ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Aditya Crest

Registered No litigation declared Others project

Aditya Crest

By Margashirsha Infra LLP

RG-MH-48858 · RERA P52100046798 · Last updated on MahaRERA portal: 12 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2027Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 95%
0Complaints at MahaRERAon this registration
Jump to the 107 documents Report an error

Aditya Crest is a Others project by Margashirsha Infra LLP in Pune, Maharashtra, registered with MahaRERA as P52100046798 on 10 Sep 2022. Possession is promised by 15 Aug 2027.

At a glance

Project

  • NameAditya Crest
  • TypeOthers
  • Location
    • Alphonsa School Road
    • Rahatani
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411017
  • Pincode411017
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100046798
  • ReraGenie IDRG-MH-48858

Builder

  • NameMargashirsha Infra LLP
  • Entity typePartnership
  • PartnersHemlata Chandraharsh Sawant, Anjali Yashodip Dhande

Key dates

this monthRegisteredSep 2022PromisedAug 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Sep 2022
  • Promised completion15 Aug 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed107 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Aditya CrestNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.

Aditya Crest: 36% average across the applicable activities

ActivityProgress
Excavation95%
Basement (if any)85%
Podiums (if any)0%
Plinth85%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area500 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 May 2025
LandownerVillageDistrict
Suresh Kashinath BansodePimpri Chinchawad (M Corp.)Pune
Ajakumar Kashinath BansodePimpri Chinchawad (M Corp.)Pune
Mangala Shivsharan MallikarjunPimpri Chinchawad (M Corp.)Pune
Aruna Kashinath BansodePimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI2100.85
Proposed, not sanctioned1,084 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWakad, Pune

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHREE SPACES
EngineerDinesh Dhimdhime
EngineerImran Shaikh
Chartered AccountantJ S DESAI & CO.
Chartered AccountantM.S.Kumbhar And Associates
PartnerRole in project
Margashirsha Infra LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 15 Aug 2027

Documents filed107

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 107 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2022-2023)File: Form 5 2022-23.pdf12 Jun 2026
Form 5 (FY 2023-2024)File: CA Form 5 FY 23-24.pdf12 Jun 2026
Form 5 (FY 2024-2025)File: CA Form 5 FY 24-25.pdf12 Jun 2026
Form 1File: Form1 Arcitect certificate Q4.pdf1 May 2026
Form 2File: Form 2 2025-26 Q4.pdf1 May 2026
Form 3File: Form 3 2025-26 Q4.pdf1 May 2026
Disclosure of Sold and Booked InventoryFile: Inventory 2025-26 Q4.pdf1 May 2026
Form 1File: Form1 Architect certificate 2025-26 Q1.pdf28 Apr 2026
Form 2File: Form 2 2025-26 Q1.pdf28 Apr 2026
Form 3File: Form 3 CA 2025-26 Q1.pdf28 Apr 2026
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold and Booked Inventory for 2025-26 Q1.pdf28 Apr 2026
Form 1File: Form1 Arcitect Certificate FY2024-25 Q2.pdf27 Apr 2026
Form 2File: Form2 Engineers Certificate 24-25 Q2.pdf27 Apr 2026
Form 3File: Form3 CA certificate FY 2024-25 Q2.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold Booked Inventory for 24-25 Q2.pdf27 Apr 2026
Form 1File: Form 1 Architect certificate 2025-26 Q2.pdf27 Apr 2026
Form 2File: Form 2 2025-26 Q2.pdf27 Apr 2026
Form 3File: Form 3 CA 2025-26 Q2.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Discolsure Of Sold and Booked Inventory For Q2 2025-26.pdf27 Apr 2026
Form 1File: Form 1 Architect certificate 2025-26 Q3.pdf27 Apr 2026
Form 2File: Form 2 2025-26 Q3.pdf27 Apr 2026
Form 3File: Form 3 2025-26 Q3.pdf27 Apr 2026
Disclosure of Sold and Booked InventoryFile: Discolsure of Sold and Booked Inventory for Q3 2025-26.pdf27 Apr 2026
Form 1File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 1File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 1File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 2File: Form 1 Architect Certificate 2022-23 Q3.pdf16 May 2025
Form 3File: Form2 Engg Certificate 2022-23 Q3.pdf16 May 2025
Form 1File: Form2 Engg Certificate 2022-23 Q3.pdf16 May 2025
Form 2File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 3File: Form 1 Architect Certificate 2022-23 Q3.pdf16 May 2025
Form 1File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 2File: Form 1 Architect Certificate 2022-23 Q3.pdf16 May 2025
Form 3File: Form2 Engg Certificate 2022-23 Q3.pdf16 May 2025
Form 1File: Form 1 Architect Certificate 2022-23 Q3.pdf16 May 2025
Form 2File: Form2 Engg Certificate 2022-23 Q3.pdf16 May 2025
Form 3File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 1File: Form 1 Architect Certificate 2022-23 Q3.pdf16 May 2025
Form 2File: Form2 Engg Certificate 2022-23 Q3.pdf16 May 2025
Form 3File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 1File: Form 1 Architect Certificate 2022-23 Q3.pdf16 May 2025
Form 2File: Form2 Engg Certificate 2022-23 Q3.pdf16 May 2025
Form 3File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 1File: Form2 Engg Certificate 2022-23 Q3.pdf16 May 2025
Form 2File: Form 1 Architect Certificate 2022-23 Q3.pdf16 May 2025
Form 3File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 1File: Form1 Architect Certificate Q3 2024-25 Aditya Crest.pdf16 May 2025
Form 2File: Form 1 Architect Certificate FY2024-25 Q1.pdf16 May 2025
Form 3File: Form-2 Engineer's Certificate 24-25 Q1.pdf16 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate FY2023-24 Q3_compressed.pdf23 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate FY2023-24 Q4_compressed.pdf23 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate FY2024-25 Q1_compressed.pdf23 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA certificate FY 2024-25 Q2_compressed (1).pdf23 Nov 2024
Building plan approvalFile: Rev1 BP_Rahatani_74_2024 Dwg page 1 of 2_compressed.pdf19 Nov 2024
Building plan approvalFile: Rev1 BP_Rahatani_74_2024 Dwg page 2 of 2_compressed.pdf19 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-2 Engineer's Certificate 24-25 Q2.pdf19 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Rev1 BP_Rahatani_74_2024 CC Bansode Kalewadi_compressed.pdf19 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Rev1 BP_Rahatani_74_2024 Dwg page 1 of 2_compressed.pdf19 Nov 2024
Building Plan Approval / NA Order for plotted developmentFile: Rev1 BP_Rahatani_74_2024 Dwg page 2 of 2_compressed.pdf19 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form1.pdf8 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Form 5.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Architect Certificate Q1-202324.pdf25 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Architect Certificate 2023-24 Q3.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Engineer Certificate FY2023-24 Q2.pdf6 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA Certificate FY2023-24 Q2_compressed.pdf6 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Architect Certificate FY2023-24 Q2.pdf23 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate 2023-24 Q1.pdf22 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate FY2023-24 Q1.pdf22 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA Certificate FY2023-24 Q1.pdf22 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 2022-23 Q4.pdf28 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 Engg Certificate 2022-23 Q4.pdf28 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA Certificate 2022-23 Q4.pdf28 Apr 2023
Proforma of Agreement for saleFile: Draft -Agreement To Sale.pdf28 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 2022-23 Q3.pdf28 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 Engg Certificate 2022-23 Q3.pdf28 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 CA Certificate 2022-23 Q3.pdf28 Jan 2023
Declaration in FORM BFile: Form B Notarized_compressed.pdf1 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificatae Aug22.pdf1 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account details -Separate.pdf1 Sep 2022
Proforma of Allotment letterFile: Proforma of the agreement for sale.pdf4 Aug 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aditya Crest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rahatani13,700+ in Pune

2 kmAditya CrestCompleted 3Lapsed / revoked 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: Margashirsha Infra LLP

Margashirsha Infra LLP has 1 registration on MahaRERA, including Aditya Crest. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Aditya Crest is delayed beyond 15 Aug 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aditya Crest?

The registered promoter entity is Margashirsha Infra LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aditya Crest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aditya Crest?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aditya Crest?

The professionals named in the filing: Architect: SHREE SPACES; Engineer: Dinesh Dhimdhime; Engineer: Imran Shaikh; Chartered Accountant: J S DESAI & CO.; Chartered Accountant: M.S.Kumbhar And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aditya Crest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aditya Crest. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aditya Crest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.