ANANTA
RG-MH-87550 · RERA P52100053184 · Last updated on MahaRERA portal: 30 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 2 complaints at MahaRERA
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ANANTA is a Others project by KK AND LEGACY DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100053184 on 17 Oct 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 43 of the 57 units on this registration are recorded sold or booked, and 32 of 44 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameANANTA
- TypeOthers
- Location
- RAHATANI
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411017
- Pincode411017
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100053184
- ReraGenie IDRG-MH-87550
Builder
- NameKK AND LEGACY DEVELOPERS
- Entity typeOthers
- Named personsM/S LEGACY LIFESPACES LLP, M/S HARSHA PROPERTIES, Mr. KIRANKUMAR SHANTILAL SHAH, MR PERSEUS ROHINTON BUHARIWALLA, MR ROSHAN KISHINCHAND RAMNANI
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Oct 2023
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
- Buildings4 building records
- Documents filed120 files
Current status
Figures as on 30 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 7 | 6 | 12 | 6 | 18 |
| WING B | NA | 6 | 6 | 12 | 6 | 18 |
| WING C | NA | 6 | 6 | 12 | 6 | 18 |
| WING COMMERCIAL | NA | 0 | 0 | 0 | 3 | 3 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 30 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
32 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Basement (if any), at 0%.
WING A73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING COMMERCIAL73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership8
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| MRS. HIRABAI GULAB KOKNE | Pimpri Chinchawad (M Corp.) | Pune |
| MRS. ALKA RAMESH KALE | Pimpri Chinchawad (M Corp.) | Pune |
| MRS. DHANASHREE NILESH BORHADE | Moshi | Pune |
| MRS. BHAGYASHREE SAURABH NEWALE | Chikhali | Pune |
| MR. AKASH BALU KOKNE | Pimpri Chinchawad (M Corp.) | Pune |
| MR. AJINKYA MAULI KOKNE | Pimpri Chinchawad (M Corp.) | Pune |
| MR. ATHARVA MAULI KOKNE | Pimpri Chinchawad (M Corp.) | Pune |
| BHAGYASHREE SAURABH NEWALE | Chikhali | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING A | NA | Rs 4.44 cr | Rs 4.44 cr |
| WING B | NA | Rs 4.44 cr | Rs 4.44 cr |
| WING C | NA | Rs 4.44 cr | Rs 4.44 cr |
| - | NA | Rs 2.68 cr | Rs 2.68 cr |
| WING COMMERCIAL | NA | Rs 1.22 cr | Rs 1.22 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MEHUL SHAH |
| Engineer | MR RUPESH MAHAMUNI |
| Chartered Accountant | PRAVIN PISE & ASSOCIATES |
| Chartered Accountant | G M Achhra and Associates |
| Partner | Role in project |
|---|---|
| KK AND LEGACY DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe respectfully submit that the said project has already been completed & has received Completion Certificate from the planning authority. However, the completion date mentioned on the registration certificate is 31/12/2024, due to which the project registration reflects as lapsed.
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12500154 | Amit Kataria | KK AND LEGACY DEVELOPERS | 16/01/2025 |
| CC12500154 | Amit Kataria | KK AND LEGACY DEVELOPERS | 16/01/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jun 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jun 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 20 Feb 2025
Documents filed120
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Form 2File: Form 2 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Form 3File: Form 3 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Circular Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 FY 2024-25.pdf | 30 Sep 2026 |
| Form 2A (FY 2025-2026)File: Form 2A - FY 2024-2025.pdf | 30 Sep 2026 |
| Form 5 (FY 2025-2026)File: Form 5 - FY 2024-2025.pdf | 30 Sep 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - FY 2024-2025.pdf | 9 Sep 2026 |
| Form 5 (FY 2024-2025)File: Form 5 - FY 2024-2025.pdf | 20 Aug 2026 |
| Form 2A (FY 2023-2024)File: Ananta Engineers Certificate 24-10-2024.pdf | 17 Aug 2026 |
| Form 5 (FY 2023-2024)File: Form 5.pdf | 17 Aug 2026 |
| Form 1File: Form-1- Q-3-23-24.pdf | 23 Jul 2026 |
| Form 2File: Form-2.pdf | 23 Jul 2026 |
| Form 3File: Form-3.pdf | 23 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 23 Jul 2026 |
| Form 1File: Form-1.pdf | 23 Jul 2026 |
| Form 2File: Form-2.pdf | 23 Jul 2026 |
| Form 3File: Form-3.pdf | 23 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold - Unsold.pdf | 23 Jul 2026 |
| Form 1File: Form-1.pdf | 23 Jul 2026 |
| Form 2File: Form-2.pdf | 23 Jul 2026 |
| Form 3File: Form-3.pdf | 23 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 23 Jul 2026 |
| Form 1File: Form-1.pdf | 23 Jul 2026 |
| Form 2File: Form-2.pdf | 23 Jul 2026 |
| Form 3File: From-3.pdf | 23 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold.pdf | 23 Jul 2026 |
| Form 1File: Form-1.pdf | 23 Jul 2026 |
| Form 2File: Form-2.pdf | 23 Jul 2026 |
| Form 3File: Form-3.pdf | 23 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: sold-unsold.pdf | 23 Jul 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3.pdf | 9 May 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ananta Shop Complition -383-2024.pdf | 20 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ananta B and C Residencial Complition - 807 - 23-10-2024.pdf | 20 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Anant A Builidng - Commercial Building Completion 96-2025.pdf | 20 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Ananta Sold-Unsold Building-A.pdf | 11 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Ananta Engineers Certificate 24-10-2024.pdf | 11 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ananta ENGINEER'S CERTIFICATE Date - 15-01-2025.pdf | 4 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 05-01-2025.pdf | 3 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 18-01-2025.pdf | 3 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 upload.pdf | 21 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ananta Architects Certificate 11-10-2024.pdf | 28 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Certificate.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ananata Engineers Certificate 18-10-2024.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold data - 30-09-2024 For All Buidings.pdf | 28 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 19-06-2024.pdf | 11 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate From-2 01-07-2024.pdf | 11 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-Unsold 30-06-2024.pdf | 11 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 - CA Certificate - ANANTA_compressed.pdf | 11 Jul 2024 |
| Layout approvalFile: 1) 01-05.pdf | 12 Jun 2024 |
| Building plan approvalFile: 2) 02-05.pdf | 12 Jun 2024 |
| Building plan approvalFile: 3) 03-05.pdf | 12 Jun 2024 |
| Building plan approvalFile: 4) 04-05.pdf | 12 Jun 2024 |
| Building plan approvalFile: 5) 05-05.pdf | 12 Jun 2024 |
| Copy of the legal title reportFile: 5) Ananta Search Report - 11-06-2024.pdf | 12 Jun 2024 |
| Copy of Layout Approval (in case of layout)File: 1) 01-05.pdf | 12 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2) 02-05.pdf | 12 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3) 03-05.pdf | 12 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4) 04-05.pdf | 12 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5) 05-05.pdf | 12 Jun 2024 |
| Layout approvalFile: 1-5.pdf | 6 May 2024 |
| Copy of Layout Approval (in case of layout)File: 1-5.pdf | 6 May 2024 |
| Building plan approvalFile: 01-05_compressed.pdf | 2 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 120 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ANANTA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near RAHATANI13,700+ in Pune
Filed coordinates, straight-line distance. 266 registered projects within 2 km.
VARDHAMAN SKYTOWN
VARDHAMAN ASSOCIATES
Tamara
Goldfinger Kataria Urban Developments
Sindhu Skies
G K Wonders
Legacy Kairos A and B Building
Legacy Lifespaces LLP
Amberwood Phase 1
SMP NAMRATA ASSOCIATES
121 Paradise Phase I
Wamanbhau & Daga Realtors LLP
Builder: KK AND LEGACY DEVELOPERS
KK AND LEGACY DEVELOPERS has 1 registration on MahaRERA, including ANANTA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if ANANTA is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ANANTA?
The registered promoter entity is KK AND LEGACY DEVELOPERS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ANANTA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ANANTA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ANANTA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ANANTA?
The professionals named in the filing: Architect: MEHUL SHAH; Engineer: MR RUPESH MAHAMUNI; Chartered Accountant: PRAVIN PISE & ASSOCIATES; Chartered Accountant: G M Achhra and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANANTA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback