Home / Browse projects / Akola, Maharashtra / ANANDAM
ANANDAM
RG-MH-66034 · RERA P50100045938 · Last updated on MahaRERA portal: 4 Nov 2024
Source: official MahaRERA filing
Red flags
- Completion date moved by 2 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Akola registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ANANDAM is a Residential / Group Housing project by A B Constructions in Akola, Maharashtra, registered with MahaRERA as P50100045938 on 15 Jun 2022. The registration is recorded completed; possession was promised by 28 Feb 2024. The completion date has moved by 2 months from the original filing.
At a glance
Project
- NameANANDAM
- TypeResidential / Group Housing
- Location
- Nityanand Nagar
- Near Saikrupa Mangal Karyalaya
- Back side of Jai Bhole Kirana
- Gaurakshan Road
- Akola (M Corp.)
- Akola
- 444001
- Pincode444001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50100045938
- ReraGenie IDRG-MH-66034
Builder
- NameA B Constructions
- Entity typePartnership
- PartnersKamlesh Anjanikumar Agrawal, Palak Satish Bhasin, Sahil Ashokkumar Bhasin
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on15 Jun 2022
- Promised completion28 Feb 2024
- Revised completionRevised to 28 Feb 2024 (originally 31 Dec 2023)
- Buildings1 building record
- Documents filed18 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Anandam | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
Anandam: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 4 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed44
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar. Sumit Agarwal |
| Engineer | Shyamsundar Sadhwani |
| Chartered Accountant | Agrawal Bajoria Padiya & Associates |
| Partner | Role in project |
|---|---|
| A B Constructions | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Reason for uploading to OC and Form 4 after date of completion of the project was not attributed from our side but due to negligence from the Akola Municipal Corporation, there are some facts we like to bring to your notice that we had applied for OC on 23/09/2023 and all other formalities are completed by the Akola Municipal Corporation on 21/11/2023 including site visit but due to non availability of DCR software and continuous leave by Akola Commissioner, OC was not issued upto 28/02/2024. The delay was not from our side but by one of the departments of State government. Copies of Appli
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 28 Feb 2024
Documents filed18
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 4 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf | 28 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 20 Oct 2023 |
| OtherFile: Self Clarification.pdf | 13 May 2023 |
| Building plan approvalFile: Building Plan Approval.pdf | 30 May 2022 |
| Layout approvalFile: Single Building Approval Plan.pdf | 30 May 2022 |
| PAN CardFile: AB PAN.pdf | 30 May 2022 |
| Copy of the legal title reportFile: Title Verification Report.pdf | 30 May 2022 |
| Details of encumbrancesFile: Encumberance Certificate.pdf | 30 May 2022 |
| Copy of Layout Approval (in case of layout)File: Single Building Approval Plan.pdf | 30 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval.pdf | 30 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 30 May 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf | 30 May 2022 |
| Declaration in FORM BFile: Form B Declaration.pdf | 30 May 2022 |
| CERSAI detailsFile: Cersai Declaration alongwith report.pdf | 30 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 30 May 2022 |
| Proforma of Allotment letterFile: Allotment Letter_Agreement to Sale.pdf | 30 May 2022 |
| OtherFile: SRO.pdf | 30 May 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Akola
Computed across the 120+ Akola projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 18 filed documents as one ZIP, foldered, with a manifest
Keep ANANDAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Gaurakshan Road120+ in Akola
Filed coordinates, straight-line distance. 32 registered projects within 2 km.
Lotus Green
Pankaj Rameshchandra Kothari
R M Dhariwal Township Akola Plotting
Dhariwal And Chhoriya Developers LLP
Yamuna Business Park
Marvel Trinity Real Estate LLP
The Grand Phoenix Market-Phase 1
Sushilkumar Ratanlal Khowal
AKOLA TEXTILE MARKET
AKOLA TEXTILE MARKET
Yamuna Trimurti Towers
Marvel Trinity Real Estate LLP
See every Akola project, with the district possession charts
Builder: A B Constructions
A B Constructions has 1 registration on MahaRERA, including ANANDAM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Akola district page.
Frequently asked questions
What are my rights if ANANDAM is delayed beyond 28 Feb 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ANANDAM?
The registered promoter entity is A B Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ANANDAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ANANDAM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ANANDAM?
The professionals named in the filing: Architect: Ar. Sumit Agarwal; Engineer: Shyamsundar Sadhwani; Chartered Accountant: Agrawal Bajoria Padiya & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ANANDAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.