ReraGenieLog inGet a buyer report

Home / Browse projects / Akola, Maharashtra / Agrawal Residency

Registration lapsed No litigation declared Residential / Group Housing project

Agrawal Residency

By SANJAYKUMAR OMPRAKASH BAJORIYA

RG-MH-02200 · RERA P50100025035 · Last updated on MahaRERA portal: 21 Nov 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 33 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Akola registration emailed to you, free during the pilot beta.
Jan 2024Possession promised33 months past this date
6 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 36 documents Report an error

Agrawal Residency is a Residential / Group Housing project by SANJAYKUMAR OMPRAKASH BAJORIYA in Akola, Maharashtra, registered with MahaRERA as P50100025035 on 18 Mar 2020. Possession was promised by 30 Jan 2024 and is now 33 months past that date.

At a glance

Project

  • NameAgrawal Residency
  • TypeResidential / Group Housing
  • Location
    • Behind Chevrolet Showroom
    • Gita Nagar
    • Balapur Road
    • Akoli Bk.
    • Akola
    • 444001
  • Pincode444001
  • RERA no.P50100025035
  • ReraGenie IDRG-MH-02200

Builder

  • NameSANJAYKUMAR OMPRAKASH BAJORIYA
  • Entity typeIndividual

Key dates

33 months past promisethis monthRegisteredMar 2020PromisedJan 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Mar 2020
  • Promised completion30 Jan 2024
  • Revised completionNone
  • Buildings3 building records
  • Documents filed36 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building 1NA50000
Building 2NA50000
Building 3NA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 21 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

Building 10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building 227%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building 327%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed364

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots364
Closed/Covered278
Open Space86
BuildingClosed/CoveredOpen SpaceTotal
Building 17286158
Building 21030103
Building 31030103

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,179 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6071.78
Proposed, not sanctioned5,416 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGrahak Seva, Behind Bhirad Complex, M G Road, Akola

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnuraj S Agrawal
EngineerS S MODI CONSULTANTS
Chartered AccountantAgrawal Bajoria Padiya & Associates
PartnerRole in project
SANJAYKUMAR OMPRAKASH BAJORIYA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed36

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 22-23.pdf21 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf21 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf14 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf14 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1 MARCH 20.pdf24 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2 JUNE 20.pdf24 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 3 SEPT 20.pdf24 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 4 DEC 20.pdf24 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 5 MARCH 21.pdf24 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 6 JUNE 21.pdf24 Aug 2021
Disclosure of sold/ booked inventoryFile: SOLD_UNSOLD_DECLARATION_.pdf24 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY 19-20_compressed.pdf24 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2020-21_compressed.pdf24 Aug 2021
Declaration about Commencement CertificateFile: CC DECLARATIONpdf.pdf22 Jul 2021
Declaration in FORM BFile: FORM B_compressed.pdf22 Jul 2021
Layout approvalFile: Commencement Certificate.pdf9 Mar 2020
Building plan approvalFile: Sanctio Plan.pdf9 Mar 2020
Building plan approvalFile: Sanctioned Plan 1.pdf9 Mar 2020
Building plan approvalFile: Sanctioned Plan 2.pdf9 Mar 2020
Building plan approvalFile: Sanctioned Plan 3.pdf9 Mar 2020
PAN CardFile: PAN.pdf9 Mar 2020
Copy of the legal title reportFile: Search Report.pdf9 Mar 2020
Copy of the legal title reportFile: Search Report 1.pdf9 Mar 2020
Copy of the legal title reportFile: Search Report 2.pdf9 Mar 2020
Details of encumbrancesFile: Encumberance.PDF9 Mar 2020
Copy of Layout Approval (in case of layout)File: Commencement Certificate.pdf9 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Sanctio Plan.pdf9 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plan 1.pdf9 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plan 2.pdf9 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plan 3.pdf9 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf9 Mar 2020
Declaration in FORM BFile: Declaration Form B.pdf9 Mar 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3.pdf9 Mar 2020
Proforma of Agreement for saleFile: Allotment Letter and Agreement to sale.pdf9 Mar 2020
Proforma of Allotment letterFile: Allotment Letter and Agreement to sale.pdf9 Mar 2020
OtherFile: Credai.PDF9 Mar 2020

How this compares with Akola

10%of Akola projects moved their completion datethis one has not
33%of Akola registrations have lapsed or been cancelledthis one is among them

Computed across the 120+ Akola projects on ReraGenie, from their own filings.

Keep Agrawal Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gita Nagar, Balapur Road120+ in Akola

Builder: SANJAYKUMAR OMPRAKASH BAJORIYA

SANJAYKUMAR OMPRAKASH BAJORIYA has 1 registration on MahaRERA, including Agrawal Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Akola district page.

Frequently asked questions

What does it mean that Agrawal Residency shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Agrawal Residency is delayed beyond 30 Jan 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Agrawal Residency?

The registered promoter entity is SANJAYKUMAR OMPRAKASH BAJORIYA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Agrawal Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Agrawal Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Agrawal Residency?

The professionals named in the filing: Architect: Anuraj S Agrawal; Engineer: S S MODI CONSULTANTS; Chartered Accountant: Agrawal Bajoria Padiya & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Agrawal Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Agrawal Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Agrawal Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.