Home / Browse projects / Thane, Maharashtra / Abhidarshan Homes

Completed No litigation declared Residential / Group Housing project

Abhidarshan Homes

By Abhidarshan Combines

RG-MH-25003 · RERA P51700007573 · Last updated on MahaRERA portal: 24 Aug 2023

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
18 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 90%
0Complaints at MahaRERAon this registration
Jump to the 75 documents Report an error

Abhidarshan Homes is a Residential / Group Housing project by Abhidarshan Combines in Thane, Maharashtra, registered with MahaRERA as P51700007573 on 17 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameAbhidarshan Homes
  • TypeResidential / Group Housing
  • Location
    • Kalyan
    • Titwala
    • Thane
    • 421605
  • Pincode421605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700007573
  • ReraGenie IDRG-MH-25003

Builder

  • NameAbhidarshan Combines
  • Entity typePartnership
  • PartnersNilesh Laxman Patel, Shantilal Khetshi Patel, Jayantilal Jivraj Patel HUF, Sanket Virendra Patel

Key dates

this monthRegisteredAug 2017First promiseJun 2020Revised toJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on17 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 30 Jun 2020)
  • Buildings2 building records
  • Documents filed75 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-Type A - WingNA90000
A-Type B - WingNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 90%.

A-Type A - Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A-Type B - Wing88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 24 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes75%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered17
BuildingClosed/CoveredTotal
A-Type A - Wing99
A-Type B - Wing88

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area550 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3426.72
Proposed, not sanctioned2,211 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVikas Paradise, LBS Marg, Mulund West, Mumbai 400080

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnil R Nirgude
EngineerArvind S Patel
Chartered AccountantAnuja More
Chartered AccountantVidya Shetty
Chartered AccountantMamta Kholiya
PartnerRole in project
Abhidarshan Combines-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700000795Jun 2020 → Jun 2021

Reason as filed by the promoterThe Project Duration increased due to improved Construction permission received

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Mar 2022

Documents filed75

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Form 3.pdf24 Aug 2023
Certificates of CA (Form 5)File: Form 5 ABHIDARSHAN COMBINES.pdf14 Sep 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC A Type A Wing Abhidarshan .pdf3 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC A Type B Wing Abhidarshan.pdf3 Mar 2022
Architect’s Certificate on Completion of Project (Form 4)File: Form-4 Architect Certificate ABDN.pdf3 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sept 2021 Abhidarshan.pdf21 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Sept 2021 Abhidarshan.pdf21 Jan 2022
Disclosure of sold/ booked inventoryFile: sold unsold inventory A wing June 2021.pdf21 Jan 2022
Disclosure of sold/ booked inventoryFile: sold unsold inventory B wing June 2021.pdf21 Jan 2022
Disclosure of sold/ booked inventoryFile: sold unsold inventory A wing Sept 2021.pdf21 Jan 2022
Disclosure of sold/ booked inventoryFile: sold unsold inventory B wing Sept 2021.pdf21 Jan 2022
Certificates of CA (Form 3)File: FORM 3 CA Certificate.pdf21 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate june abdn.pdf18 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate June-2021 abdn.pdf18 Dec 2021
Certificates of CA (Form 3)File: CA Certifcate ABDNC_Jun 21.pdf18 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: CA certificate Form 5.pdf15 Dec 2021
Disclosure of sold/ booked inventoryFile: A Wing Sold Unsold inventory.pdf12 Oct 2021
Disclosure of sold/ booked inventoryFile: B Wing Sold Unsold inventory.pdf12 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf8 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Cetificate.pdf8 Oct 2021
Certificates of CA (Form 3)File: CA certificate March'21.pdf1 Sep 2021
Certificates of CA (Form 3)File: CA Certifcate.pdf17 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf15 May 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate-.pdf15 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate ABDN-compressed(1).pdf13 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate-compressed.pdf13 Jan 2021
Certificates of CA (Form 3)File: CA Certificate-compressed.pdf13 Jan 2021
Certificates of CA (Form 3)File: CA certificate June.pdf5 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arrchitect vitan consultants .pdf25 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate .pdf25 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect vitan consultants.pdf24 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.pdf24 Nov 2020
Certificates of CA (Form 3)File: CA certificate form 3_compressed.pdf24 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Abhidarshan Combines-min.pdf24 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Abhidarshan Form 5.pdf24 Nov 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf11 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf11 Feb 2020
Certificates of CA (Form 3)File: CA Certificate.pdf11 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's certificate.pdf23 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf23 Dec 2019
Certificates of CA (Form 3)File: CA Certificate.pdf23 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf13 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf13 Dec 2019
Certificates of CA (Form 3)File: CA certificate_compressed.pdf13 Dec 2019
Certificates of CA (Form 5)File: Form 5 Abhidarshan Combines-min.pdf12 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf18 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf18 Jul 2019
Certificates of CA (Form 3)File: Form 3 CA Certificate_compressed.pdf18 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT CERTIFICATE.pdf1 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineers Certificate.pdf1 Feb 2019
Certificates of CA (Form 3)File: Form 3 C A Certificate abhidarshan.pdf1 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate-Abhidarshan Combines.pdf15 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate-ABHIDARSHAN COMBINES.pdf15 Dec 2018
Certificates of CA (Form 3)File: Form 3 CA certificate Abhidarshan Combines.pdf15 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARchitect Certificate-ABDN.pdf12 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate- abhidarshan.pdf12 Oct 2018
Certificates of CA (Form 3)File: CA Certificate Form 3.pdf12 Oct 2018
Certificates of CA (Form 5)File: Form 5 Abhidarshan Combines.pdf29 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Abhidarshan Combines - Architect Certificate.pdf7 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Abhidarshan Combines Engineer Certificate.pdf7 Apr 2018
Certificates of CA (Form 3)File: CA RERA Certificate-pdf.pdf7 Apr 2018
Building plan approvalFile: IOD Layout.pdf29 Jul 2017
Layout approvalFile: Approval Layout.pdf29 Jul 2017
PAN CardFile: Pan card.pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate.pdf29 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Approval Layout.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOD Layout.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Comencement Certificate.pdf29 Jul 2017
Declaration in FORM BFile: Form B.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA CERTIFICATE (ABDNC).pdf29 Jul 2017
Proforma of Allotment letterFile: Agreement for sale and allotment letter.pdf29 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Abhidarshan Homes on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kalyan7,600+ in Thane

2 kmAbhidarshan HomesCompleted 45Lapsed / revoked 24Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 106 registered projects within 2 km.

Builder: Abhidarshan Combines

Abhidarshan Combines has 1 registration on MahaRERA, including Abhidarshan Homes. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Abhidarshan Homes is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Abhidarshan Homes?

The registered promoter entity is Abhidarshan Combines, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Abhidarshan Homes?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Abhidarshan Homes?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Abhidarshan Homes?

The professionals named in the filing: Architect: Anil R Nirgude; Engineer: Arvind S Patel; Chartered Accountant: Anuja More; Chartered Accountant: Vidya Shetty; Chartered Accountant: Mamta Kholiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Abhidarshan Homes?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Abhidarshan Homes. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Abhidarshan Homes to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.