Home / Browse projects / Sindhudurg, Maharashtra / ANANDVAN SAIRAJ SANKUL PHASE 1
ANANDVAN SAIRAJ SANKUL PHASE 1
By CONSORTEXE PROPERTIES PVT LTD
RG-MH-73379 · RERA P52900046802 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 41 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ANANDVAN SAIRAJ SANKUL PHASE 1 is a Residential / Group Housing project by CONSORTEXE PROPERTIES PVT LTD in Sindhudurg, Maharashtra, registered with MahaRERA as P52900046802 on 10 Sep 2022. Possession is promised by 31 Dec 2028. The completion date has moved by 41 months from the original filing. 6 of the 18 units on this registration are recorded sold or booked, and 48 of 198 construction stages are filed complete.
At a glance
Project
- NameANANDVAN SAIRAJ SANKUL PHASE 1
- TypeResidential / Group Housing
- Location
- VENGURLA ROAD
- GONDHALPUR
- Pinguli
- Kudal
- Sindhudurg
- 416528
- Pincode416528
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52900046802
- ReraGenie IDRG-MH-73379
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Sep 2022
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 31 Jul 2025)
- Buildings18 building records
- Documents filed160 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| TWIN BUNGLOW A 1 | NA | 2 | 1 | 1 | 0 | 1 |
| TWIN BUNGLOW A 2 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW A 3 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW A 4 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW A 5 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW A 6 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW A 7 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW A 8 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW A 9 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW A 10 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW B 1 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW B 2 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW B 3 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW B 4 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW B 5 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW B 6 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW B 7 | NA | 2 | 2 | 1 | 0 | 1 |
| TWIN BUNGLOW B 8 | NA | 2 | 2 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building18
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
48 of 198 construction stages are filed complete across 18 buildings. The stage furthest along is External plumbing and external plaster, at 90%.
TWIN BUNGLOW A 167%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
TWIN BUNGLOW A 255%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
TWIN BUNGLOW A 341%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW A 441%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW A 539%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW A 639%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW A 735%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW A 835%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 25% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW A 973%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
TWIN BUNGLOW A 1073%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
TWIN BUNGLOW B 121%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW B 221%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW B 30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW B 40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW B 50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW B 60%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW B 717%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
TWIN BUNGLOW B 817%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 90% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 25% |
| Water Supply | Yes | 25% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 25% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| TWIN BUNGLOW A 1 | 1 | 1 |
| TWIN BUNGLOW A 2 | 1 | 1 |
| TWIN BUNGLOW A 3 | 1 | 1 |
| TWIN BUNGLOW A 4 | 1 | 1 |
| TWIN BUNGLOW A 5 | 1 | 1 |
| TWIN BUNGLOW A 6 | 1 | 1 |
| TWIN BUNGLOW A 7 | 1 | 1 |
| TWIN BUNGLOW A 8 | 1 | 1 |
| TWIN BUNGLOW A 9 | 1 | 1 |
| TWIN BUNGLOW A 10 | 1 | 1 |
| TWIN BUNGLOW B 1 | 1 | 1 |
| TWIN BUNGLOW B 2 | 1 | 1 |
| TWIN BUNGLOW B 3 | 1 | 1 |
| TWIN BUNGLOW B 4 | 1 | 1 |
| TWIN BUNGLOW B 5 | 1 | 1 |
| TWIN BUNGLOW B 6 | 1 | 1 |
| TWIN BUNGLOW B 7 | 1 | 1 |
| TWIN BUNGLOW B 8 | 1 | 1 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| CONSORTEXE PROPERTIES PVT LTD | Thane (M Corp.) | Thane |
| PUSHKARAJ KOLE | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 1.50 cr | Rs 4.75 lakh |
| TWIN BUNGLOW A 9 | NA | Rs 66.67 lakh | Rs 66.67 lakh |
| TWIN BUNGLOW A 10 | NA | Rs 66.67 lakh | Rs 66.67 lakh |
| TWIN BUNGLOW B 3 | NA | Rs 66.67 lakh | - |
| TWIN BUNGLOW B 4 | NA | Rs 66.67 lakh | - |
| TWIN BUNGLOW B 5 | NA | Rs 66.67 lakh | - |
| TWIN BUNGLOW B 6 | NA | Rs 66.67 lakh | - |
| TWIN BUNGLOW A 5 | NA | Rs 33.33 lakh | Rs 23.33 lakh |
| TWIN BUNGLOW A 6 | NA | Rs 33.33 lakh | Rs 23.33 lakh |
| TWIN BUNGLOW A 7 | NA | Rs 33.33 lakh | Rs 20.00 lakh |
| TWIN BUNGLOW A 8 | NA | Rs 33.33 lakh | Rs 20.00 lakh |
| TWIN BUNGLOW B 1 | NA | Rs 33.33 lakh | Rs 20.00 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CONSORTIUM |
| Architect | Swarup Mayekar |
| Engineer | RUPESH TAWATE |
| Engineer | Vinayak Nawar |
| Chartered Accountant | SABAT & CO |
| Chartered Accountant | Kapure & Kapure |
| Chartered Accountant | Shripati Gandhi Choudhari & Co |
| Partner | Role in project |
|---|---|
| CONSORTEXE PROPERTIES PVT LTD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per the attachment
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Jul 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Aug 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed160
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1 - June 2026 ASRS.PDF | 20 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 - June 2026 ASRS.PDF | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - July 26 ASRS.PDF | 20 Jul 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A - MARCH 2026 -Aanadvan.pdf | 25 May 2026 |
| Withdrawal Update Form 1File: Form 1 - Anadvan - March 26.PDF | 22 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Anandvan - March 26.PDF | 22 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 - Anandvan - March 26.PDF | 22 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 - Sairaj Sankul - Dec 25.PDF | 28 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 - Sairaj Sankul - Dec 25.PDF | 28 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 - Sairaj Sankul - Dec 25.PDF | 28 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 - Sept 25.PDF | 1 Dec 2025 |
| Withdrawal Update Form 2File: Form 2 - Sept 25.PDF | 1 Dec 2025 |
| Withdrawal Update Form 3File: Form 3 - September 25.PDF | 1 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 Arch Cert June 2025.pdf | 19 Aug 2025 |
| Withdrawal Update Form 2File: Form 2 - June 2025 - Final.PDF | 19 Aug 2025 |
| Withdrawal Update Form 3File: Form 3 - CA Certificate June 25 - Anandvan.PDF | 19 Aug 2025 |
| Form 2A (FY 2024-2025)File: Form 2A - Certificate no. 3_compressed.pdf | 1 Jul 2025 |
| Form 2A (FY 2022-2023)File: Site engineer cert 2023.PDF | 26 Jun 2025 |
| Form 2A (FY 2023-2024)File: Site engineer certificate 2024.pdf | 26 Jun 2025 |
| Form 5 (FY 2022-2023)File: Form 5 - 2022-23 - SAIRAJ.PDF | 26 Jun 2025 |
| Form 5 (FY 2023-2024)File: Form 5 - 2023-24 - SAIRAJ.PDF | 26 Jun 2025 |
| Form 1File: Architect cert Jan 23.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 Jan 23.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - December 2022.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - December 2022.PDF | 4 Jun 2025 |
| Form 1File: Architect cert April 23.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 April 23.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - March 2023.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 2023.PDF | 4 Jun 2025 |
| Form 1File: Architect cert July 23.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 July 23.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - June 2023.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - June 2023.PDF | 4 Jun 2025 |
| Form 1File: Architect cert Oct 23.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 Oct 23.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - September 2023.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - September 2023.PDF | 4 Jun 2025 |
| Form 1File: Architect cert Jan 24.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 Jan 24.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - December 2023.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - December 2023.pdf | 4 Jun 2025 |
| Form 1File: Architect cert April 24.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 April 24.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - March 2024.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 2024.PDF | 4 Jun 2025 |
| Form 1File: Architect cert July 24.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 July 24.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - June 2024.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - June 2024.PDF | 4 Jun 2025 |
| Form 1File: Architect cert Octo 24.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 Oct 24.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - September 2024.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - September 2024.PDF | 4 Jun 2025 |
| Form 1File: Architect cert Jan 25.PDF | 4 Jun 2025 |
| Form 2File: Engg Certificate 1 Jan 25.PDF | 4 Jun 2025 |
| Form 3File: Form 3 - December 2024.PDF | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - December 2024.PDF | 4 Jun 2025 |
| Form 1File: Form 1 - March 25.PDF | 4 Jun 2025 |
| Form 2File: Form 2 March 2025_compressed.pdf | 4 Jun 2025 |
| Form 3File: Signed Form 3_compressed.pdf | 4 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure - March 2025.PDF | 4 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2025_compressed.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - March 25.PDF | 2 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3_compressed.pdf | 2 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - March 2025.PDF | 2 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022-23 - SAIRAJ.PDF | 7 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023-24 - SAIRAJ.PDF | 7 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - December 2022.PDF | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - March 2023.PDF | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - June 2023.PDF | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - September 2023.PDF | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - December 2023.pdf | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - March 2024.PDF | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - June 2024.PDF | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - September 2024.PDF | 1 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - December 2024.PDF | 1 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - March 2023.PDF | 28 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 2023.PDF | 28 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - September 2023.PDF | 28 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - December 2023.PDF | 28 Feb 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| PORTO DO DIO-ESTRELA | PUNOLA VILLAGE UCASSAIM BARDEZ GOA | 13 | Completed | May 2015 | Late, Apr 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 160 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ANANDVAN SAIRAJ SANKUL PHASE 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near GONDHALPUR530+ in Sindhudurg
Filed coordinates, straight-line distance. 6 registered projects within 2 km.
Avdhoot Manthan
Shashikant Shamrao Jadhav
SINDHUDURG PARADISE
G.V.P. REALTY PRIVATE LIMITED
ANANDVAN DABHOLKAR SANKUL PHASE 2
Promoter name not stated in filing
ANANDVAN DABHOLKAR SANKUL PHASE 3
CONSORTEXE PROPERTIES PVT LTD
ANANDVAN DABHOLKAR SANKUL- PHASE 4
CONSORTEXE PROPERTIES PVT LTD
CLASSICAL RESIDENCY
CLASSIC BUILDER & DEVELOPER
See every Sindhudurg project, with the district possession charts
Builder: CONSORTEXE PROPERTIES PVT LTD
CONSORTEXE PROPERTIES PVT LTD has 5 registrations on MahaRERA, including ANANDVAN DABHOLKAR SANKUL PHASE 3 and ANANDVAN DABHOLKAR SANKUL- PHASE 4. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What are my rights if ANANDVAN SAIRAJ SANKUL PHASE 1 is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ANANDVAN SAIRAJ SANKUL PHASE 1?
The registered promoter entity is CONSORTEXE PROPERTIES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ANANDVAN SAIRAJ SANKUL PHASE 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ANANDVAN SAIRAJ SANKUL PHASE 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ANANDVAN SAIRAJ SANKUL PHASE 1?
The professionals named in the filing: Architect: CONSORTIUM; Architect: Swarup Mayekar; Engineer: RUPESH TAWATE; Engineer: Vinayak Nawar; Chartered Accountant: SABAT & CO; Chartered Accountant: Kapure & Kapure. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANANDVAN SAIRAJ SANKUL PHASE 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback