Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
11 of 11Construction stages doneevery applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 84 documents Report an error

ARADHANA ENCLAVE is a Residential / Group Housing project by A C JAIN BUILDERS AND DEVELOPERS LLP in Nashik, Maharashtra, registered with MahaRERA as P51600031439 on 23 Oct 2021. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameARADHANA ENCLAVE
  • TypeResidential / Group Housing
  • Location
    • GOPAL NAGAR
    • ARTILLERY CENTER ROAD NASIKROAD
    • Nashik
    • 422101
  • Pincode422101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600031439
  • ReraGenie IDRG-MH-14083

Builder

  • NameA C JAIN BUILDERS AND DEVELOPERS LLP
  • Entity typePartnership
  • GSTIN27ABOFA9179M1ZH
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerVIDHYA ABHAY JAIN TODARWAL
  • Other registrations7 more →
  • Completed3 of 8
  • Past their filed date1
  • Declared earlier projects11 →

Key dates

this monthRegisteredOct 2021First promiseDec 2022Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Oct 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2022)
  • Buildings1 building record
  • Documents filed84 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ARADHANA ENCLAVENA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

ARADHANA ENCLAVE: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Closed/Covered14

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area631 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
ALOK NILKANTH CHANDRATRENashik (M Corp.)Nashik

Approvals and building plan

Permissible FSI1978.25
Proposed, not sanctioned1,978 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHARANPUR ROAD NASIK

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAR DINESH UGHADE
ArchitectAR MOHIT KANAVAT
EngineerSANJAY SHRIRAM PATIL
Chartered AccountantCA Paresh P. Sabadra
PartnerRole in project
A C JAIN BUILDERS AND DEVELOPERS LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600019434Dec 2022 → Dec 2025

Reason as filed by the promoterWe Have Completed Said Project But Due To Low Sale and Gst Liability To Be Paid On Completion, We Need Said Extention.

EXT51600013697Dec 2022 → Dec 2023

Reason as filed by the promoterProject Completion Date Revision for Sub Registrar Agreement Execution Purpose.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 23 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 23 Sep 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Mar 2025

Documents filed84

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 84 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Rera Audit Report 23-24.pdf24 Mar 2025
Other - TechnicalFile: Architect Certificate - Form 4-Aradhana Enclave.pdf4 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC and Form 4.pdf1 Mar 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Aradhana Enclave jun24.pdf22 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Aradhana Enclave1.pdf22 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Aradhana Enclave.pdf22 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect Certificate_June 24.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect Certificate_Sept 24.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architect Certificate_Dec 24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1_CA_Cert_Enclave_June_24[1].pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2_CA_Cert_Enclave_Sept_24[1].pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA DEC 24.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer Certificate_Enclave_June 24.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer Certificate_Enclave_Sept 24.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_Enclave_Dec 24.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect Certificate_Enclave_March 24.pdf5 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA Cert_Enclave_March 2024 signed.pdf5 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer Certificate_Enclave_March 24.pdf5 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Aradhana Enclave.pdf20 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Aradhana Enclave.pdf20 Jun 2024
Declaration in FORM BFile: Form B - Aradhana Enclave.pdf19 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Mar 23 - Aradhana Enclave.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Aradhana Enclave.pdf19 Apr 2024
CERSAI detailsFile: Declaration-Nil-CERSAI Report - Aradhana Enclave.pdf19 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations - Aradhana Enclave.pdf19 Apr 2024
CERSAI detailsFile: CERSAI_Search_Report_200302903290_For_Asset_Based_Search_03_04_2024_10_13_11_208.pdf3 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organization.pdf3 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 CA Certificate June 2023_signed.pdf29 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 CA Certificate Sept 2023_Signed.pdf29 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 CA Certificate Dec 2023_Signed.pdf29 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect Certificate_June 23.pdf27 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect Certificate_Sept 23.pdf27 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architect Certificate_Dec 23.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer Certificate_Aradhana Enclave_June 23.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer Certificate_Aradhana Enclave_Sept 23.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer Certificate_Aradhana Enclave_Dec 23.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Aradhana Enclave.pdf27 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Aradhana Enclave - Sep 23.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Aradhana Enclave - Dec 23.pdf26 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_New format from June 22.pdf29 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_New format from Sep 22.pdf29 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_New format from Dec 22.pdf29 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_New format from Mar 23.pdf29 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer Certificate_ Enclave_June 22.pdf29 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Enclave CA certificate Jun'22.pdf29 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Enclave CA certificate Sept'22.pdf29 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Enclave CA certificate Dec'22.pdf29 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Enclave CA certificate Mar'23.pdf29 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Enclave_from Dec 21.pdf29 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_Enclave_MAR 22.pdf29 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT-ENCLAVE-DEC-21.pdf29 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT- ENCLAVE-MAR-22.pdf29 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 Engineer Certificate_Aradhana Enclave_dec21.pdf23 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer Certificate_Aradhana Enclave_March22.pdf23 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA_ Audit Report_ Enclave_signed_ 21 22.pdf23 May 2023
Other - TechnicalFile: Quality Assurance Certificate Form 2A- Aradhana Enclave.pdf6 May 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold INVENTORY - MAR23 .pdf14 Apr 2023
Declaration about Commencement CertificateFile: FORM D - DECLARATION OF COMMENCEMENT CERTIFICATE.pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 07009 2021 .pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1012 2021.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 0103 2022.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 0406 2022.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 0709 2022.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1012 2022.pdf2 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold INVENTORY .pdf2 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 - 2021-22.pdf2 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Master 8891.pdf2 Feb 2023
Details of encumbrancesFile: ENCLAVE_ENC.pdf26 Nov 2022
Details of encumbrancesFile: ENC_MORTGAGE.pdf26 Nov 2022
Copy of the legal title reportFile: Title nEw Rera.pdf14 Oct 2021
Proforma of Allotment letterFile: Agmt to Sale_Format.pdf14 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Binder1.pdf8 Oct 2021
Declaration in FORM BFile: Form B ACJLLP.pdf24 Sep 2021
Building plan approvalFile: Full page photo.pdf23 Sep 2021
PAN CardFile: PAN Alok.pdf23 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: Full page photo.pdf23 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf23 Sep 2021
Declaration about Commencement CertificateFile: commencement declaration.pdf23 Sep 2021
Layout approvalFile: LAYOUT PLAN.pdf18 Aug 2021

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

9 delivered on promise2 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
AbhinavS. No. G. No. 87 1 2 11 3 of Deolali Shiwar Nashik - 42210178-OngoingDec 2026Dec 2026
AARADHYA RESIDENCY PHASE IIS NO 31 2 1 19 Nashik Maharashtra63-OngoingDec 2026Dec 2026
ARADHANA ENCLAVES NO 40 8 9 10 PLOT NO 4 Nashik Maharashtra14-OngoingDec 2025Dec 2025
ARRPAN HOUSINGP51600022627VIHITGAON, Nashik415Oct 2019CompletedApr 2025Jun 2024
AARADHANA RESIDENCY - AS no - 39 6 40 6 7 2 3 - Plot No 25 to 46 Nashik Maharashtra84-CompletedDec 2022Dec 2022
AARADHANA RESIDENCY - BS NO - 39 6 40 6 7 2 3 PLOT NO 62 65 Nashik Maharashtra16-CompletedDec 2022Dec 2022
AARADHANA VILLAS39 6 40 6 7 2 3 Nashik Maharashtra13-CompletedDec 2020Dec 2020
ABHINANDAN HEIGHTSANUSAYA NAGAR NEAR MHADA BUILDINGS MAKHMALABAD NASIK48-CompletedJun 2019Late, Jul 2019
KAPALESHWAR CO OP HSG SOCIETYOPP SURANA HOSPITAL ARTILLERY CENTER ROAD NASIKROAD38-CompletedMar 2019Mar 2019
AARADHYA RESIDENCYA WING OPP JADHAV HOSPITAL JAGTAP MALA ANAND NAGAR NASIKROAD45-CompletedJun 2018May 2018
AANUSHREE RESIDENCYPLOT NO 1 TO 8 BEHIND KAMAL AUTO ASHOKA MARG OPP ASHOKA SCHOOL NASIK53-CompletedMar 2018Late, May 2018

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 36 months
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ARADHANA ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ARTILLERY CENTER ROAD NASIKROAD4,100+ in Nashik

2 kmARADHANA ENCLAVECompleted 32Lapsed / revoked 8Other 31Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: A C JAIN BUILDERS AND DEVELOPERS LLP

A C JAIN BUILDERS AND DEVELOPERS LLP has 8 registrations on MahaRERA, including ARRPAN HOUSING and AARADHANA RESIDENCY - A. Its filings disclose 11 earlier MahaRERA projects: declares 9 of 11 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if ARADHANA ENCLAVE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ARADHANA ENCLAVE?

The registered promoter entity is A C JAIN BUILDERS AND DEVELOPERS LLP, a partnership as per the filing. Its GSTIN 27ABOFA9179M1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ARADHANA ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ARADHANA ENCLAVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ARADHANA ENCLAVE?

The professionals named in the filing: Architect: AR DINESH UGHADE; Architect: AR MOHIT KANAVAT; Engineer: SANJAY SHRIRAM PATIL; Chartered Accountant: CA Paresh P. Sabadra. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARADHANA ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARADHANA ENCLAVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARADHANA ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.