Home / Browse projects / Mumbai Suburban, Maharashtra / ANDHERI INDIRA NAGAR CHS LIMITED

Registration lapsed No litigation declared Others project

ANDHERI INDIRA NAGAR CHS LIMITED

By JASPAL SINGH SURI

RG-MH-66465 · RERA P51800014152 · Last updated on MahaRERA portal: 10 Jan 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 66 months
  • 6 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
7Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

ANDHERI INDIRA NAGAR CHS LIMITED is a Others project by JASPAL SINGH SURI in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800014152 on 9 Nov 2017. Possession was promised by 30 Jun 2024 and is now 28 months past that date. The completion date has moved by 66 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameANDHERI INDIRA NAGAR CHS LIMITED
  • TypeOthers
  • Location
    • J.P. Road
    • Andheri West
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800014152
  • ReraGenie IDRG-MH-66465

Builder

  • NameJASPAL SINGH SURI
  • Entity typeIndividual

Key dates

28 months past promisethis monthRegisteredNov 2017First promiseDec 2018Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Nov 2017
  • Promised completion30 Jun 2024
  • Revised completionRevised to 30 Jun 2024 (originally 31 Dec 2018)
  • Buildings2 building records
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANDHERI INDIRA NAGAR CHS LIMITED WING BNA80000
ANDHERI INDIRA NAGAR CHS LIMITED WING CNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

ANDHERI INDIRA NAGAR CHS LIMITED WING B90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ANDHERI INDIRA NAGAR CHS LIMITED WING C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Open Space22

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,400 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5256.14
Proposed, not sanctioned5,256 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLA SARENA PLOT NO 34 J P ROAD ANDHERI WEST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAARYA LIFESTYLE LLP
EngineerMOHILE AND ASSOCIATES
Chartered AccountantSudhanshu Shekhar Singh
PartnerRole in project
JASPAL SINGH SURI-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013132Dec 2018 → Mar 2023

Reason as filed by the promoterRespected Sir/Madam, Commercial project 100% completed - Occupation Certificate (OC) applied. Residential project 90% completed and expected to be completed in 1-2 months. The marginal delay is due to heavy increase in cost of construction and funding and recovery issues. Delay in getting few compliance's and non availability of specific materials.

EXT51800010225Dec 2018 → Jun 2022

Reason as filed by the promoterDue to global pandemic all over the world (Outbreak of coronavirus), and lockdown in maharashtra, many construction labours left the city and also non-availability of construction materials we were not able to complete the project in due time and therefore we request you to kindly extend the period of registration till 30.06.2022.

EXT51800000818Dec 2018 → Dec 2020

Reason as filed by the promoterCertain eligibility of slum dwellers had been received with revised supplementary Annexure II from Competent Authority (MHADA) .As such the developer had to obtain revised LOI and amended plan with further CC from SRA. The application with respect to the same was filed with SRA by the developer about 1 year back. The revised LOI with amended plan and further CC has been received by the developer on 25th October, 2018. Hence, the completion date for the project is extended from 31st December, 2018 to 31st October, 2019.

EXT51800005568Dec 2018 → Dec 2020

Reason as filed by the promoterAs it is SRA project, some permissions were delayed.

EXT51800018673Dec 2018 → Jun 2024

Reason as filed by the promoterWe have applied for the OC with the appropriate authority which is under process. At the time of hearing with RERA authority for delay in completion of project, we had given the reason for delay in OC and it was instructed to make an application for extension of project and to do the arrangements for OC at the earliest possible.

EXT51800016907Dec 2018 → Sep 2023

Reason as filed by the promoterWe have applied for OC with the appropriate authority which is under process. At the time of hearing with RERA authority, we were instructed to make an application for extension. Hence, we are hereby applying for extension till 30/09/2023

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000079229Bela AgarwalJaspal Singh09/05/2019
CC006000000078507Mrs Mona GuptaM/s Kanwal Corporation Builders and Developers18/03/2019
CC006000000100384Manjit Singh GarkelJaspal Singh Suri06/08/2019
CC006000000100386Renu AghiJaspal Singh Suri06/08/2019
CC006000000197033FAROOQ ANSARIKANWAL CORPORATION24/05/2021
CC006000000197034WAHIDA ANSARIKANWAL CORPORATION BUILDERS & DEVELOPERS24/05/2021
CC006000000292479Bela Suresh AgarwalJaspal SIngh Suri28/08/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Jun 2023

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Affidavit Cum Declaration.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Agreed and Accepted- Form 5.pdf10 Jan 2024
Declaration in FORM BFile: Form B_Affidavit.pdf28 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf28 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A.pdf28 Jun 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLDBOOKED INVENTORY.pdf28 Jun 2023
Certificates of CA (Form 3)File: Form 3.pdf28 Jun 2023
Certificates of CA (Form 5)File: Form 5.pdf28 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ocupation Certificate_C Wing.pdf26 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate_C Wing.pdf24 Mar 2023
Layout approvalFile: Layout Plan.pdf23 Feb 2023
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf23 Feb 2023
Proforma of Agreement for saleFile: Proforma Agreement for sale.pdf13 Feb 2023
Declaration about Commencement CertificateFile: Form D-Declaration about CC.pdf31 Dec 2022
Declaration in FORM BFile: Form B RERA_2022.pdf31 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 RERA_2022.pdf31 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM-2A RERA_2021-22.pdf31 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold booked Inventory_2022.pdf31 Dec 2022
Certificates of CA (Form 3)File: Form 3 RERA.pdf31 Dec 2022
Certificates of CA (Form 5)File: Form5_2020-21.pdf31 Dec 2022
Certificates of CA (Form 5)File: Form5_2021-22.pdf31 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form5_2020-21.pdf31 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5_2021-22.pdf31 Dec 2022
OtherFile: Intimation letter for formation of society.pdf8 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_Kanwal.pdf26 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_Kanwal.pdf26 Jul 2021
Disclosure of sold/ booked inventoryFile: SOLD BOOKED UNSOLD INVENTORY AS ON 17TH JULY 2021.pdf17 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: CA CERTIFICATE_FORM 5.pdf17 Jul 2021
Declaration about Commencement CertificateFile: Declaration for CC.pdf10 Jul 2021
Disclosure of sold/ booked inventoryFile: Sold Unsold Booked Inventory.pdf10 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_Kanwal_Mukesh_ 2018-19.pdf10 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5_KANWAL CORPORATION.pdf10 Jul 2021
Certificates of CA (Form 3)File: Form 3_Kanwal Corporation.pdf30 Jan 2020
Certificates of CA (Form 5)File: Form 5_2018-19_Kanwal Corporation.pdf30 Jan 2020
OtherFile: Architect Certificate.pdf24 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate andheri indira nagar.pdf23 Jan 2020
Building plan approvalFile: IOD.pdf30 Oct 2018
Building Plan Approval (IOD)File: IOD.pdf30 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf30 Oct 2018
OtherFile: Revised LOI.pdf30 Oct 2018
Certificates of CA (Form 5)File: FORM 5_ KANWAL CORPORATION.pdf30 Sep 2018
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE_KANWAL CORPORATION.pdf21 Apr 2018
Building plan approvalFile: Intimation of Approval.pdf12 Aug 2017
Layout approvalFile: Commencement Certificate.pdf12 Aug 2017
PAN CardFile: PAN.pdf12 Aug 2017
Copy of the legal title reportFile: Legal Title Report.pdf12 Aug 2017
Details of encumbrancesFile: No Encumbrances Certificate.pdf12 Aug 2017
Copy of Layout Approval (in case of layout)File: Commencement Certificate.pdf12 Aug 2017
Building Plan Approval (IOD)File: Intimation of Approval.pdf12 Aug 2017
Declaration in FORM BFile: FORM B Affidavit cum declaration rev.pdf12 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Indiranagar CHSL FINAL.pdf12 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Indiranagar.pdf12 Aug 2017
Certificates of CA (Form 3)File: CA CERTIFICATE_FORM 3.pdf12 Aug 2017
Proforma of Allotment letterFile: Allotment Letter and Agreement for Sale.pdf12 Aug 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 66 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANDHERI INDIRA NAGAR CHS LIMITED on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri West6,700+ in Mumbai Suburban

2 kmANDHERI INDIRA NAGAR CHSCompleted 93Lapsed / revoked 58Other 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 271 registered projects within 2 km.

Builder: JASPAL SINGH SURI

JASPAL SINGH SURI has 1 registration on MahaRERA, including ANDHERI INDIRA NAGAR CHS LIMITED. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that ANDHERI INDIRA NAGAR CHS LIMITED shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ANDHERI INDIRA NAGAR CHS LIMITED is delayed beyond 30 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANDHERI INDIRA NAGAR CHS LIMITED?

The registered promoter entity is JASPAL SINGH SURI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANDHERI INDIRA NAGAR CHS LIMITED?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ANDHERI INDIRA NAGAR CHS LIMITED?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ANDHERI INDIRA NAGAR CHS LIMITED?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANDHERI INDIRA NAGAR CHS LIMITED?

The professionals named in the filing: Architect: AARYA LIFESTYLE LLP; Engineer: MOHILE AND ASSOCIATES; Chartered Accountant: Sudhanshu Shekhar Singh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANDHERI INDIRA NAGAR CHS LIMITED?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANDHERI INDIRA NAGAR CHS LIMITED. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANDHERI INDIRA NAGAR CHS LIMITED to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.