ReraGenieLog inGet a buyer report

Home / Browse projects / Palghar, Maharashtra / ANANT SHREE

Registered No litigation declared Residential / Group Housing project

ANANT SHREE

By BRICKWORK INFRABUILD LLP

RG-MH-32800 · RERA P99000080427 · Last updated on MahaRERA portal: 2 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2031Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 15%
104 of 109Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

ANANT SHREE is a Residential / Group Housing project by BRICKWORK INFRABUILD LLP in Palghar, Maharashtra, registered with MahaRERA as P99000080427 on 4 Jun 2025. Possession is promised by 31 Dec 2031. 5 of the 109 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameANANT SHREE
  • TypeResidential / Group Housing
  • Location
    • Near Sky City
    • Nallasopara West
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401203
  • Pincode401203
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000080427
  • ReraGenie IDRG-MH-32800

Builder

  • NameBRICKWORK INFRABUILD LLP
  • Entity typePartnership
  • Authorized PartnerRahul Ramesh Thumar
  • PartnersDevendra Khemraj Jain, Hiren Trambaklal Parekh, Miitesh Arora

Key dates

this monthRegisteredJun 2025PromisedDec 2031

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Jun 2025
  • Promised completion31 Dec 2031
  • Revised completionNone
  • Buildings1 building record
  • Documents filed60 files

Current status

5%5 of 109 units booked
13.1%Work done, per cost certificate

Figures as on 2 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANANT SHREENA23231090109

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 2 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 15%.

ANANT SHREE: 29% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure15%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 2 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed140

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots140
Open Space140

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area806 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on24 Dec 2025

Approvals and building plan

Sanctioning authorityVVCMC
Permissible FSI5898.45
Proposed, not sanctioned5,898 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOKUL BUILDING,I ST FLOOR AGASHI ROAD, VIRAR (WEST)
Estimated costRs 19.50 cr
Cost incurredRs 2.55 cr
Work done13.08%
BuildingWingEstimatedIncurred
ANANT SHREENARs 17.00 crRs 2.55 cr
-NARs 2.50 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay Maloo & Associates
EngineerGR Consultants
Chartered AccountantMISHRA MAYEKAR & CO.
PartnerRole in project
BRICKWORK INFRABUILD LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2031

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1.pdf2 Jun 2026
Withdrawal Update Form 1File: Form-1.pdf2 Jun 2026
Withdrawal Update Form 2File: Form-2.pdf2 Jun 2026
Withdrawal Update Form 2File: Form-2.pdf2 Jun 2026
Withdrawal Update Form 3File: Brickwork Form-3.pdf2 Jun 2026
Withdrawal Update Form 3File: Brickwork Form-3.pdf2 Jun 2026
Withdrawal Update Form 1File: Form1.pdf13 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf13 Feb 2026
Withdrawal Update Form 3File: Form 3_11zon.pdf13 Feb 2026
Withdrawal Update Form 1File: Form1.pdf12 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf12 Feb 2026
Withdrawal Update Form 3File: Form3_11zon.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1.pdf24 Dec 2025
Withdrawal Update Form 1File: Form-1_11zon.pdf24 Dec 2025
Withdrawal Update Form 2File: Form 2.pdf24 Dec 2025
Withdrawal Update Form 2File: Form-2.pdf24 Dec 2025
Withdrawal Update Form 3File: Form 3 Jun-25 Certified_11zon.pdf24 Dec 2025
Withdrawal Update Form 3File: Form 3 Sep-25 Certified_11zon.pdf24 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (3)_11zon.pdf17 Apr 2025
Other - TechnicalFile: 5 Other - Legal (1).pdf17 Apr 2025
Other - TechnicalFile: 3 Other - Legal (1).pdf17 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: additional declaration.pdf31 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Layout Plan_11zon (1).pdf31 Mar 2025
Other - LegalFile: additional declaration.pdf31 Mar 2025
Deviation Report with respect to model copy of AgreementFile: no deviation afs.pdf31 Mar 2025
Proforma of Agreement for saleFile: AFS Draff.pdf31 Mar 2025
Building plan approvalFile: Layout Plan_11zon.pdf22 Mar 2025
Details of encumbrances concerned to FinanceFile: legal.pdf22 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Layout Plan_11zon.pdf22 Mar 2025
Other - LegalFile: Declaration cun undertaking.pdf22 Mar 2025
Other - LegalFile: Agreement for Sale 21-39_11zon.pdf22 Mar 2025
Other - LegalFile: Agreement for Sale 1-20_11zon.pdf22 Mar 2025
Other - LegalFile: Email.pdf22 Mar 2025
Details of encumbrances concerned to LegalFile: legal.pdf22 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Form-B Bank AC Declaration .pdf22 Mar 2025
Layout approvalFile: Layout_11zon.pdf10 Mar 2025
Building plan approvalFile: NA Order.pdf10 Mar 2025
PAN CardFile: company pan card.pdf10 Mar 2025
Copy of the legal title reportFile: TITLE SEARCH.pdf10 Mar 2025
Details of encumbrances concerned to FinanceFile: legal and finance.pdf10 Mar 2025
Copy of Layout Approval (in case of layout)File: Layout_11zon.pdf10 Mar 2025
Proforma of Allotment letterFile: AL Draf.pdf10 Mar 2025
Declaration in FORM BFile: Form B Affidavit Cum Declaration .pdf10 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (2).pdf10 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf10 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC Order_11zon.pdf10 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: NA Order.pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold and Unsold (1).pdf10 Mar 2025
Declaration about Commencement CertificateFile: declaration about cc.pdf10 Mar 2025
CERSAI detailsFile: Cersai report.pdf10 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: form A.pdf10 Mar 2025
Deviation Report with respect to Allotment letterFile: no deviation of allotment later.pdf10 Mar 2025
Details of encumbrances concerned to LegalFile: legal and finance.pdf10 Mar 2025
Other - TechnicalFile: GST Certificate.pdf10 Mar 2025
Other - TechnicalFile: SRO Certificate.pdf10 Mar 2025
Other - TechnicalFile: LLP Agreement_11zon.pdf10 Mar 2025
Other - TechnicalFile: LLP Certificate.pdf10 Mar 2025
Other - TechnicalFile: Declaration cum undertaking.pdf10 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Other Real Estate Project.pdf10 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: secure and unsecure.pdf10 Mar 2025

How this compares with Palghar

5%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANANT SHREE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Nallasopara West3,200+ in Palghar

2 kmANANT SHREECompleted 32Lapsed / revoked 24Other 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 113 registered projects within 2 km.

Builder: BRICKWORK INFRABUILD LLP

BRICKWORK INFRABUILD LLP has 1 registration on MahaRERA, including ANANT SHREE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if ANANT SHREE is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANANT SHREE?

The registered promoter entity is BRICKWORK INFRABUILD LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANANT SHREE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ANANT SHREE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANANT SHREE?

The professionals named in the filing: Architect: Sanjay Maloo & Associates; Engineer: GR Consultants; Chartered Accountant: MISHRA MAYEKAR & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANANT SHREE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANT SHREE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANT SHREE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.