ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / AISHWARYA COOPERATIVE HOUSING SOCIETY

Registered No litigation declared Others project

AISHWARYA COOPERATIVE HOUSING SOCIETY

By ROYAL ENTERPRISES

RG-MH-64530 · RERA P52000048300 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 2 months past the filed date
  • Completion date moved by 25 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
12 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
21 of 45Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

AISHWARYA COOPERATIVE HOUSING SOCIETY is a Others project by ROYAL ENTERPRISES in Raigarh, Maharashtra, registered with MahaRERA as P52000048300 on 26 Dec 2022. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 25 months from the original filing. 24 of the 45 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.

At a glance

Project

  • NameAISHWARYA COOPERATIVE HOUSING SOCIETY
  • TypeOthers
  • Location
    • PRABHUALI
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000048300
  • ReraGenie IDRG-MH-64530

Builder

  • NameROYAL ENTERPRISES
  • Entity typePartnership
  • PartnersImran Abdul Rashid Patel, Rizwan Abdul Rashid Patel, Nouman Abdul Rashid Patel, Farooq Abdul Rashid Patel, Sanobar Siraj Sayyed, Asma Imran Patel, Shazia Patel, Tazeen Anwar Patel
  • Other registrations5 more →
  • Completed2 of 6
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date1

Key dates

2 months past promisethis monthRegisteredDec 2022First promiseJul 2024Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Dec 2022
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 31 Jul 2024)
  • Buildings2 building records
  • Documents filed114 files

Current status

53%24 of 45 units booked
100.0%Work done, per cost certificate

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AISHWARYA CHSNA9721324
AISHWARYA CHSNA9721021

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

AISHWARYA CHS55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
AISHWARYA CHS55%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
AISHWARYA CHS11
AISHWARYA CHS11

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area539 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jul 2026
LandownerVillageDistrict
AISHWARYA COOPERATIVE HOUSING SOCIETYPanvelRaigarh

Approvals and building plan

Sanctioning authorityPANVEL MUMCIPAL CORPORATION
Permissible FSI2405.4
Proposed, not sanctioned2 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPANVEL
Estimated costRs 13.38 cr
Cost incurredRs 13.38 cr
Work done100.0%
BuildingWingEstimatedIncurred
AISHWARYA CHSNARs 6.54 crRs 6.54 cr
AISHWARYA CHSNARs 6.54 crRs 6.54 cr
-NARs 29.50 lakhRs 29.50 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM3 CONSULTANTS
EngineerSOLKAR CONSULTANTS SOLKAR
Chartered AccountantKEYUR BHAYANI &ASSOCIATES KEYUR BHAYANI
Chartered Accountantshraddha kalpesh gurav
PartnerRole in project
ROYAL ENTERPRISES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000024647Jul 2024 → Aug 2026

Reason as filed by the promoterDUE TO SOME FINANCIAL CIRCUMSTANCE THE PROJECT IS NOT COMPLETED WITHIN TIME HENCE APPLIED FOR EXTENSIONS

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: ARCHITECHT.pdf17 Jul 2026
Form 2File: ENGONEER.pdf17 Jul 2026
Form 3File: ROYAL ENT FORM 3.pdf17 Jul 2026
Disclosure of Sold and Booked InventoryFile: ROYAL ENT FORM 3.pdf17 Jul 2026
Form 1File: ARCHITECHT.pdf17 Jul 2026
Form 2File: ENGONEER.pdf17 Jul 2026
Form 3File: ROYAL ENT FORM 3.pdf17 Jul 2026
Disclosure of Sold and Booked InventoryFile: ROYAL ENT FORM 3.pdf17 Jul 2026
Form 1File: ARCHITECHT.pdf17 Jul 2026
Form 2File: ENGONEER.pdf17 Jul 2026
Form 3File: ROYAL ENT FORM 3.pdf17 Jul 2026
Disclosure of Sold and Booked InventoryFile: ROYAL ENT FORM 3_compressed.pdf17 Jul 2026
Form 1File: withdrawal_Architect_certificate__1_.pdf17 Jul 2026
Form 2File: RERA_Certificates__Form_2_.pdf17 Jul 2026
Form 3File: FORM 3 CA CERTIFICATE.pdf17 Jul 2026
Disclosure of Sold and Booked InventoryFile: FORM 3 CA CERTIFICATE.pdf17 Jul 2026
Withdrawal Update Form 1File: AISH_FORM_01.pdf7 Jul 2026
Withdrawal Update Form 2File: Form_02_Aishwarya.pdf7 Jul 2026
Withdrawal Update Form 3File: FORM3 CA CERTIFICATE.pdf7 Jul 2026
Withdrawal Update Form 1File: AISH_FORM_01.pdf11 Apr 2026
Withdrawal Update Form 2File: AISH_FORM_02.pdf11 Apr 2026
Withdrawal Update Form 3File: CA CERTIFICATE FORM 3.pdf11 Apr 2026
Withdrawal Update Form 1File: 01_Form_1_Aish.pdf10 Jan 2026
Withdrawal Update Form 2File: ENG CERTIFICATE.pdf10 Jan 2026
Withdrawal Update Form 3File: form 3 dec final (2).pdf10 Jan 2026
Withdrawal Update Form 1File: AISHWARYA_FORM_01.pdf13 Oct 2025
Withdrawal Update Form 2File: AISHWARYA_FORM_02.pdf13 Oct 2025
Withdrawal Update Form 3File: FORM_3_AISH.pdf13 Oct 2025
Form 5 (FY 2024-2025)File: royal ent- aishwarya hs.pdf30 Sep 2025
Withdrawal Update Form 1File: 01_AISHWARYA_FORM_1.pdf18 Jul 2025
Withdrawal Update Form 2File: 01_AISHWARYA_FORM_2.pdf18 Jul 2025
Withdrawal Update Form 3File: 04_Aish_form3 final.pdf18 Jul 2025
Form 1File: aish_form1.pdf27 Jun 2025
Form 2File: aish_form2.pdf27 Jun 2025
Form 3File: ca certificate.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: ca certificate.pdf27 Jun 2025
Form 1File: 05_form_1_aish.pdf27 Jun 2025
Form 2File: 04_ENGINEER_CERTIFICATE_FORM2_AISH (1).pdf27 Jun 2025
Form 3File: FORM 3 CA CERTIFICATE.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 CA CERTIFICATE.pdf27 Jun 2025
Form 1File: architect_form1_aish.pdf27 Jun 2025
Form 2File: Engi_firm2_aish.pdf27 Jun 2025
Form 3File: FORM 3 DEC24.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 DEC24.pdf27 Jun 2025
Form 1File: aish_architect_form1.pdf27 Jun 2025
Form 2File: AISHWARYA_Certificates__Form_2_.pdf27 Jun 2025
Form 3File: FORM 3 AS ON JUNE 24.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 AS ON JUNE 24.pdf27 Jun 2025
Form 1File: AISHWARYA_ARCHITEC_FORM_1.pdf27 Jun 2025
Form 2File: AISHWARYA_ENGG.pdf27 Jun 2025
Form 3File: FORM 3 AISHWARYA AS ON MARCH 24.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 AISHWARYA AS ON MARCH 24.pdf27 Jun 2025
Form 3File: FORM 3 CA CERTIFICATE.pdf27 Jun 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 CA CERTIFICATE.pdf27 Jun 2025
Form 1File: withdrawal_Architect_certificate__1_.pdf27 Jun 2025
Form 2File: RERA_Certificates__Form_2_.pdf27 Jun 2025
Form 5 (FY 2023-2024)File: FORM 5.pdf27 Jun 2025
Form 5 (FY 2022-2023)File: FORM 5.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: aish_form1.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: aish_form2.pdf12 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect_form1_aish.pdf8 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf8 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi_firm2_aish.pdf8 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5CA CERTIFICATE.pdf28 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 01_QUALITY_ASSURANCE.pdf14 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 01_QUALITY_ASSURANCE.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 04_ENGINEER_CERTIFICATE_FORM2_AMBER (1).pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05_form_1_amber.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 05_form_1_amber.pdf10 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf10 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 04_ENGINEER_CERTIFICATE_FORM2_AMBER (1).pdf10 Oct 2024
Declaration in FORM BFile: AFFIDAVIT.pdf8 Oct 2024
Declaration in FORM BFile: AFFIDAVIT.pdf8 Oct 2024
Disclosure of sold/ booked inventoryFile: DISCLOSER_OF_SOL_BOOK_OF_FLATS.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH_FORM_1.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA_Certificates__Form_2_-1.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH_FORM_1.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA_Certificates__Form_2_-1.pdf7 Oct 2024

How this compares with Raigarh

53%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 25 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AISHWARYA COOPERATIVE HOUSING SOCIETY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PRABHUALI5,900+ in Raigarh

2 kmAISHWARYA COOPERATIVE HOCompleted 10Lapsed / revoked 10Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: ROYAL ENTERPRISES

Royal Enterprises has 6 registrations on MahaRERA, including ROYAL HERITAGE and ROYAL RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if AISHWARYA COOPERATIVE HOUSING SOCIETY is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AISHWARYA COOPERATIVE HOUSING SOCIETY?

The registered promoter entity is ROYAL ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AISHWARYA COOPERATIVE HOUSING SOCIETY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AISHWARYA COOPERATIVE HOUSING SOCIETY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AISHWARYA COOPERATIVE HOUSING SOCIETY?

The professionals named in the filing: Architect: M3 CONSULTANTS; Engineer: SOLKAR CONSULTANTS SOLKAR; Chartered Accountant: KEYUR BHAYANI &ASSOCIATES KEYUR BHAYANI; Chartered Accountant: shraddha kalpesh gurav. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AISHWARYA COOPERATIVE HOUSING SOCIETY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AISHWARYA COOPERATIVE HOUSING SOCIETY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AISHWARYA COOPERATIVE HOUSING SOCIETY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.