ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / Adidhan Landmark

Registration approved Mixed Development project

Adidhan Landmark

By VIDYULLEKHA BUILDERS & DEVELOPERS

RG-KA-24085 · RERA PRM/KA/RERA/1257/334/PR/200304/003314 · Last updated on RERA Karnataka portal: 20 Feb 2020

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jun 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 60 documents Report an error

Adidhan Landmark is a Mixed Development project by VIDYULLEKHA BUILDERS & DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/200304/003314 on 4 Mar 2020. Possession is promised by 20 Jun 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameAdidhan Landmark
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1257/334/PR/200304/003314
  • ReraGenie IDRG-KA-24085

Builder

  • NameVIDYULLEKHA BUILDERS & DEVELOPERS
  • Entity typePartnership Firm
  • Authorized SignatoryAdithya Shetty
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredMar 2020First promiseSep 2021Revised toJun 2022

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on4 Mar 2020
  • Promised completion20 Jun 2022
  • Revised completionRevised to 20 Jun 2022 (originally 20 Sep 2021)
  • Buildings1 building record
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ADIDHAN LANDMARK-----51

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 20 Feb 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 20 Feb 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasYes-
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,275 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.84 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGANESH ACHARYA
EngineerNithin U

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2021 → Jun 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed60

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/200304/003314 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
SALE DEEDFile: SALE DEED 1.pdf20 Feb 2020
conversion orderFile: CONVERATION ORDER.pdf20 Feb 2020
affidavit cum declarationFile: AFFIDAVIT CUM DECLARATION.pdf20 Feb 2020
Notarized Affidavit for 3(1) ViolationFile: Notarized Affidavit for 3(1) Violation.pdf20 Feb 2020
KATHAFile: E KATHA.jpg20 Feb 2020
Registered GPAFile: GPA.pdf20 Feb 2020
EC 15 yearsFile: EC 04042005 TO 2020.pdf20 Feb 2020
SANCTION PLAN 1File: SANCTION PLAN 1.pdf20 Feb 2020
SANCTION PLAN 1File: SANCTION PLAN 2.pdf20 Feb 2020
DEED OF PARTNER SHIPFile: DEED OF PARTNERSHIP_1.pdf20 Feb 2020
FROM BFile: FROM B.pdf20 Feb 2020
DEED OF RELEASE OF 4 5TH UNDIVIED RIGHTFile: DEED OF RELEASE OF 4 5TH UNDIVIED RIGHT_1.pdf20 Feb 2020
MESCOM NOCFile: MESCOM NOC.jpeg20 Feb 2020
KSPCBFile: 32 NOC POLLUTIUON CONTROL BOARD.pdf20 Feb 2020
CertificateFile: Firm Reg Certificate.pdf-
15 COMMENCEMENT CERTIFICATE-
APPROVED PLAN-
17 Approved Layout plan-
24 Proforma of Sale Deed-
18 Proforma of agreement for Sale-
19 RTC-
20 Approved Infrastructure plan-
21 Area Development Plan-
22 Proforma Allotment Letter-
23 BROCHURE (2)-
25 Project Specifications-
ECA-
AFFIDAVIT-
AFFIDAVIT-
28 KHATHA(RTC)-
26 Joint Development Agrement-
29 Existing Layout PlanApproved Building Plan - Copy-
30 Existing Section Plan And Specification-
31 Change Of Land Use-
Balance Sheet 2017 - 2018File: 03BS 2017-18.pdf-
Balance Sheet 2016 - 2017File: 02 BS 2016-17.pdf-
Balance Sheet 2015 - 2016File: 01 BS 2015-16.pdf-
Audited Profit and Loss Statement 2017 - 2018File: 06 PL 2017-18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: 05 PL 2016-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 04 PL 2015-16.pdf-
Director's Report 2017 - 2018File: NA DIRECTORS REPORT.pdf-
Director's Report 2016 - 2017File: NA DIRECTORS REPORT.pdf-
Director's Report 2015 - 2016File: NA DIRECTORS REPORT.pdf-
Cash Flow Statement 2017 - 2018File: NA CASH FLOW STATEMENT.pdf-
Cash Flow Statement 2016 - 2017File: NA CASH FLOW STATEMENT.pdf-
Auditor's Report 2017 - 2018File: 09 Auditors Report 2017-18.PDF-
Auditor's Report 2016 - 2017File: 08 Auditors Report 2016-17.pdf-
Auditor's Report 2015 - 2016File: 07 Auditors Report 2015-16.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: 12 VIDYULLEKHA BUILDERS & DEVELOPERS PY 2017-18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: 11 VIDYULLEKHA BUILDERS & DEVELOPERS PY 2016-17.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 10 VIDYULLEKHA BUILDERS & DEVELOPERS PY 2015-16.pdf-
AFFIDAVIT-
Prospectus/BrochureFile: 23 BROCHURE (2).pdf-
Tower Excel SheetFile: PRM_KA_RERA_1257_334_PR_200304_003314 (1).xlsx-
Occupancy CertificateFile: completion certificate.pdf-
Architect certificate for having completed the work(in format no 5)File: form num 5 of adidhan landmark.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: ca certificate mukka.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: completion affidavit.pdf-
engineer certificateFile: form num 6 of adidhan landmark.pdf-
occupancy certificateFile: occupancy adidhan landmark mukka.pdf-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one moved by 9 months
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep Adidhan Landmark on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: VIDYULLEKHA BUILDERS & DEVELOPERS

VIDYULLEKHA BUILDERS & DEVELOPERS has 3 registrations on RERA Karnataka, including Adidhan Landmark and ADIDHAN SAIKRIPA. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if Adidhan Landmark is delayed beyond 20 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Adidhan Landmark?

The registered promoter entity is VIDYULLEKHA BUILDERS & DEVELOPERS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Adidhan Landmark?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Adidhan Landmark?

The professionals named in the filing: Architect: GANESH ACHARYA; Engineer: Nithin U. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Adidhan Landmark?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Adidhan Landmark. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Adidhan Landmark to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.