Red flags
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AMANSARA EARTHSTAR is a Plotted project by SVB LIFESPACES LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000054002 on 19 Dec 2023. Possession is promised by 6 Nov 2026. 47 of the 91 units on this registration are recorded sold or booked. 1 complaint is on record with the regulator.
At a glance
Project
- NameAMANSARA EARTHSTAR
- TypePlotted
- Location
- Pen Road
- Ganeshnagar
- Khalapur
- Raigarh
- 410203
- Pincode410203
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000054002
- ReraGenie IDRG-MH-06823
Builder
- NameSVB LIFESPACES LLP
- Entity typePartnership
- GSTIN27AESFS2181N1Z7
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersShrenik Vinaykumar Balai, Manoj Gopinath Hode
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Dec 2023
- Promised completion6 Nov 2026
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed89 files
Current status
Figures as on 18 Apr 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 18 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 49% |
| Water Supply | Yes | 49% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 36% |
| Storm Water Drains | Yes | 49% |
| Landscaping & Tree Planting | Yes | 36% |
| Street Lighting | Yes | 36% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 36% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 36% |
| Open Parking | No | Not applicable |
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SVB LIFESPACES LLP | Pune (M Corp.) | Pune |
| Fahim Chand Shaikh | Mumbai City | Mumbai City |
| Falcon Group | Pune (M Corp.) | Pune |
| Avinash Ramesh Khatnahar | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 29.27 cr | Rs 13.05 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shailesh Dandane |
| Engineer | Udhav Patil |
| Chartered Accountant | V S Fathepur & Co |
| Chartered Accountant | RAJ PADAVALE |
| Partner | Role in project |
|---|---|
| SVB LIFESPACES LLP | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| SM12600076 | Bhakti Achrekar | SVB LIFESPACES LLP | 23/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Nov 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Oct 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Nov 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 6 Nov 2026
Documents filed89
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - QTR 4.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Form 2 - Amansara Eartstar.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: Form3 - AMANSARA EARTHSTAR.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 QPR 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 - QPR 2.pdf | 8 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 - QPR 2.pdf | 8 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 - QPR 2.pdf | 8 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5 FY 24-25.pdf | 22 Sep 2025 |
| Withdrawal Update Form 1File: Form 1 QTR - 1.pdf | 19 Jul 2025 |
| Withdrawal Update Form 1File: Form 1 QTR - 1.pdf | 19 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 QTR - 1.pdf | 19 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 QTR - 1.pdf | 19 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 QTR 1.pdf | 19 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 QTR 1.pdf | 19 Jul 2025 |
| Declaration and undertaking (Annexure A)File: Annexure A as per Order 50.pdf | 17 Jul 2025 |
| Form 1File: LLP Form 1 Dec 23 to April 24.pdf | 2 Jun 2025 |
| Form 2File: LLP Form 2 Dec 23 to April 24.pdf | 2 Jun 2025 |
| Form 3File: Form 3 April 2024 Technical Remarks.pdf | 2 Jun 2025 |
| OthersFile: Form 2A LLP.pdf | 2 Jun 2025 |
| Form 1File: LLP Form 1 May 24 to Aug 24.pdf | 2 Jun 2025 |
| Form 2File: Form 2 Jan 24 to Sep 2024 Technical Remarks.pdf | 2 Jun 2025 |
| Form 3File: Form 3 Aug 2024 Technical Remarks.pdf | 2 Jun 2025 |
| Form 1File: Form 1 QPR - July 2024 to Sep 2024 Technical Remarks.pdf | 2 Jun 2025 |
| Form 2File: LLP Form 2 May 24 to Aug 24.pdf | 2 Jun 2025 |
| Form 3File: Form 3 - July 24 to Sep 24 Technical Remarks.pdf | 2 Jun 2025 |
| Form 1File: LLP Form 1 Sep 24 to Dec 24.pdf | 2 Jun 2025 |
| Form 2File: LLP Form 2 QTR Sep 24 to Dec 24.pdf | 2 Jun 2025 |
| Form 3File: Form 3 Dec 2024 Technical Remarks.pdf | 2 Jun 2025 |
| OthersFile: Form 2A LLP.pdf | 2 Jun 2025 |
| Form 1File: Form 1 QPR Jan 2025 to March 2025 Technical Remarks.pdf | 2 Jun 2025 |
| Form 2File: LLP Form 2 March 2025.pdf | 2 Jun 2025 |
| Form 3File: Form 3 March 2025 Technical Remarks.pdf | 2 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 QPR - July 2024 to Sep 2024.pdf | 13 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 QPR Jan 2025 to March 2025.pdf | 13 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LLP Form 3 March 2025.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LLP Form 2 March 2025.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LLP Form 1 Dec 23 to April 24.pdf | 31 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LLP Form 1 May 24 to Aug 24.pdf | 31 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LLP Form 1 Sep 24 to Dec 24.pdf | 31 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LLP Form 2 QTR 1.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LLP Form 2 QTR 2.pdf | 29 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LLP Form 2 QTR 3.pdf | 29 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 LLP Q1.pdf | 26 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 LLP Q2.pdf | 26 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 LLP Q3.pdf | 26 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A LLP.pdf | 26 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Amansara Earthstar.pdf | 17 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 up to 13th March 2025.pdf | 17 Mar 2025 |
| Other - LegalFile: Reply Letter Scan.pdf | 6 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Amansara Earthstar Form 5 FY 2023-2024.pdf | 6 Dec 2024 |
| Declaration about Commencement CertificateFile: Form D.PDF | 11 Dec 2023 |
| Proforma of Agreement for saleFile: Plot ATS - Amansara Earthstar.pdf | 4 Dec 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report-2.pdf | 4 Dec 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report-1.pdf | 24 Nov 2023 |
| Copy of the legal title reportFile: Legal_Title_Report-1.pdf | 10 Nov 2023 |
| Copy of the legal title reportFile: Legal_Title_Report-2.pdf | 10 Nov 2023 |
| Details of encumbrances concerned to FinanceFile: Non_Enc_Finance.pdf | 10 Nov 2023 |
| Details of encumbrances concerned to FinanceFile: Non_Enc_Legal.pdf | 10 Nov 2023 |
| Details of encumbrances concerned to LegalFile: Non_Enc_Finance.pdf | 10 Nov 2023 |
| Details of encumbrances concerned to LegalFile: Non_Enc_Legal.pdf | 10 Nov 2023 |
| Other - TechnicalFile: Other_Tech_Declaration.pdf | 10 Nov 2023 |
| Building plan approval or NA orderFile: NA Order_Amansara_Earthstar.pdf | 9 Nov 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order_Amansara_Earthstar.pdf | 9 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order_Amansara_Earthstar.pdf | 9 Nov 2023 |
| CERSAI detailsFile: Cersai Declaration.PDF | 8 Nov 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank_Form A.pdf | 8 Nov 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200284836019_For_Asset_Based_Search_27_10_2023_12_13_50_609.pdf | 27 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certification.pdf | 27 Oct 2023 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 27 Oct 2023 |
| Deviation Report with respect to Allotment letterFile: Allotment Letter Deviation Report.pdf | 27 Oct 2023 |
| Details of encumbrances concerned to FinanceFile: Non - Encumbramce-1.pdf | 26 Oct 2023 |
| Details of encumbrances concerned to LegalFile: Non - Encumbramce-1.pdf | 26 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 89 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AMANSARA EARTHSTAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ganeshnagar5,900+ in Raigarh
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
Godrej Hillview Estate
Godrej Projects Development Limited
Haware My First Home Shil Phata Phase 2 Bldg 1
Haware Properties LLP
UNIMONT IMPERIA
RSM DESIGNERS
Haware My First Home Shil Phata Phase 1 Bldg 1
Haware Properties LLP
AeroEstate
HOABL Landmark Realty Private Limited
Haware My First Home Shil Phata Phase 2 Bldg 2
Haware Properties LLP
See every Raigarh project, with the district possession charts
Builder: SVB LIFESPACES LLP
SVB LIFESPACES LLP has 2 registrations on MahaRERA, including AMANSARA EARTHSTAR and AMANSARA EARTHSTAR PH. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if AMANSARA EARTHSTAR is delayed beyond 6 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AMANSARA EARTHSTAR?
The registered promoter entity is SVB LIFESPACES LLP, a partnership as per the filing. Its GSTIN 27AESFS2181N1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AMANSARA EARTHSTAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AMANSARA EARTHSTAR?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AMANSARA EARTHSTAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AMANSARA EARTHSTAR?
The professionals named in the filing: Architect: Shailesh Dandane; Engineer: Udhav Patil; Chartered Accountant: V S Fathepur & Co; Chartered Accountant: RAJ PADAVALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMANSARA EARTHSTAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback