Home / Browse projects / Raigarh, Maharashtra / ARIHANT AMISHA PHASE III
ARIHANT AMISHA PHASE III
By ARIHANT AASHIYANA PRIVATE LIMITED
RG-MH-30363 · RERA P52000030293 · Last updated on MahaRERA portal: 16 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 11 other registrations.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARIHANT AMISHA PHASE III is a Residential / Group Housing project by ARIHANT AASHIYANA PRIVATE LIMITED in Raigarh, Maharashtra, registered with MahaRERA as P52000030293 on 15 Aug 2021. Possession is promised by 30 Dec 2027. 33 of the 166 units on this registration are recorded sold or booked, and 10 of 44 construction stages are filed complete.
At a glance
Project
- NameARIHANT AMISHA PHASE III
- TypeResidential / Group Housing
- Location
- MAOHDAR
- MAHODAR
- Panvel
- Raigarh
- 410208
- Pincode410208
- RERA no.P52000030293
- ReraGenie IDRG-MH-30363
Builder
- NameARIHANT AASHIYANA PRIVATE LIMITED
- Entity typeCompany
- DirectorsASHOKKUMAR BHANWARLAL CHHAJER, PARTH ASHOKKUMAR CHHAJER
- Other registrations11 more →
- Completed7 of 12
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Aug 2021
- Promised completion30 Dec 2027
- Revised completionNone
- Buildings4 building records
- Documents filed93 files
Current status
Figures as on 16 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D1 | NA | 8 | 8 | 70 | 0 | 70 |
| D2 | NA | 8 | 8 | 12 | 0 | 12 |
| D3 | NA | 8 | 8 | 42 | 0 | 42 |
| D4 | NA | 8 | 8 | 42 | 0 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 16 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 80%.
D146%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 32% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D224%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D324%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D446%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 32% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 15% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed62
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| D1 | 22 | 22 |
| D2 | 12 | 12 |
| D3 | 14 | 14 |
| D4 | 14 | 14 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| D1 | NA | Rs 5.06 cr | Rs 2.96 cr |
| D2 | NA | Rs 5.06 cr | Rs 2.96 cr |
| D3 | NA | Rs 5.06 cr | Rs 2.96 cr |
| D4 | NA | Rs 5.06 cr | Rs 2.96 cr |
| - | NA | Rs 2.42 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | YOGITA BHANDARKAR |
| Engineer | KALEEM SAYYAD |
| Chartered Accountant | ANJANI KUMAR GOYAL |
| Chartered Accountant | Ummed Jain & Co. |
| Partner | Role in project |
|---|---|
| ARIHANT AASHIYANA PRIVATE LIMITED | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2027
Documents filed93
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: 12 Form 1_AMISHA PH III_310326.pdf | 16 Apr 2026 |
| Withdrawal Update Form 2File: Form 2_Amisha Ph III_250306.pdf | 16 Apr 2026 |
| Withdrawal Update Form 3File: 12 Form 3_Amisha Ph III_250326.pdf | 16 Apr 2026 |
| Withdrawal Update Form 1File: Form 1_Amisha Ph III_31122025_signed.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_Amisha Ph III_31122025.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: Form 3_Amisha Ph III_31122025.pdf | 28 Jan 2026 |
| Withdrawal Update Form 1File: Form 1_AMISHA PHASE III_30092025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form 2_Amisha Ph III_30092025.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3_Amisha Ph III_30092025.pdf | 17 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5_Arihant Amisha Phase-III.pdf | 17 Oct 2025 |
| Form 2A (FY 2024-2025)File: Arihant Amisha Phase III.pdf | 4 Oct 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-Amisha Ph III_310325.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Amisha Ph-III_310325.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Amisha Ph III_310325_SIGNED__.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - AMISHA PHASE III.pdf | 19 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Amisha Phase III.pdf | 19 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - AMISHA PHASE III.pdf | 19 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE SIGNED.pdf | 19 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Amisha Phase III_Signed.pdf | 11 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Amisha Ph III.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE_SIGNED.pdf | 21 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I -AMISHA PHASE III_SIGNED.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amisha Phase 3 SIGNED.pdf | 19 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A AMISHA III FY 23-24.pdf | 23 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Amisha III.pdf | 22 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arihant Amisha Phase III.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure SIGNED.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 30062024 Amisha Phase 3 SIGNED.pdf | 20 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_Amisha Phase 3_FY 22-23.pdf | 7 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Amisha III - Dec 23 SIGNED.pdf | 28 May 2024 |
| Disclosure of sold/ booked inventoryFile: Amisha III - Mar 24 SIGNED.pdf | 28 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Amisha Phase III 31032024.PDF | 4 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Amisha Phase III 31032024.pdf | 4 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I ARIHANT AMISHA III 31ST DECEMBER 2023.PDF | 3 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 AMISHA PH3 DEC2023.pdf | 3 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032024 Amisha Phase 3 SIGN.pdf | 23 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amisha Phase-3.pdf | 7 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM I ARIHANT AMISHA PHASE III - 30 SEPTEMBER 2023.PDF | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 RERA Amisha Ph III Sept 2023.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Arihant Amisha Phase 3-Aashiyana.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amisha Phase -3.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A-Arihant Amisha Phase III.pdf | 9 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amisha III.pdf | 20 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARIHANT AMISHA PHASE III - FORM I - ARCHITECT CERTIFICATE 30TH JUNE 2023.PDF | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA Amisha III June 2023.pdf | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 RERA AMIHSA PH3 MARCH2023.pdf | 19 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: aMISHA III_11zon1.pdf | 19 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AMISHA PHASE III 31 MARCH 23.PDF | 18 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amisha Phase3 21122021 Architect Certificate.pdf | 21 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amisha Phase3 30062022 Architect CertificatE.pdf | 21 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amisha Phase3 30092022 Architect Certificate.pdf | 21 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amisha Phase3 31032022 Architect Certificate.pdf | 21 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amisha Phase3 31122021 Architect Certificate.pdf | 21 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amisha Phase3 31122022 Architect Certificate.pdf | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 amisha 31122022.PDF | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 amisha ph3 30062022.PDF | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 amisha ph3 31122021.PDF | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 amisha ph3 21122021.PDF | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 amisha ph3 30092022.PDF | 21 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 amisha ph3 31032022.PDF | 21 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 amisha iii 211221.pdf | 21 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 amisha iii 300622.pdf | 21 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 amisha iii 300922.pdf | 21 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 amisha iii 310322.pdf | 21 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 amisha iii 311221.pdf | 21 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 amisha iii 311222.pdf | 21 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form2 amisha ph3 31032022.PDF | 21 Feb 2023 |
| Details of encumbrancesFile: Declaration for Encumberance_Anmol Phase III123.pdf | 4 Aug 2021 |
| Declaration in FORM BFile: Form-B_Amisha III_RERA.pdf | 4 Aug 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1_Amisha III_RERA.pdf | 4 Aug 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_Arihant Amisha Phase III.pdf | 4 Aug 2021 |
| Layout approvalFile: LAYOUT 01_RERA.pdf | 29 Jul 2021 |
| Layout approvalFile: LAYOUT 02_RERA.pdf | 29 Jul 2021 |
| Building plan approvalFile: Building Plan_1_RERA.pdf | 29 Jul 2021 |
| Building plan approvalFile: Building Plan_2.pdf | 29 Jul 2021 |
| Building plan approvalFile: Building Plan_3.pdf | 29 Jul 2021 |
| Building plan approvalFile: Building Plan_4.pdf | 29 Jul 2021 |
| Building plan approvalFile: Building Plan_5.pdf | 29 Jul 2021 |
| PAN CardFile: PAN_Arihant Aashiyana.PDF | 29 Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 11 other registrations, which the RERA portal never shows together
- All 93 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ARIHANT AMISHA PHASE III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAHODAR5,900+ in Raigarh
Plot No -1 Sector -29 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
Plot No.-1 Sector -39 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
Plot No -1 Sector -31 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
SAI SUNCITY PHASE II
Chariot Properties LLP
Plot No. 14 Sector-37 Taloja
CITY AND INDUSTRIAL DEVELOPMENT CORPORATIO
ARIHANT ADARSH PHASE I
ARIHANT SUPERSTRUCTURES LIMITED
See every Raigarh project, with the district possession charts
Builder: ARIHANT AASHIYANA PRIVATE LIMITED
ARIHANT AASHIYANA PRIVATE LIMITED has 12 registrations on MahaRERA, including ARIHANT ANSHULA and ARIHANT AMISHA PHASE I. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if ARIHANT AMISHA PHASE III is delayed beyond 30 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARIHANT AMISHA PHASE III?
The registered promoter entity is ARIHANT AASHIYANA PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARIHANT AMISHA PHASE III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ARIHANT AMISHA PHASE III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARIHANT AMISHA PHASE III?
The professionals named in the filing: Architect: YOGITA BHANDARKAR; Engineer: KALEEM SAYYAD; Chartered Accountant: ANJANI KUMAR GOYAL; Chartered Accountant: Ummed Jain & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARIHANT AMISHA PHASE III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback