Home / Browse projects / Mumbai Suburban, Maharashtra / ANANDA RESIDENCY

Completed No litigation declared Residential / Group Housing project

ANANDA RESIDENCY

By PARADIGM AMBIT BUILDCON

RG-MH-09015 · RERA P51800000204 · Last updated on MahaRERA portal: 11 May 2022

Source: official MahaRERA filing

Red flags

  • 12 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 97%
12Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

ANANDA RESIDENCY is a Residential / Group Housing project by PARADIGM AMBIT BUILDCON in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000204 on 10 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing. 12 complaints are on record with the regulator.

At a glance

Project

  • NameANANDA RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Shivaji Nagar
    • Vazira
    • Borivali (West)
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000204
  • ReraGenie IDRG-MH-09015

Builder

  • NamePARADIGM AMBIT BUILDCON
  • Entity typeOthers
  • Named personsPARADIGM HOMES LLP, DOTOM URBAN SPACE LLP

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on10 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANANDA RESIDENCYNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 May 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 97%.

ANANDA RESIDENCY: 96% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities21

As on 11 May 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes70%
Landscaping & Tree PlantingYes60%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes60%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes60%
Energy managemcntYes60%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes10%
Open ParkingNoNot applicable
Amphi TheatreYes75%
Fitness CentreYes75%
Jogging Track and Children Play AreaYes80%
Multi Purpose CourtYes80%
Sky Garden at TerraceYes30%
Swimming Pool and Kids PoolYes70%

Parking filed216

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots216
Closed/Covered216

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,268 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI17526.31
Proposed, not sanctioned17,526 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSana Building Linking Road Santacruz West Mumbai 400053

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANOJ VISHWAKARMA
PartnerRole in project
PARADIGM AMBIT BUILDCON-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800003963Dec 2019 → Jun 2020

Reason as filed by the promoterOn account of some unexpected and unavoidable external factors, which were completely beyond our control like: (i) The Project consists of total 4 wings. Lift installation permission received by us initially was upto 20th habitable floor in each of the wings. However, considering various age group residents will be residing in our project, of them few of being senior citizens, few are kids & few are differently able individuals, hence we had applied for approval extension of lift till the terrace slab & the same as a whole has taken more than 6 months for us to receive the approval;(ii) PWD li

EXT51800008838Dec 2019 → Jun 2021

Reason as filed by the promoterOn account of the outbreak of pandemic Covid - 19, there were some unexpected and unavoidable circumstances which were beyond our control.

Complaints filed with MahaRERA12

Case no.ComplainantRespondentFiled
CC006000000000103GOLDPRISM REALTY PRIVATE LIMITEDGOLDPRISM REALTY PRIVATE LIMITED09/08/2017
CC006000000023135Paradigm Ambit BuildconMrs. Falguni Shah & Mrs. Mira Shah07/03/2018
CC006000000023934KUTBUDDIN AMRELIWALAPARADIGM AMBIT BUILDCON04/04/2018
CC006000000198427Deepak Arun Lade and Anita Deepak LadeM/s. Paradigm Ambit Buildcon24/10/2021
CC006000000198189PRAMILA M SHAHPRADIGM AMBIT BUILDCON01/09/2021
CC006000000198203MAHENDRA T SHAH HUFPARADIGM AMBIT BUILDCON01/09/2021
CC006000000198207HARSHABHEN SHETHPRADIGM AMBIT BUILDCON01/09/2021
CC006000000198210CHANDRAKANT THAKKARPRADIGM AMBIT BUILDCON02/09/2021
CC006000000198217J M GANDHI HUFPARADIGM AMBIT BUILDCON02/09/2021
CC006000000198219ASHWIN VALLABHDAS SHAHPRADIGM AMBIT BUILDCON02/09/2021
CC006000000396930Paradigm Ambit BuildconDEEPAKLADE07/08/2023
CC006000000428728Manish Vinodchandra SolankiM/s Paradigm Ambit Buildcon07/01/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Sep 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Oct 2020

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Ananda Inventory May22.pdf11 May 2022
Disclosure of sold/ booked inventoryFile: Ananda.pdf18 Feb 2022
Disclosure of sold/ booked inventoryFile: sold unsold ananda.pdf26 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ananda AC 30-03-21.pdf9 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: anandaAC 31-06-21.pdf9 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MARCH.pdf6 Jul 2021
Disclosure of sold/ booked inventoryFile: ananda.pdf24 Jun 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Ananda Society Regi Certificate.pdf22 Jun 2021
Disclosure of sold/ booked inventoryFile: Ananda Sold - Unsold.pdf9 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4-ANANDA RESIDENCY_rotated.pdf25 Feb 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Ananda Residency Part OC.pdf17 Oct 2020
Building plan approvalFile: Ananda IOD revised.pdf21 Sep 2020
Building Plan Approval (IOD)File: Ananda IOD revised.pdf21 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate Ananda (March).pdf21 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate Ananda (June).pdf21 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ANANDA RESIDENCY - 30-12-2019 ARCHITECT CERTIFICATE.pdf12 Mar 2020
Details of encumbrancesFile: Details of Further Encumbrances_20_01_2020_PAB.pdf5 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ANANDA RESIDENCY - 30-12-2019 ARCHITECT CERTIFICATE.pdf5 Mar 2020
Form 2AFile: 09 07 2019_ANANDA QUALITY ASSURANCE_TILL December 2019.pdf5 Mar 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Paradigm Ambit Buildcon FORM 5.pdf28 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE- 29-06-2019.pdf8 Aug 2019
Details of encumbrancesFile: Details of further Encumbrances.pdf23 Jul 2019
Form 2AFile: 09 07 2019_ANANDA QUALITY ASSURANCE_TILL JUNE 2019.pdf23 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ANANDA RESIDENCY ARCHITECT CERTIFICATE - 30-03-2019.pdf21 May 2019
Form 2AFile: 14 05 2019_ANANDA QUALITY ASSURANCE_TILL MARCH2 019.pdf16 May 2019
Form 2AFile: ANANDA QUALITY ASSURANCE_07 02 2019 FORM 2A.pdf21 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_31_12_2018.pdf13 Feb 2019
Certificates of CA (Form 5)File: FORM 5 Ananda Residency.pdf1 Dec 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Reservation_Ananda Residency_29_08_2018.pdf29 Aug 2018
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate.pdf4 Apr 2018
Certificates of CA (Form 3)File: Form 3 CA Certificate final.pdf6 Jul 2017
Proforma of Allotment letterFile: Ananda RERA Allotment Letter and Agreement Final.pdf6 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate 03 07 17.pdf5 Jul 2017
Building plan approvalFile: Sale IOD.pdf3 Jul 2017
Layout approvalFile: Layout Approval.pdf3 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf3 Jul 2017
Building Plan Approval (IOD)File: Sale IOD.pdf3 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Full CC - Ananda.pdf3 Jul 2017
Declaration in FORM BFile: Form-B-Affidavit cum Declaration.pdf3 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT'S CERTIFICATE 30-06-2017-.pdf3 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Letter Sale and Rehab.pdf3 Jul 2017
PAN CardFile: PAN Card - PAB.pdf29 Jun 2017
Copy of the legal title reportFile: ASA Legal Title Certificate.PDF29 Jun 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANANDA RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vazira, Borivali (West)6,700+ in Mumbai Suburban

2 kmANANDA RESIDENCYCompleted 133Lapsed / revoked 76Other 212Dot size: filed unitsN

Filed coordinates, straight-line distance. 421 registered projects within 2 km.

Builder: PARADIGM AMBIT BUILDCON

PARADIGM AMBIT BUILDCON has 1 registration on MahaRERA, including ANANDA RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ANANDA RESIDENCY is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANANDA RESIDENCY?

The registered promoter entity is PARADIGM AMBIT BUILDCON, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANANDA RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ANANDA RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ANANDA RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANANDA RESIDENCY?

The professionals named in the filing: Architect: MANOJ VISHWAKARMA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANANDA RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANDA RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANDA RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.