Home / Browse projects / Palghar, Maharashtra / Anand Park Mamta Heights

Completed No litigation declared Residential / Group Housing project

Anand Park Mamta Heights

By Sachin Shantilal Joshi

RG-MH-10901 · RERA P99000004112 · Last updated on MahaRERA portal: 19 Nov 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 63 months
  • 5 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
14 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
1Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

Anand Park Mamta Heights is a Residential / Group Housing project by Sachin Shantilal Joshi in Palghar, Maharashtra, registered with MahaRERA as P99000004112 on 8 Aug 2017. The registration is recorded completed; possession was promised by 30 Mar 2025. The completion date has moved by 63 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAnand Park Mamta Heights
  • TypeResidential / Group Housing
  • Location
    • Man
    • Palghar
    • 401501
  • Pincode401501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000004112
  • ReraGenie IDRG-MH-10901

Builder

  • NameSachin Shantilal Joshi
  • Entity typeIndividual
  • GSTIN27AABPJ0224G1ZB

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Aug 2017
  • Promised completion30 Mar 2025
  • Revised completionRevised to 30 Mar 2025 (originally 30 Dec 2019)
  • Buildings2 building records
  • Documents filed74 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No 1 DharmiNA50000
Building No 2 ZealNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

Building No 1 Dharmi82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building No 2 Zeal73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes90%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,480 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityCollector's Office Palghar
Permissible FSI2678.4
Proposed, not sanctioned1,854 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRupam Centre Sion Circle Cine Planet Sion East Mumbai 400022

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectLS
ArchitectVijay Gurav & Associates
EngineerVijay Gurav
EngineerVijay Gurav & Associates
Chartered AccountantV. L. Nagda & Co.
PartnerRole in project
Sachin Shantilal Joshi-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000003953Dec 2019 → Dec 2020

Reason as filed by the promoterRespected Sir/Madam We have a ongoing project at Survey No/Gut No. 2 of Village Maan Taluka & Dist: Palghar. Registered with Rera under the Rera Act vide Number . P99000004112 The completion date for this project at time of registration was given as 30.12.2019.Now after revision in DCR in the region we are now elegible for additional FSI as per the sanctioned DCR and accordingly we have submitted a revised proposal to the collector Palghar ( Planning Authority) for revision in the plans as per prevailing rules and regulations. The requisite Challans payable to GOM for the revision of plans is

EXT99000013202Dec 2019 → Dec 2023

Reason as filed by the promoterTo, Rera Authority, SUBJECT: EXTENSION OF RERA Sir/ Madam, We have obtained development permission and registered our project of Residential Buildings at Boisar, District Palghar. Project Reg No: P99000004112 in the name of project Anand Park.The Due Date of Rera Certificate is till 30/12/2022. Our work is in progress as on date. My site was working in full swing before Pandemic, as per the new guidelines work started slowly with minimum workers and staff according to the government guidelines. Building number 1, is almost 100% ready building cleaning & finishing is ongoing. Expected possessio

EXT99000009899Dec 2019 → Jun 2022

Reason as filed by the promoterTo, Rera Authority, SUBJECT: EXTENSION OF RERA DATE Sir/ Madam, My Project registered under RERA Reg No: P99000004112 & site situated at Boisar, Maan village, Dist Palghar, project known as Anand Park, had been given a Rera Due till 30/6/2021. My site was working in full swing till the Pandemic, Covid 19 started. Due to the lockdown, we had to stop work for sometime according to the Government guidelines. Thereafter, as per the new guidelines, work started slowly with minimum workers and staff. My office is located at Mumbai and the distance is almost 195 to 200 kilometres from office to site

EXT99000017868Dec 2019 → Jun 2024

Reason as filed by the promoterTo, Rera Authority, SUBJECT: REVISE EXTENSION DATE OF RERA CERTIFICATE Sir/ Madam, My site is situated at Boisar, District Palghar. Project Reg No: P99000004112. The name of the project is Anand Park. It had been given a Rera Due till 30/12/2023. As per my RERA submission, my balance FSI is pending. It is also shown on the RERA website. After the Government announced clearance of UDCPR 2020, updated Jan. 2023 , FSI clearance work started by our Architect and we have applied in the government town planning department- palghar in December 2022 and at the same time we also apply in RERA for exten

EXT99000024215Dec 2019 → Mar 2025

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 91% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. In ac

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000397630Harish Jaisaram MaliGuru Krupa Infra Creations proprietor Sachin S Joshi11/10/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Oct 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Circular 29 30-10-2024.pdf19 Nov 2024
Certificates of CA (Form 3)File: Form 3 Oct 24.pdf19 Nov 2024
Certificates of CA (Form 3)File: Form 3 Oct 24.pdf19 Nov 2024
Disclosure of sold/ booked inventoryFile: Circular 29 30-10-2024.pdf19 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf29 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf25 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf23 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf23 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf23 Oct 2024
Declaration in FORM BFile: Form B.pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 14-08-2024.pdf7 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aug 24.pdf7 Oct 2024
CERSAI detailsFile: Declaration of CERSAI.pdf7 Oct 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Architect progress report bldg no 1.pdf5 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold unsold list as on.pdf2 Jul 2024
Certificates of CA (Form 3)File: Form 3.pdf28 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 year 22 23.pdf28 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2 A certificate.pdf20 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Interest Anex A.pdf20 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Form A Declaration Bank AC.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked.pdf18 Nov 2023
Declaration about Commencement CertificateFile: Disclosure of sold booked.pdf6 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A LAST YEAR.pdf6 Nov 2023
CERSAI detailsFile: RPM_MCHI_990000_PAL_848-1 CERTIFICATE.pdf6 Nov 2023
Deviation Report with respect to model copy of AgreementFile: Agreement for Sale DRAFT UNDER RERA.pdf6 Nov 2023
Layout approvalFile: Lay out sheet 1.pdf2 Oct 2023
Building plan approvalFile: Building no 1 plan copy.pdf2 Oct 2023
Layout approvalFile: Building no 1 plan copy.pdf2 Oct 2023
Layout approvalFile: Building no 2 plan copy.pdf2 Oct 2023
Layout approvalFile: Building no 2 plan coopy 2.pdf2 Oct 2023
Copy of Layout Approval (in case of layout)File: Lay out sheet 1.pdf2 Oct 2023
Copy of Layout Approval (in case of layout)File: Building no 1 plan copy.pdf2 Oct 2023
Copy of Layout Approval (in case of layout)File: Building no 2 plan copy.pdf2 Oct 2023
Copy of Layout Approval (in case of layout)File: Building no 2 plan coopy 2.pdf2 Oct 2023
Building Plan Approval (IOD)File: Building no 1 plan copy.pdf2 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: N A or C C Copy.pdf2 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020 21.pdf16 Jan 2023
Proforma of Agreement for saleFile: Agreement for Sale draft as per under RERA.pdf10 Jan 2023
Details of encumbrances concerned to FinanceFile: GetUserDocumentFileContent-3.pdf5 Jan 2023
Details of encumbrances concerned to LegalFile: GetUserDocumentFileContent-3.pdf5 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Maan bldg no 1 structural stability certificate.pdf5 Jan 2023
Declaration about Commencement CertificateFile: Declaration of C C.pdf28 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Architect From 2 a.pdf28 Jun 2021
Disclosure of sold/ booked inventoryFile: Disclose sold unsold Inventory.pdf28 Jun 2021
Declaration about Commencement CertificateFile: C C R Anand Park.pdf25 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Building No 1, progress report.pdf25 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Building No 2, progress report.pdf25 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ANUAL C A AUDIT REPORT.pdf25 Jun 2021
Details of Restarting of Construction work post lockdownFile: Restarting work letter.pdf17 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Rera Audit Certificate-2 year 2018 - 2019.pdf18 Feb 2020
Architect’s Certificate on Completion of Project (Form 4)File: Architect Form 4 certificate pdf.pdf30 Dec 2019
Certificates of CA (Form 5)File: c a form 5 pdf.pdf8 Jun 2019
Certificates of CA (Form 3)File: Certificate of CA Form 3.pdf28 Jul 2017
Certificates of CA (Form 3)File: Certificates of CA Form 3 continued.pdf28 Jul 2017
Proforma of Allotment letterFile: Agreement for Sale.pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment Letter.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AR CERT.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ER cert.pdf27 Jul 2017
Layout approvalFile: Layout Plan.pdf15 Jul 2017
Building plan approvalFile: Declaration for I O D.pdf15 Jul 2017
Layout approvalFile: Building No 1 Plan.pdf15 Jul 2017
Layout approvalFile: Building No 2 Plan.pdf15 Jul 2017
PAN CardFile: Sachin PAN CARD.pdf15 Jul 2017
Copy of the legal title reportFile: Title Report.pdf15 Jul 2017
Details of encumbrancesFile: Scan copy of Declaration.pdf15 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf15 Jul 2017
Copy of Layout Approval (in case of layout)File: Building No 1 Plan.pdf15 Jul 2017
Copy of Layout Approval (in case of layout)File: Building No 2 Plan.pdf15 Jul 2017
Building Plan Approval (IOD)File: Declaration for I O D.pdf15 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf15 Jul 2017
Declaration in FORM BFile: Form B.pdf15 Jul 2017
OtherFile: Gram Panchayat NOC.pdf15 Jul 2017

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 63 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Anand Park Mamta Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Man3,200+ in Palghar

Builder: Sachin Shantilal Joshi

Sachin Shantilal Joshi has 1 registration on MahaRERA, including Anand Park Mamta Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if Anand Park Mamta Heights is delayed beyond 30 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Anand Park Mamta Heights?

The registered promoter entity is Sachin Shantilal Joshi, an individual as per the filing. Its GSTIN 27AABPJ0224G1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Anand Park Mamta Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Anand Park Mamta Heights?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Anand Park Mamta Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Anand Park Mamta Heights?

The professionals named in the filing: Architect: LS; Architect: Vijay Gurav & Associates; Engineer: Vijay Gurav; Engineer: Vijay Gurav & Associates; Chartered Accountant: V. L. Nagda & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Anand Park Mamta Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Anand Park Mamta Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Anand Park Mamta Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.