Registration approved Mixed Development project

Agraja Atharva

By Sandesh Kumar Shetty

RG-KA-43902 · RERA PRM/KA/RERA/1257/334/PR/180905/001995 · Last updated on RERA Karnataka portal: 24 Mar 2022

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 19 months
  • 2 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
Apr 2022Possession promisedmoved 19 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 101 documents Report an error

Agraja Atharva is a Mixed Development project by Sandesh Kumar Shetty in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/180905/001995 on 5 Sep 2018. Possession is promised by 19 Apr 2022. The completion date has moved by 19 months from the original filing.

At a glance

Project

  • NameAgraja Atharva
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/180905/001995
  • ReraGenie IDRG-KA-43902

Builder

  • NameSandesh Kumar Shetty
  • Other registrations4 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2018First promiseSep 2020Revised toApr 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on5 Sep 2018
  • Promised completion19 Apr 2022
  • Revised completionRevised to 19 Apr 2022 (originally 9 Sep 2020)
  • Buildings1 building record
  • Documents filed101 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Agraja Atharva-----52

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 24 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 24 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area910 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.43 cr

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2020 → Jun 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1257/334/PR/221231/001995Jun 2021 → Apr 2022

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed101

As listed on the registration, under the names the promoter filed them with; the newest 80 of 101 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/180905/001995 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
valid NOC issued by KSPCBFile: POLLUTION NOC.pdf24 Mar 2022
STP POSITION MARKEDFile: AGRAJA ATHARVA-STP POSITION.pdf25 Feb 2022
STP DRAWINGFile: STP DRAWING.pdf25 Feb 2022
STP REPORTFile: STP REPORT.pdf25 Feb 2022
STP demarcated site planFile: AGRAJA ATHARVA-SITE PLAN.pdf25 Feb 2022
POLLUTION NOC PAYMENT RECEIPTFile: payment recipt pollution noc.pdf25 Feb 2022
clarificationFile: Agraja atharva-clarification.pdf25 Feb 2022
mescom fee detailsFile: fee payment to mescom.pdf10 Feb 2022
pollution noc applicationFile: Pollution noc application.pdf10 Feb 2022
payment of pollution nocFile: payment recipt pollution noc.pdf10 Feb 2022
inventory detailsFile: Agraja atharva- Inventory details.pdf10 Feb 2022
structural certficateFile: Stability certificate.pdf10 Feb 2022
affidavith of paying componsetionFile: affidavit agree to pay componseation.pdf10 Feb 2022
affidavith 3(1)File: Agraja atharva-affidavit sec 3(1).pdf10 Feb 2022
water nocFile: water noc.pdf10 Feb 2022
status of projectFile: Agraja atharva-Project details.pdf10 Feb 2022
list of allottesFile: Agraja Atharva-list of allotees.pdf10 Feb 2022
power noc challanFile: challan fo power noc.pdf10 Feb 2022
clarificationFile: Clarification.pdf10 Feb 2022
power nocFile: Atharva-Power sanction letter.pdf17 Jan 2022
clarificationFile: clarification.jpeg17 Jan 2022
clarification pdfFile: clarification.pdf17 Jan 2022
form BFile: Agraja Atharva - Form B.pdf20 Dec 2021
affidavith in form EX-7File: Agraja atharva-affidavit.pdf20 Dec 2021
Clarification on Pollution, water, power, airport authority nocFile: Clarification Agraja atharva.pdf20 Dec 2021
clarification by promoterFile: Clarification Agraja atharva.pdf20 Dec 2021
type of flat/houses/commercial detailsFile: Agraja atharva- Inventory details.pdf20 Oct 2021
pollution nocFile: Agraja atharva-Clarification by promoter.pdf20 Oct 2021
List of AllotteesFile: Agraja Atharva-list of allotees.pdf20 Oct 2021
Structural safety of the building certificateFile: Stability certificate.pdf20 Oct 2021
Affidavit abiding to pay compensation event due to delayFile: affidavit agree to pay componseation.pdf20 Oct 2021
section 3(1) Notarized AffidavitFile: Agraja atharva-affidavit sec 3(1).pdf20 Oct 2021
affidavith for extesnion of projectFile: affidavit for extesnion of project.pdf20 Oct 2021
temporary power supply nocFile: Agraja Atharva-Power supply noc.pdf20 Oct 2021
Fire Force department nocFile: Agraja atharva- fire noc.pdf20 Oct 2021
water noc and airport authority nocFile: Agraja atharva-Clarification by promoter.pdf20 Oct 2021
project ongoing status, Project Architect/Engineer detailsFile: Agraja atharva-Project details.pdf20 Oct 2021
allottment letterFile: Agraja atharva- allotment letter.pdf20 Oct 2021
clarification by promoterFile: Agraja atharva-Clarification by promoter.pdf20 Oct 2021
Architect Certificate for Work Completion Schedule till DateFile: Agraja atharva-ARC WORK COMPLETED.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Agraja atharva-ENG WORK COMPLETED.pdf-
CA Certificate for Funds UtilizationFile: Agraja atharva-CA form 3 Fund utilization.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Agraja atharva- ARC WORK PENDING.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Agraja atharva-ENG WORK PENDING.pdf-
CA Certificate for Funds required for Project CompletionFile: Agraja atharva-CA form Ex 4 Fund required.pdf-
AffidavitFile: Agraja atharva-extension affidavit.pdf-
Latest Encumbrance CertificateFile: Agraja Atharva-Ec.pdf-
Consent letter from 2/3rd of AllotteesFile: consent letter_compressed.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: Agraja atharva-extension form b.pdf-
Document 2File: Agraja Atharva- Building License.pdf-
Document 3File: SANCTION PLAN.jpg-
Document 4File: SANCTION PLAN 2.jpg-
Document 5File: consent letter with consent list.pdf-
Document 6File: SOLD UNSOLD UNIT.pdf-
Document 7File: REASON FOR DELAY.pdf-
BUILDING-
building plan_002-
LICENCE PLAN-
Sale deed-
Agreement Attarva-
Sale deed-
building plan_001-
single site-
Allotment latter-
PAMPHLET ATHARVA FINAL 16-07-2018-
single site-
specification-
Untitled-
Katha-
Sale deed-
single site-
building plan_001-
convertion-
Balance Sheet 2016 - 2017File: Balance Sheet-16-17.jpg-
Balance Sheet 2015 - 2016File: balancesheet15-16.jpg-
Balance Sheet 2014 - 2015File: Balance Sheet(14-15).jpg-
Audited Profit and Loss Statement 2016 - 2017File: Profit& Loss 16-17.jpg-
Audited Profit and Loss Statement 2015 - 2016File: profit& Loss15-16.jpg-
Audited Profit and Loss Statement 2014 - 2015File: Profit & Loss 14-15.jpg-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 19 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep Agraja Atharva on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: Sandesh Kumar Shetty

SANDESH KUMAR SHETTY has 5 registrations on RERA Karnataka, including Agraja Sampada and Agraja Atharva. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if Agraja Atharva is delayed beyond 19 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Agraja Atharva?

The registered promoter entity is Sandesh Kumar Shetty. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Agraja Atharva?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Agraja Atharva?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Agraja Atharva. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Agraja Atharva to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.