Registration lapsed No litigation declared Residential / Group Housing project

ANANT CLASSIC

By GOVIND VENKATRAO IPKALWAR

RG-MH-47761 · RERA P52000047813 · Last updated on MahaRERA portal: 8 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
11 of 90Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

ANANT CLASSIC is a Residential / Group Housing project by GOVIND VENKATRAO IPKALWAR in Raigarh, Maharashtra, registered with MahaRERA as P52000047813 on 28 Nov 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 6 months from the original filing. 79 of the 90 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.

At a glance

Project

  • NameANANT CLASSIC
  • TypeResidential / Group Housing
  • Location
    • SECTOR 6E
    • KALAMBOLI
    • Panvel
    • Raigarh
    • 410218
  • Pincode410218
  • RERA no.P52000047813
  • ReraGenie IDRG-MH-47761

Builder

  • NameGOVIND VENKATRAO IPKALWAR
  • Entity typeIndividual

Key dates

4 months past promisethis monthRegisteredNov 2022First promiseDec 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Nov 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed80 files

Current status

88%79 of 90 units booked
100.0%Work done, per cost certificate

Figures as on 8 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANANT CLASSIC A WINGNA8749049
ANANT CLASSIC B WINGNA8741041

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 8 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

ANANT CLASSIC A WING82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
ANANT CLASSIC B WING82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed81

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots81
Closed/Covered74
Open Space7
BuildingClosed/CoveredOpen SpaceTotal
ANANT CLASSIC A WING36036
ANANT CLASSIC B WING38745

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,291 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPanvel Municipal Corporation
Permissible FSI4337.66
Proposed, not sanctioned3,771 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVASHI
Estimated costRs 7.36 cr
Cost incurredRs 7.36 cr
Work done100.0%
BuildingWingEstimatedIncurred
ANANT CLASSIC A WINGNARs 3.42 crRs 3.42 cr
ANANT CLASSIC B WINGNARs 3.42 crRs 3.42 cr
-NARs 53.00 lakhRs 53.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTOSPATI DESIGN GROUP ARCHITECTS
EngineerEPICONS CONSULTANTS PVT LTD
Chartered AccountantCA DEVYANI SHEJWAL
Chartered AccountantMs Singh Ranjan & Co
PartnerRole in project
GOVIND VENKATRAO IPKALWAR-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA24122518959Dec 2025 → Jun 2026

Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf8 May 2026
Withdrawal Update Form 2File: FORM 2 Engineer Certificate - Anant Clssic.pdf8 May 2026
Withdrawal Update Form 3File: Form 3 anant classic 31-03-2026 SIgn.pdf8 May 2026
Layout approvalFile: Plan 01.pdf22 Feb 2026
Layout approvalFile: Plan 02.pdf22 Feb 2026
Building plan approvalFile: Plan 01.pdf22 Feb 2026
Building plan approvalFile: Plan 02.pdf22 Feb 2026
Withdrawal Update Form 1File: Form 1 31-12-2025.pdf18 Feb 2026
Withdrawal Update Form 2File: FORM 2 - 31-12-2025.pdf18 Feb 2026
Withdrawal Update Form 3File: Form 3 Anant Classic 31-12-2025.pdf18 Feb 2026
Form 2A (FY 2022-2023)File: FORM 2A 22-23.pdf10 Jan 2026
Form 2A (FY 2023-2024)File: FORM 2A 23-24.pdf10 Jan 2026
Form 2A (FY 2024-2025)File: FORM 2A 24-25.pdf10 Jan 2026
Form 5 (FY 2023-2024)File: FORM 5 23-24 NEW.pdf10 Jan 2026
Form 5 (FY 2024-2025)File: FORM 5 24-25 NEW.pdf10 Jan 2026
Form 5 (FY 2022-2023)File: Form 5 22-23.pdf6 Jan 2026
Form 1File: Form 1 30-06-25.pdf3 Dec 2025
Form 2File: Form 2 30-06-25.pdf3 Dec 2025
Form 3File: Form 3 Anant Classic 30-06-2025.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ Unsold 30-06-25.pdf3 Dec 2025
Form 1File: FORM 1 30-09-25.pdf3 Dec 2025
Form 2File: FORM 2 30-09-25.pdf3 Dec 2025
Form 3File: Form 3 Anant Classic 30-09-2025.pdf3 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold 30-09-25.pdf3 Dec 2025
Form 1File: Form 1_Anant Classic q4.pdf14 Jun 2025
Form 2File: Form 2_Anant Classic q4.pdf14 Jun 2025
Form 3File: FORM 3 Anant classic q4.pdf14 Jun 2025
Disclosure of Sold and Booked InventoryFile: sold unsold anant q4.pdf14 Jun 2025
Self-declaration of Quarterly ProgressFile: Declaration for qpr Anant Classic q4.pdf14 Jun 2025
Layout approvalFile: PLAN 1.pdf19 Feb 2025
Layout approvalFile: PLAN 2.pdf19 Feb 2025
Building plan approvalFile: PLAN 1.pdf19 Feb 2025
Building plan approvalFile: PLAN 2.pdf19 Feb 2025
Copy of Layout Approval (in case of layout)File: PLAN 1.pdf19 Feb 2025
Copy of Layout Approval (in case of layout)File: PLAN 2.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 .pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - converted.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - converted.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf19 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 1.pdf19 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1.pdf21 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf21 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23_1 (4 files merged).pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate-.pdf4 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate.pdf4 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Govind .pdf4 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARTC CERT.pdf8 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM 2.pdf8 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3.pdf8 May 2023
Commencement Certificates / NA Order for plotted developmentFile: CC NEW.pdf17 Nov 2022
Building plan approvalFile: PLAN 3 (1).pdf22 Oct 2022
Building plan approvalFile: PLAN 2.pdf22 Oct 2022
Building plan approvalFile: PLAN 1 (1).pdf22 Oct 2022
Layout approvalFile: PLAN 3 (1).pdf22 Oct 2022
Layout approvalFile: PLAN 2.pdf22 Oct 2022
Layout approvalFile: PLAN 1 (1).pdf22 Oct 2022
Copy of the legal title reportFile: NEW TITLE REPORT.pdf22 Oct 2022
Details of encumbrances concerned to FinanceFile: Image (18).pdf22 Oct 2022
Details of encumbrances concerned to LegalFile: Image (18).pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: PLAN 3 (1).pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: PLAN 2.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: PLAN 1 (1).pdf22 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN 3 (1).pdf22 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.pdf22 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN 1 (1).pdf22 Oct 2022
Declaration about Commencement CertificateFile: DECLERATION ABT CC.pdf22 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT.pdf22 Oct 2022
Proforma of Agreement for saleFile: AFS (1).pdf22 Oct 2022
Proforma of Allotment letterFile: ALLOTMENT DRAFT NEW.pdf22 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A BANK AC.pdf22 Oct 2022
Deviation Report with respect to Allotment letterFile: DEVATION ALLOTMENT.pdf22 Oct 2022
Deviation Report with respect to model copy of AgreementFile: DEVIATION AGREEMENT FOR SALE.pdf22 Oct 2022
CERSAI detailsFile: CERSAI Search Report.pdf21 Oct 2022
PAN CardFile: PAN (3).pdf19 Oct 2022
Declaration in FORM BFile: FORM B.pdf19 Oct 2022

How this compares with Raigarh

88%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 6 months
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANANT CLASSIC on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALAMBOLI5,900+ in Raigarh

Builder: GOVIND VENKATRAO IPKALWAR

GOVIND VENKATRAO IPKALWAR has 1 registration on MahaRERA, including ANANT CLASSIC. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that ANANT CLASSIC shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ANANT CLASSIC is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANANT CLASSIC?

The registered promoter entity is GOVIND VENKATRAO IPKALWAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANANT CLASSIC?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ANANT CLASSIC?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANANT CLASSIC?

The professionals named in the filing: Architect: VASTOSPATI DESIGN GROUP ARCHITECTS; Engineer: EPICONS CONSULTANTS PVT LTD; Chartered Accountant: CA DEVYANI SHEJWAL; Chartered Accountant: Ms Singh Ranjan & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANANT CLASSIC?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANT CLASSIC. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANT CLASSIC to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.