AMAR GANGA is a Residential/Group Housing project by yamini builders and developers in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/171031/001570 on 31 Oct 2017. Possession is promised by 4 May 2019.
At a glance
Project
- NameAMAR GANGA
- TypeResidential/Group Housing
- Location
- Mangalore
- Dakshina Kannada
- PincodeNot stated
- RERA no.PRM/KA/RERA/1257/334/PR/171031/001570
- ReraGenie IDRG-KA-02500
Builder
- Nameyamini builders and developers
- Entity typePartnership Firm
- Authorized SignatoryDAMODAR DANDEKERO
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on31 Oct 2017
- Promised completion4 May 2019
- Revised completionNone
- Buildings1 building record
- Documents filed40 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| AMAR GANGA | - | - | - | 12 | 0 | 12 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Not applicable |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | Not applicable |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | No | Not applicable |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | Yes | - |
| Water conservation and renewable energy | No | Not applicable |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | DEVADAS C KAMATH |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed40
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/171031/001570 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: 01 registration of firm.PDF | - |
| Commencement cert | - |
| approved building plan | - |
| Proforma for sale deed | - |
| Proforma of agreement for sale | - |
| land documents and location | - |
| approved section plan | - |
| Proforma for allotment letter | - |
| brochure | - |
| noc | - |
| specification | - |
| EC | - |
| The requested DOCUMENT could not be compressed less than 1MB | - |
| joint development agreement | - |
| Balance Sheet 2015 - 2016File: Balance Sheet 2016.pdf | - |
| Balance Sheet 2014 - 2015File: Balance Sheet 2015.pdf | - |
| Balance Sheet 2013 - 2014File: Balance Sheet 2014.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss Account 2016.pdf | - |
| Audited Profit and Loss Statement 2014 - 2015File: Profit Loss Account 2015.pdf | - |
| Audited Profit and Loss Statement 2013 - 2014File: Profit & Loss Account 2014.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR-2016.pdf | - |
| Income Tax Return Acknowledgement 2014 - 2015File: ITR-2015.pdf | - |
| Income Tax Return Acknowledgement 2013 - 2014File: ITR-2014.pdf | - |
| declaration form b | - |
| Prospectus/BrochureFile: brochure.pdf | - |
| Advertisement Copy 1File: ag advt copy.jpg | - |
| Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_171031_001570.xlsx | - |
| Stability CertificateFile: stability Ag.pdf | - |
| NOC issued by the Fire Force department after completion of workFile: fire completion certificate.pdf | - |
| Occupancy CertificateFile: completion certificate.pdf | - |
| Consent for operation issued by KSPCBFile: pollution certificate completion.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: lift operation certificate Ag.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: mescom Ag.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: water conncetion Ag.pdf | - |
| Details of external infrastructure work such as drive way, play area, park, STP and water treatment plant, WheFile: form5 completed project AG.pdf | - |
| Common Area and other amenities facilities are completed or not and details of handling over of the same to asFile: form5 completed project AG.pdf | - |
| Details of undivided share of land handed over to the association of allotteesFile: undivided rights Ag.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: form6 completed project Ag.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Amargana 4CC_compressed.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: completion affidavit AG.pdf | - |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| TARA | - | Completed | Aug 2017 | No date filed |
| RAMAKRISHNA RESIDENCY | - | Completed | Aug 2017 | No date filed |
| DANDEKERI RESIDENCY | - | Completed | Aug 2017 | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep AMAR GANGA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
Sai Matha Garden
Matha Developers Pvt Ltd
ROHAN MARINA ONE
ROHAN PLAZA PRIVATE LIMITED
See every Dakshina Kannada project, with the district possession charts
Builder: yamini builders and developers
yamini builders and developers has 1 registration on RERA Karnataka, including AMAR GANGA. Its filings declare 3 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if AMAR GANGA is delayed beyond 4 May 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of AMAR GANGA?
The registered promoter entity is yamini builders and developers, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in AMAR GANGA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at AMAR GANGA?
The professionals named in the filing: Engineer: DEVADAS C KAMATH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMAR GANGA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback