ReraGenieLog inGet a buyer report

Home / Browse projects / Sangli, Maharashtra / Amey Shilp

Completed No litigation declared Residential / Group Housing project

Amey Shilp

By Amey Construction

RG-MH-55977 · RERA P53100049555 · Last updated on MahaRERA portal: 11 Mar 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Internal walls, 95%
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

Amey Shilp is a Residential / Group Housing project by Amey Construction in Sangli, Maharashtra, registered with MahaRERA as P53100049555 on 15 Feb 2023. The registration is recorded completed; possession was promised by 30 Jun 2026.

At a glance

Project

  • NameAmey Shilp
  • TypeResidential / Group Housing
  • Location
    • Rajashri Shahunagar
    • Wanlesswadi
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416416
  • Pincode416416
  • RERA no.P53100049555
  • ReraGenie IDRG-MH-55977

Builder

  • NameAmey Construction
  • Entity typePartnership
  • PartnersPrashant Appasaheb Chougule, Mohan Akappa Desai
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredFeb 2023PromisedJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on15 Feb 2023
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Amey ShilpNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

Amey Shilp: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Open Space13

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area253 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI507.2
Proposed, not sanctioned507 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSangli Miraj Road, Sangli

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAmber M Shinde
EngineerSuresh K Keripale
Chartered AccountantRushabh M Lodha
PartnerRole in project
Amey Construction-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Mar 2025

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Amey Shilp Completion Certificate.pdf11 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Amey Shilp Form 5 Annual Audit Reprt March 2023.pdf4 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Amey Shilp Form 5 Annual Audit Report March 2024.pdf4 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amey Shilp Form 1 Architect Cert June 2024.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amey Shilp Form 1 Architect Cert Sep 2024.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amey Shilp Form 1 Architect Cert Dec 2024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amey Shilp Form 3 CA Cert June 2024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amey Shilp Form 3 CA Cert Sept 2024.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amey Shilp Form 3 CA Cert Dec 2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amey Shilp Form 2 Engineer Cert June 2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amey Shilp Form 2 Engineer Cert Sep 2024.pdf19 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amey Shilp Form 2 Engineer Cert Dec 2024.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: March 24 Amey Shilp Architect Certificate.PDF20 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March 24 Amey Shilp Engineer Certificate.PDF20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: March 24 Amey Shilp Quality Assurance Certificate.PDF20 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: March 24 Amey Shilp CA Certificate.pdf20 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Amey Shilp Architect Ceertificate Sep 23.PDF26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Amey Shilp Engineer Certificate Sep 23.PDF26 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amey Shilp CA Certificate Sep 23 Min.pdf26 Oct 2023
Other - TechnicalFile: Amey Shilp Construction Declaration .pdf7 Feb 2023
Details of encumbrances concerned to FinanceFile: Amey Shilp Encumbrance Certificate Corrected .pdf27 Jan 2023
Details of encumbrances concerned to LegalFile: Amey Shilp Encumbrance Certificate Corrected .pdf27 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Amey Shilp Partner Disclosure Chougule.PDF25 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Amey Shilp Partner Disclosure Desai.PDF25 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Amey Shilp Partner Disclosure Keripale.PDF25 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Amey Shilp Partner Disclosure Kulkarni.PDF25 Jan 2023
Deviation Report with respect to Allotment letterFile: Amey Shilp Deviation report Allotment Letter.PDF25 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Amey Shilp Deviation Report Model Agreement.PDF25 Jan 2023
Layout approvalFile: Amey Shilp Layout .pdf19 Jan 2023
Building plan approvalFile: Amey Shilp Revised Blueprint.PDF19 Jan 2023
PAN CardFile: Amey Shilp PAN.pdf19 Jan 2023
Copy of the legal title reportFile: Amey Shilp Search Report .pdf19 Jan 2023
Copy of Layout Approval (in case of layout)File: Amey Shilp Layout .pdf19 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Amey Shilp Revised Blueprint.PDF19 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: Amey Shilp Revised Commencement Certificate .pdf19 Jan 2023
Declaration about Commencement CertificateFile: Amey Shilp Declaration Commencement Certificate .pdf19 Jan 2023
Declaration in FORM BFile: Amey Shilp Declaration From B.pdf19 Jan 2023
CERSAI detailsFile: Amey Shilp CERSAI Undertaking .pdf19 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Amey Shilp Corrected CA Certificate Min.pdf19 Jan 2023
Proforma of Agreement for saleFile: Amey Shilp Agreement Draft.pdf19 Jan 2023
Proforma of Allotment letterFile: Amey Shilp Allotment Letter Draft.pdf19 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Amey Shilp Declaration Separate Bank Account .pdf19 Jan 2023

How this compares with Sangli

11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is completed

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep Amey Shilp on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wanlesswadi790+ in Sangli

Builder: Amey Construction

Amey Construction has 2 registrations on MahaRERA, including Amey Pushp and Amey Shilp. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if Amey Shilp is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Amey Shilp?

The registered promoter entity is Amey Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Amey Shilp?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Amey Shilp?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Amey Shilp?

The professionals named in the filing: Architect: Amber M Shinde; Engineer: Suresh K Keripale; Chartered Accountant: Rushabh M Lodha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Amey Shilp?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Amey Shilp. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Amey Shilp to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.