Home / Browse projects / Pune, Maharashtra / Amrutvel
Amrutvel
RG-MH-52427 · RERA P52100052068 · Last updated on MahaRERA portal: 12 Jul 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 17 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Amrutvel is a Residential / Group Housing project by R K Developers in Pune, Maharashtra, registered with MahaRERA as P52100052068 on 19 Jul 2023. Possession was promised by 25 May 2025 and is now 17 months past that date.
At a glance
Project
- NameAmrutvel
- TypeResidential / Group Housing
- Location
- Mahalunge Gaon
- Mahalunge
- Mulshi
- Pune
- 410501
- Pincode410501
- RERA no.P52100052068
- ReraGenie IDRG-MH-52427
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Jul 2023
- Promised completion25 May 2025
- Revised completionNone
- Buildings1 building record
- Documents filed22 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Amrutvel | NA | 3 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 4%.
Amrutvel: 28% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 4% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed124
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership9
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Shri Kaluram Nathoba Sutar | Pimpale Gurav | Pune |
| Shri Suresh Nathoba Shinde | Pimpale Gurav | Pune |
| Shri Baban Nathoba Sutar | Pimpale Gurav | Pune |
| Shri Balu Nathoba Sutar | Pimpale Gurav | Pune |
| Mrs Punam Balu Sutar | Pimpale Gurav | Pune |
| Mrs Daupadrabai Baburao Zinzurde | Pimpale Gurav | Pune |
| Mrs Chandrabhaga Balasaheb Parkhi | Pimpale Gurav | Pune |
| Shri Bhausaheb Nathoba Sutar | Pimpale Gurav | Pune |
| Shri Gulab Nathoba Shinde | Pimpale Gurav | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Amit A Darunkar |
| Engineer | Rohinee Engineers |
| Chartered Accountant | Pravin Pise and Asociates |
| Partner | Role in project |
|---|---|
| R K Developers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 May 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 May 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 May 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed22
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Commencement Certificates / NA Order for plotted developmentFile: New CC (2).pdf | 12 Jul 2023 |
| Other - LegalFile: Paternership Retired.pdf | 4 Jul 2023 |
| Building plan approvalFile: 1 Copy of Layout Approval (in case of layout).pdf | 23 May 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 Copy of Layout Approval (in case of layout).pdf | 23 May 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200269215815_For_Asset_Based_Search_20_05_2023_15_32_36_385 (1) (6).p | 20 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 20 May 2023 |
| Proforma of Agreement for saleFile: Agreement Of Sale.pdf | 18 May 2023 |
| Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf | 17 May 2023 |
| PAN CardFile: Firm Pan Card.pdf | 17 May 2023 |
| Copy of the legal title reportFile: 1 Copy of the legal title report (18) (1).pdf | 17 May 2023 |
| Details of encumbrances concerned to FinanceFile: R K Developers.pdf | 17 May 2023 |
| Details of encumbrances concerned to LegalFile: R K Developers.pdf | 17 May 2023 |
| Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf | 17 May 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement.pdf | 17 May 2023 |
| Declaration about Commencement CertificateFile: Decalaration Of Commencement.pdf | 17 May 2023 |
| Declaration in FORM BFile: Form B Promoter.pdf | 17 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Rohidas.pdf | 17 May 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Sushma (1).pdf | 17 May 2023 |
| Proforma of Allotment letterFile: Model Form Of Allotment Letter.pdf | 17 May 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow | 17 May 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Of Allotment Letter.pdf | 17 May 2023 |
| Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement (1) (1).pdf | 17 May 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations, which the RERA portal never shows together
- All 22 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Amrutvel on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mahalunge13,700+ in Pune
DWARKA PROJECT3
NAIKNAVAREHOUSINGDEVELOPEMENTSPVTLTD
SARA NILAAY
JAGRUTSARA STRUCTURES LLP
SARA CITY TOWER C3
JAGRUTSARA STRUCTURES LLP
SARA CITY TOWER C2
JAGRUTSARA STRUCTURES LLP
SARA SWAPNODAY
Jagrutsara Structures LLP
Aapla Ghar Moshi Annex Phase I
Maple Shelters Pvt. Ltd.
Builder: R K Developers
R K DEVELOPERS has 9 registrations on MahaRERA, including R K RESIDENCY and CHINMAY APARTMENT. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Amrutvel shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Amrutvel is delayed beyond 25 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Amrutvel?
The registered promoter entity is R K Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Amrutvel?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Amrutvel?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Amrutvel?
The professionals named in the filing: Architect: Ar Amit A Darunkar; Engineer: Rohinee Engineers; Chartered Accountant: Pravin Pise and Asociates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Amrutvel?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback