ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / ALLEGRO AVENTUS

Registration approved No litigation declared Residential/Group Housing project

ALLEGRO AVENTUS

By ALLEGRO BUILDERS AND DEVELOPERS

RG-KA-33172 · RERA PRM/KA/RERA/1257/334/PR/100222/004694 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2026Possession promisedno revision filed
16 of 16Construction stages doneevery applicable stage filed complete
14 of 78Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 116 documents Report an error

ALLEGRO AVENTUS is a Residential/Group Housing project by ALLEGRO BUILDERS AND DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/100222/004694 on 10 Feb 2022. Possession is promised by 31 Dec 2026. 64 of the 78 units on this registration are recorded sold or booked, and 16 of 16 construction stages are filed complete.

At a glance

Project

  • NameALLEGRO AVENTUS
  • TypeResidential/Group Housing
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575003
  • Pincode575003
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/100222/004694
  • ReraGenie IDRG-KA-33172

Builder

  • NameALLEGRO BUILDERS AND DEVELOPERS
  • Entity typeProprietorship Firm
  • GSTIN29ABWPM8524EIZ2
  • Authorized SignatoryDharmendra Bansilal Mehta
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on10 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed116 files

Current status

82%64 of 78 units booked
4.5%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Allegro Aventus---78078

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 16 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,431 sq m
Named landowners1
LandownerVillageDistrict
Dharmendra Bansilal Mehta--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.00 cr
Cost incurredRs 89.60 lakh
Spent of the estimate4.48%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 20.00 crRs 89.60 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNayak Pai & Associates
EngineerK.Anil Hegde
Chartered AccountantB.N. Surendra Bhat

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed116

As listed on the registration, under the names the promoter filed them with; the newest 80 of 116 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/100222/004694 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Auditor Certificate.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 Archtec Certificate.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Labour and Education Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form4 Q1 2026-27.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form5 Q1 2026-27.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form6 Q1 2026-27.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Labour and Education Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Auditor Cer Q4.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architec Cert Q4.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form6 Engineers Certificate Q4.pdf14 Apr 2026
Q4 2025-26 Water supply and sewage board14 Apr 2026
Q4 2025-26 KPTCL- BESCOM14 Apr 2026
Q4 2025-26 Fire and Safety14 Apr 2026
Q4 2025-26 Labour and Education Department14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Auditor Cer Q3.pdf12 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate Q3.pdf12 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate Q3.pdf12 Jan 2026
Q3 2025-26 Water supply and sewage board12 Jan 2026
Q3 2025-26 KPTCL- BESCOM12 Jan 2026
Q3 2025-26 Fire and Safety12 Jan 2026
Q3 2025-26 Labour and Education Department12 Jan 2026
NOC- MESCOMFile: Mescom NOC.pdf31 Jan 2022
STP location and its diagramFile: STP location and its drawing.pdf31 Jan 2022
Previous Project Details as shown in websiteFile: Previous Project Details.pdf18 Jan 2022
Balance Sheet 2019-20 with UDINFile: Balance Sheet 19-20.pdf18 Jan 2022
Profit and Loss 2019-20 with UDINFile: Profit and Loss 19-20.pdf18 Jan 2022
Audit Report 2019-20 with UDINFile: Auditor report 19-20.pdf18 Jan 2022
Balance Sheet 2020-21 with UDINFile: Balance Sheet 2020-21.pdf18 Jan 2022
Profit and Loss 2020-21 with UDINFile: Profit and Loss 2020-21.pdf18 Jan 2022
Audit Report 2020-21 with UDINFile: Auditor's report 20-21.pdf18 Jan 2022
NOC-KSPCB-CorrigendumFile: NOC- KSPCB-Corrigendum.pdf18 Jan 2022
Single Layout PlanFile: Single layout plan.pdf18 Jan 2022
NOC-WaterFile: NOC - Water.pdf18 Jan 2022
NOC-Airport with clarificationFile: NOC-Airport with Clarification.pdf18 Jan 2022
NOC-FireFile: NOC - Fire.pdf18 Jan 2022
NOC-MESCOMFile: NOC- MESCOM.pdf18 Jan 2022
STP DrawingsFile: STP drawing.pdf18 Jan 2022
RTC, survey Survey No.1136/1-
Mutation, survey Survey No.1136/1-
Encumbrance Certificate, survey Survey No.1136/1-
Conversion/Alienation Order, survey Survey No.1136/1-
Sale/Title/Gift Deed, survey Survey No.1136/1-
Khatha, survey Survey No.1136/1-
Registration CertificateFile: Udyam Registration Certificate.pdf-
Certificate issued by CA Form 1File: Form 1 Charted Accountant Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form 3 Civil Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for non litigation.pdf-
Certificate from Chartered AccountFile: Form 1 Charted Accountant Certificate.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet 2019-20.pdf-
Balance Sheet 2019 - 2020File: Balance Sheet 2018-19.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet 2017-18.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit and Loss 2019-20.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit and Loss 2018-19.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit and Loss 2017-18.pdf-
Cash Flow Statement 2020 - 2021File: Cash flow 2020.pdf-
Cash Flow Statement 2019 - 2020File: Cash flow 2019.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: FY 19-20.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: FY 18-19.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: FY 17-18.pdf-
Licence_c-
NOC Mescom-
NOC Water-
Plan-
Plan-
Plan-
specification on letter head-
Site Section Elevation-
legal opinion-
Sale Agreement Rera-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Allegro AureusVas Lane, Falnir, MangaloreCompleted-No date filed

How this compares with Dakshina Kannada

82%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep ALLEGRO AVENTUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmALLEGRO AVENTUSOther 79Dot size: filed unitsN

Filed coordinates, straight-line distance. 79 registered projects within 2 km.

Builder: ALLEGRO BUILDERS AND DEVELOPERS

ALLEGRO BUILDERS AND DEVELOPERS has 1 registration on RERA Karnataka, including ALLEGRO AVENTUS. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if ALLEGRO AVENTUS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of ALLEGRO AVENTUS?

The registered promoter entity is ALLEGRO BUILDERS AND DEVELOPERS, a proprietorship firm as per the filing. Its GSTIN 29ABWPM8524EIZ2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in ALLEGRO AVENTUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at ALLEGRO AVENTUS?

The professionals named in the filing: Architect: Nayak Pai & Associates; Engineer: K.Anil Hegde; Chartered Accountant: B.N. Surendra Bhat. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ALLEGRO AVENTUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ALLEGRO AVENTUS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ALLEGRO AVENTUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.