Home / Browse projects / Akola, Maharashtra / Yamuna Business Park
Yamuna Business Park
By Marvel Trinity Real Estate LLP
RG-MH-05017 · RERA P50100053326 · Last updated on MahaRERA portal: 18 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 2 months past the filed date
- Rs 19.00 crore secured on the land, in favour of State Bank of India
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Akola registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Yamuna Business Park is a Commercial project by Marvel Trinity Real Estate LLP in Akola, Maharashtra, registered with MahaRERA as P50100053326 on 27 Oct 2023. Possession was promised by 31 Aug 2026 and is now 2 months past that date. 4 of the 98 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameYamuna Business Park
- TypeCommercial
- Location
- Opposite Yamuna Plaza
- National Highway No. 6
- National Highway No. 6
- Akola (M Corp.)
- Akola
- 444001
- Pincode444001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50100053326
- ReraGenie IDRG-MH-05017
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on27 Oct 2023
- Promised completion31 Aug 2026
- Revised completionNone
- Buildings1 building record
- Documents filed69 files
Current status
Figures as on 18 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Yamuna Business Park | NA | 10 | 7 | 0 | 98 | 98 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 75%.
Yamuna Business Park: 70% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Progress on shared amenities15
As on 18 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 75% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 75% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed364
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Yamuna Business Park | NA | Rs 42.92 cr | Rs 30.55 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sanjeev Jain |
| Engineer | Khwaja Saud Ur Rahman Najeeb Rahman |
| Engineer | Agasti Kalyan Rathod |
| Chartered Accountant | Hemant Agrawal |
| Chartered Accountant | Agrawal Bajoria Padiya & Associates |
| Chartered Accountant | SAGAR S. RATHI & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Marvel Trinity Real Estate LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 20 Sep 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Sep 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Sep 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed69
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 YBP.pdf | 18 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 YBP.pdf | 18 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 YBP.pdf | 18 Jun 2026 |
| Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf | 9 Mar 2026 |
| Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 28 Jan 2026 |
| Form 5 (FY 2024-2025)File: Form 5.pdf | 10 Jan 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 17 Oct 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 20 Jul 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 20 Jul 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 20 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 310325.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 310325.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 310325.pdf | 19 Apr 2025 |
| Details of encumbrances concerned to FinanceFile: Finance Encumberance.pdf | 26 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 26 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Usold.pdf | 26 Mar 2025 |
| CERSAI detailsFile: CERSAI.pdf | 26 Mar 2025 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 26 Mar 2025 |
| Details of encumbrances concerned to LegalFile: Finance Encumberance.pdf | 26 Mar 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Format B.pdf | 26 Mar 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Loan Diclosure along with CA Certificate.pdf | 26 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 311224.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 311224.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-311224.pdf | 20 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf | 4 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 300924.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 300924.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 300924.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 300624.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2-300624.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 300624.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: YBP 1 310324.pdf | 18 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: YBP 2 310324.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: YBP 3 310324.pdf | 18 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-311223.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-311223.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-311223.pdf | 20 Jan 2024 |
| Other - TechnicalFile: Gmail - Fwd_ AKOLA MUNICIPAL CORPORATION COMPLATION CERTIFICATE OF BUILDING PERMISSION PRO | 20 Oct 2023 |
| Other - LegalFile: INDEX-2.pdf | 6 Oct 2023 |
| Layout approvalFile: Building Sanction Map 1.pdf | 20 Sep 2023 |
| Building plan approvalFile: Building Sanction Map.pdf | 20 Sep 2023 |
| Building plan approvalFile: Building Sanction Map 1.pdf | 20 Sep 2023 |
| PAN CardFile: PAN.pdf | 20 Sep 2023 |
| Copy of the legal title reportFile: LSR.pdf | 20 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: Finance Encumberance.pdf | 20 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: Legal Encumberance.pdf | 20 Sep 2023 |
| Details of encumbrances concerned to LegalFile: Finance Encumberance.pdf | 20 Sep 2023 |
| Details of encumbrances concerned to LegalFile: Legal Encumberance.pdf | 20 Sep 2023 |
| Copy of Layout Approval (in case of layout)File: Building Sanction Map 1.pdf | 20 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Sanction Map.pdf | 20 Sep 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Building Sanction Map 1.pdf | 20 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 20 Sep 2023 |
| Declaration about Commencement CertificateFile: Declaration of Commencement.pdf | 20 Sep 2023 |
| Declaration in FORM BFile: Form B-Declaration.pdf | 20 Sep 2023 |
| CERSAI detailsFile: Cersai Declaration.pdf | 20 Sep 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 20 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Other Project Interest- Ghanshyam.pdf | 20 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Other Project Interest- Madhur.pdf | 20 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Other Project Interest- Santosh.pdf | 20 Sep 2023 |
| Proforma of Agreement for saleFile: Agrenment to sale.pdf | 20 Sep 2023 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 20 Sep 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf | 20 Sep 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf | 20 Sep 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Agreement to Sale.pdf | 20 Sep 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Yamuna TowerP50100051525 | Near Sai Mandir, Akola | Jun 2023 | Completed | Mar 2025 | Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Akola
Computed across the 120+ Akola projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 69 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Yamuna Business Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near National Highway No. 6120+ in Akola
Filed coordinates, straight-line distance. 28 registered projects within 2 km.
Lotus Green
Pankaj Rameshchandra Kothari
R M Dhariwal Township Akola Plotting
Dhariwal And Chhoriya Developers LLP
The Grand Phoenix Market-Phase 1
Sushilkumar Ratanlal Khowal
AKOLA TEXTILE MARKET
AKOLA TEXTILE MARKET
Yamuna Trimurti Towers
Marvel Trinity Real Estate LLP
Shakambari Business Park
R J Commercials
See every Akola project, with the district possession charts
Builder: Marvel Trinity Real Estate LLP
Marvel Trinity Real Estate LLP has 4 registrations on MahaRERA, including Yamuna Tower and Yamuna Business Park. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Akola district page.
Frequently asked questions
What are my rights if Yamuna Business Park is delayed beyond 31 Aug 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Yamuna Business Park?
The registered promoter entity is Marvel Trinity Real Estate LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Yamuna Business Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Yamuna Business Park?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Yamuna Business Park?
The professionals named in the filing: Architect: Sanjeev Jain; Engineer: Khwaja Saud Ur Rahman Najeeb Rahman; Engineer: Agasti Kalyan Rathod; Chartered Accountant: Hemant Agrawal; Chartered Accountant: Agrawal Bajoria Padiya & Associates; Chartered Accountant: SAGAR S. RATHI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Yamuna Business Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback