ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / Akshay

Registered No litigation declared Residential / Group Housing project

Akshay

By Mahendra Purushottam Tank

RG-MH-01520 · RERA P50500010478 · Last updated on MahaRERA portal: 24 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 48 months
  • 1 extension taken
  • Rs 3.00 crore secured on the land, in favour of BULDHANA URBAN COOPERATIVE CREDIT SOCIETY LTD
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
10 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 75%
19 of 89Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 166 documents Report an error

Akshay is a Residential / Group Housing project by Mahendra Purushottam Tank in Nagpur, Maharashtra, registered with MahaRERA as P50500010478 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 70 of the 89 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameAkshay
  • TypeResidential / Group Housing
  • Location
    • Ward no 42
    • Sheet no 12
    • City Survey No 01
    • Nagpur
    • Chikhali (Deosthan)
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440002
  • Pincode440002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500010478
  • ReraGenie IDRG-MH-01520

Builder

  • NameMahendra Purushottam Tank
  • Entity typeIndividual

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed166 files

Current status

79%70 of 89 units booked
72.8%Work done, per cost certificate

Figures as on 24 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AkshayNA8689089

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 75%.

Akshay: 98% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes45%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed314

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots314
Closed/Covered1
Open Space313

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,736 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBULDHANA URBAN COOPERATIVE CREDIT SOCIETY LTD
Secured amountRs 3.00 crore
CERSAI search filedYes
Declared on12 May 2026

Approvals and building plan

Sanctioning authorityNAGPUR MUNICIPAL CORPORATION
Permissible FSI4582.91
Proposed, not sanctioned4,583 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKALMANA , NAGPUR, 440008
Estimated costRs 10.50 cr
Cost incurredRs 7.65 cr
Work done72.84%
BuildingWingEstimatedIncurred
AkshayNARs 10.50 crRs 7.65 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHUL DESHPANDE
EngineerBALRAM GUPTA
Chartered AccountantBudhraja & Company
PartnerRole in project
Mahendra Purushottam Tank-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA25052621091Dec 2022 → Dec 2026

Reason as filed by the promoterFinancial hardships due to under valued & low sales than expected. I, the promoter had to liquidate my personal property to ensure completion of the project. Now the project is out of debt & in position of completion hence requesting your genuine kindness in approving the extension & completion for me to deliver the promised units to the buyers & complete the project appropriately. Have also attached the PERT CPM chart for reference.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed166

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 166 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Architect.pdf24 Jun 2026
Withdrawal Update Form 2File: Form 2 - Engineer.pdf24 Jun 2026
Withdrawal Update Form 3File: Form 3 - CA.pdf24 Jun 2026
Form 1File: March 2023.pdf23 Jun 2026
Form 2File: EC Mar 23.pdf23 Jun 2026
Form 3File: Form 3 Mar 23.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: INVENTORY 2023.pdf23 Jun 2026
Form 1File: AC Jun 23.pdf23 Jun 2026
Form 2File: EC Jun 23.pdf23 Jun 2026
Form 3File: Form 3 Jun 23.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: June 2023.pdf23 Jun 2026
Form 1File: AC Sept-23.pdf23 Jun 2026
Form 2File: EC Sept-23.pdf23 Jun 2026
Form 3File: Form 3 Sept 23.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sept 2023.pdf23 Jun 2026
Form 1File: AC Dec 23.pdf23 Jun 2026
Form 2File: EC Dec-23.pdf23 Jun 2026
Form 3File: Form 3 Dec 23.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: December 2023.pdf23 Jun 2026
Form 1File: AC Mar 24.pdf23 Jun 2026
Form 2File: EC Mar-24.pdf23 Jun 2026
Form 3File: Form 3 Mar 24.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: March 2024.pdf23 Jun 2026
Form 1File: AC Jun-24.pdf23 Jun 2026
Form 2File: EC Jun-24.pdf23 Jun 2026
Form 3File: Form 3 Jun 24.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: June 2024.pdf23 Jun 2026
Form 1File: AC Sept 24.pdf23 Jun 2026
Form 2File: EC Sept-24.pdf23 Jun 2026
Form 3File: Form 3 Sept 24.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sept 24.pdf23 Jun 2026
Form 1File: AC Dec-24.pdf23 Jun 2026
Form 2File: EC Dec-24.pdf23 Jun 2026
Form 3File: Form 3 Dec 2024.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: December 2024.pdf23 Jun 2026
Form 1File: AC Mar 25.pdf23 Jun 2026
Form 2File: EC Mar-25.pdf23 Jun 2026
Form 3File: Form 3 Mar 25.pdf23 Jun 2026
Disclosure of Sold and Booked InventoryFile: March 2025.pdf23 Jun 2026
Withdrawal Update Form 1File: AC Jun 25.pdf23 Jun 2026
Withdrawal Update Form 1File: AC Sept 25.pdf23 Jun 2026
Withdrawal Update Form 1File: AC Dec 25.pdf23 Jun 2026
Withdrawal Update Form 2File: EC Jun-25.pdf23 Jun 2026
Withdrawal Update Form 2File: EC Sept-25.pdf23 Jun 2026
Withdrawal Update Form 2File: EC Dec-25.pdf23 Jun 2026
Withdrawal Update Form 3File: Form 3 Jun 25.pdf23 Jun 2026
Withdrawal Update Form 3File: Form 3 Sept 25.pdf23 Jun 2026
Withdrawal Update Form 3File: Form 3 Dec-25.pdf23 Jun 2026
Form 2A (FY 2023-2024)File: QA Certificate FY 23 24.pdf23 Jun 2026
Form 2A (FY 2024-2025)File: QA Certificate FY 24 25.pdf23 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A - FY 25-26.pdf23 Jun 2026
Form 5 (FY 2023-2024)File: Annual Form 5 23 24.pdf23 Jun 2026
Form 5 (FY 2024-2025)File: Annual Form 5 24 25.pdf23 Jun 2026
Form 5 (FY 2025-2026)File: Form 5 - FY 25-26.pdf23 Jun 2026
Form 1File: Form 1 Sept 2017.pdf8 Jun 2026
Form 2File: Form 2 Sept 2017.pdf8 Jun 2026
Form 3File: Form 3 Sept 2017.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sept 2017.pdf8 Jun 2026
Form 1File: Form 1 Dec 2017.pdf8 Jun 2026
Form 2File: Form 2 Dec 2017.pdf8 Jun 2026
Form 3File: Form 3 Dec 2017.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Dec 2017.pdf8 Jun 2026
Form 1File: March 2018.pdf8 Jun 2026
Form 2File: March 2018.pdf8 Jun 2026
Form 3File: Form 3 2018.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: March 2018.pdf8 Jun 2026
Form 1File: June 2018.pdf8 Jun 2026
Form 2File: June 2018.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: June 2018.pdf8 Jun 2026
Form 3File: June 2018.pdf8 Jun 2026
Form 1File: Sept 2018.pdf8 Jun 2026
Form 2File: Sept 2018.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sept 2018.pdf8 Jun 2026
Form 3File: Sept 2018.pdf8 Jun 2026
Form 1File: Dec 2018.pdf8 Jun 2026
Form 2File: Dec 2018.pdf8 Jun 2026
Form 3File: Dec 2018.pdf8 Jun 2026
Disclosure of Sold and Booked InventoryFile: Dec 2018.pdf8 Jun 2026
Form 1File: March 2019.pdf8 Jun 2026
Form 2File: March 2019.pdf8 Jun 2026

How this compares with Nagpur

79%of this project is bookeddistrict median 35%
13%of Nagpur projects moved their completion datethis one moved by 48 months
22%of Nagpur registrations have lapsed or been cancelledthis one is on the register

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Akshay on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikhali (Deosthan)2,800+ in Nagpur

2 kmAkshayCompleted 9Lapsed / revoked 12Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 30 registered projects within 2 km.

Builder: Mahendra Purushottam Tank

Mahendra Purushottam Tank has 1 registration on MahaRERA, including Akshay. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if Akshay is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Akshay?

The registered promoter entity is Mahendra Purushottam Tank, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Akshay?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Akshay?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Akshay?

The professionals named in the filing: Architect: RAHUL DESHPANDE; Engineer: BALRAM GUPTA; Chartered Accountant: Budhraja & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Akshay?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Akshay. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Akshay to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.