(14)/5
- Taloja
- Taloje Majkur
- Panvel
- Raigarh
- 410208
- Pincode410208
- RERA no.P52000030053
- ReraGenie IDRG-MH-30233
Builder
- NameMAHALAXMI COTTON MILLS
- Entity typePartnership
- PartnerPARTH ASHOKKUMAR CHHAJER
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on26 Jul 2021
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed91 files
Current status
Figures as on 17 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ARIHANT ANANT | NA | 10 | 10 | 143 | 5 | 148 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 17 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.
ARIHANT ANANT: 86% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 82% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 98% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 62% |
Progress on shared amenities15
As on 17 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 40% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 50% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 10% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed92
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| ARIHANT ANANT | NA | Rs 36.25 cr | Rs 31.17 cr |
| - | NA | Rs 2.02 cr | Rs 1.45 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOGITA BHANDARKAR |
| Engineer | KALEEM SAYYAD |
| Chartered Accountant | ANJANI KUMAR GOYAL |
| Chartered Accountant | Kailash Chand Jain & Co. |
| Partner | Role in project |
|---|---|
| MAHALAXMI COTTON MILLS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Apr 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Apr 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2026
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: March 2026 Form 1.pdf | 17 Apr 2026 |
| Withdrawal Update Form 2File: March 2026 Form 2.pdf | 17 Apr 2026 |
| Withdrawal Update Form 3File: March 2026 Form 3.pdf | 17 Apr 2026 |
| Layout approvalFile: Page 1 (Highlighted) (Parking) (Permissible and Sanctioned BUA).pdf | 16 Apr 2026 |
| Building plan approvalFile: Page 2 - Floor Plans.pdf | 16 Apr 2026 |
| Building plan approvalFile: Page 3 - Floor Plans.pdf | 16 Apr 2026 |
| Building plan approvalFile: Page 4 - Elevation.pdf | 16 Apr 2026 |
| Withdrawal Update Form 1File: Form 1_Anant_31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_Anant Ph I_31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Form 3_Anant_31122025.pdf | 29 Jan 2026 |
| Withdrawal Update Form 1File: Form 1_ANANT PHASE I.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form 2_Anant_30092025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Arihant Anant_30092025.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: ArihantAnant_Form5_FY2425.pdf | 16 Oct 2025 |
| Form 2A (FY 2024-2025)File: Arihant Anant.pdf | 4 Oct 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Anant_310325.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Anant_310325.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Anant Ph-I_310325_SIGNED.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE signed.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Anant.pdf | 19 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Anant.pdf | 19 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anant.pdf | 19 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 19 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Anant.pdf | 7 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Anant Ph I.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - ARIHANT ANANT_SIGNED.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anant_SIGNED.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A ANANT FY 23-24.pdf | 23 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARIHANT ANANT.PDF | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Anant I.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure signed.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30062024 Anant SIGNED.pdf | 20 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Anant_FY 22-23.pdf | 7 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Anant Dec 23 SIGNED.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: Anant Mar 24 SIGNED.pdf | 28 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Anant 31032024.pdf | 6 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Anant 31122023.pdf | 4 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032024 Anant.pdf | 23 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form I - ARCHITECT CERTIFICATE - ANANT PROJECT.PDF | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anant Phase.pdf | 31 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anant Phase.pdf | 31 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Arihant Anant Phase 1.pdf | 21 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I - ARIHANT ANANT PHASE I 30 SEPTEMBER 2023.PDF | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 RERA Anant Ph I Sept 2023.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anant-1.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Arihant Anant.pdf | 9 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARIHANT ANANT A - FORM 1 - ARCHITECT CERTIFICATE 30TH JUNE 2023.PDF | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA Anant 1 June 2023.pdf | 19 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 anant.pdf | 8 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ANANT PHASE I - 31 MARCH 23.PDF | 21 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: anant_31032023.PDF | 21 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anant i_11zon.pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JUNE 22 Anant.pdf | 9 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sept 22 Anant.pdf | 9 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Dec 22 Anant.pdf | 9 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ANANT 21DEC21.pdf | 3 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ANANT DEC21.pdf | 3 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ANANT DEC22.pdf | 3 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ANANT DEC22.pdf | 3 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ANANT JUNE22.pdf | 3 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ANANT MARCH22.pdf | 3 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA ANANT SEPT22.pdf | 3 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2.pdf | 2 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3.pdf | 2 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANANT FORM 1 21ST DECEMBER 2021.PDF | 2 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANANT FORM 1 30TH JUNE 2022.PDF | 2 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANANT FORM 1 30TH SEPTEMBER 2022.PDF | 2 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANANT FORM 1 31ST DECEMBER 2021.PDF | 2 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANANT FORM 1 31ST DECEMBER 2022.PDF | 2 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ANANT FORM 1 31ST MARCH 2022.PDF | 2 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1.pdf | 2 Mar 2023 |
| Layout approvalFile: LAYOUT PLAN_RERA1.pdf | 16 Jul 2021 |
| Building plan approvalFile: 2 - 1ST FLOOR AND PLOT AREA CALCULATION.pdf | 16 Jul 2021 |
| Building plan approvalFile: 3 - TYPICAL FLOOR PLAN AND MULTIPURPOSE ROOM.pdf | 16 Jul 2021 |
| Building plan approvalFile: 4 - ELEVATION AND SECTIONS.pdf | 16 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN_RERA1.pdf | 16 Jul 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 - 1ST FLOOR AND PLOT AREA CALCULATION.pdf | 16 Jul 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 - TYPICAL FLOOR PLAN AND MULTIPURPOSE ROOM.pdf | 16 Jul 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: 4 - ELEVATION AND SECTIONS.pdf | 16 Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ARIHANT ANANT on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Taloja5,900+ in Raigarh
Plot No -1 Sector -29 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
Plot No.-1 Sector -39 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
Plot No -1 Sector -31 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
SAI SUNCITY PHASE II
Chariot Properties LLP
Plot No. 14 Sector-37 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
ARIHANT ADARSH PHASE I
ARIHANT SUPERSTRUCTURES LIMITED
See every Raigarh project, with the district possession charts
Builder: MAHALAXMI COTTON MILLS
MAHALAXMI COTTON MILLS has 2 registrations on MahaRERA, including ARIHANT ANANT and ARIHANT ANANT PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if ARIHANT ANANT is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARIHANT ANANT?
The registered promoter entity is MAHALAXMI COTTON MILLS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARIHANT ANANT?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ARIHANT ANANT?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARIHANT ANANT?
The professionals named in the filing: Architect: YOGITA BHANDARKAR; Engineer: KALEEM SAYYAD; Chartered Accountant: ANJANI KUMAR GOYAL; Chartered Accountant: Kailash Chand Jain & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARIHANT ANANT?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback