Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ABD PRIDE is a Others project by ANUP BUILDERS & DEVELOPERS in Nashik, Maharashtra, registered with MahaRERA as P51600048494 on 3 Jan 2023. The registration is recorded completed; possession was promised by 31 Dec 2025.
At a glance
Project
- NameABD PRIDE
- TypeOthers
- Location
- BEHIND NAMCO HOSPITAL
- NEAR RTO OFFICE
- Nashik
- 422004
- Pincode422004
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600048494
- ReraGenie IDRG-MH-76060
Builder
- NameANUP BUILDERS & DEVELOPERS
- Entity typePartnership
- PartnerASMIT PATEL
- Other registrations1 more →
- Completed2 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on3 Jan 2023
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed72 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ABD PRIDE | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 18 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 95%.
ABD PRIDE: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 18 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed15
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| NAVIN RATILAL PATEL | Nashik Road | Nashik |
| SHREE ATRI DEVELOPERS | Nashik Road | Nashik |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SURESH N PATEL |
| Engineer | KISHOR CHOPDA |
| Chartered Accountant | ADARSH A PATEL & CO |
| Chartered Accountant | YASH SUNIL SHAH |
| Partner | Role in project |
|---|---|
| ANUP BUILDERS & DEVELOPERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Oct 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Oct 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Oct 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Oct 2024
Documents filed72
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 10-10-24.pdf | 18 Oct 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - ABD Pride.pdf | 18 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABD Pride 30092024.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate ABD PRIDE 27-07-2024.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABD Pride 30092024.pdf | 18 Oct 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate ABD Pride.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Declaration 30092024.pdf | 18 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Anup Buildcon 30062024.pdf | 12 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Anup Buildcon Engineer Certificate 29-07-2024.pdf | 12 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Anup Buildcon Sold Unsold Inventory Signed.pdf | 12 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Anup Buildcon Gurudeep Apartment Form 3 25-7-24.pdf | 12 Aug 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 ABD PRIDE Signed for Upload.pdf | 30 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 ARCHITECT CERTIFICATE 31-03-2024.pdf | 25 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 ENGINEER CERTIFICATE 30-04-2023.pdf | 25 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 ENGINEER CERTIFICATE 07-01-2024.pdf | 25 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 ENGINEER CERTIFICATE 02-04-2024.pdf | 25 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Declaration ABD Pride.pdf | 25 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 ABD Pride 15042024.pdf | 25 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 ABD FY2223.pdf | 2 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT CERTIFICATE 30062023.pdf | 11 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT CERTIFICATE 30092023.pdf | 11 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT CERTIFICATE 31122023.pdf | 11 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 30062023.pdf | 11 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 30092023.pdf | 11 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 31122023.pdf | 11 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Disclosure 30062023.pdf | 11 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Disclosure 30092023.pdf | 11 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Disclosure 31122023.pdf | 11 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 30062023.pdf | 11 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 30092023.pdf | 11 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 31122023.pdf | 11 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect.pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect.pdf | 7 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers.pdf | 7 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA-ABD_comp.pdf | 7 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 ABD PRIDE_compressed.pdf | 19 Dec 2022 |
| Details of encumbrances concerned to FinanceFile: Non Enc Finance Navin Patel.pdf | 10 Dec 2022 |
| Details of encumbrances concerned to FinanceFile: Non Enc Finance Atri.pdf | 10 Dec 2022 |
| Details of encumbrances concerned to FinanceFile: Non Enc Legal Navin Patel.pdf | 10 Dec 2022 |
| Details of encumbrances concerned to FinanceFile: Non Enc Legal Atri.pdf | 10 Dec 2022 |
| Details of encumbrances concerned to LegalFile: Non Enc Finance Navin Patel.pdf | 10 Dec 2022 |
| Details of encumbrances concerned to LegalFile: Non Enc Finance Atri.pdf | 10 Dec 2022 |
| Details of encumbrances concerned to LegalFile: Non Enc Legal Navin Patel.pdf | 10 Dec 2022 |
| Details of encumbrances concerned to LegalFile: Non Enc Legal Atri.pdf | 10 Dec 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200254437218_For_Asset_Based_Search_10_12_2022_10_32_22_017.pdf | 10 Dec 2022 |
| Proforma of Allotment letterFile: Allotment Letter rera abd pride_compressed.pdf | 10 Dec 2022 |
| Proforma of Agreement for saleFile: Rera AOS Draft ABD Builders and Developers (1).pdf | 10 Dec 2022 |
| Deviation Report with respect to Allotment letterFile: Atri Deviation AL.pdf | 10 Dec 2022 |
| Deviation Report with respect to Allotment letterFile: Navin Deviation AL.pdf | 10 Dec 2022 |
| Deviation Report with respect to model copy of AgreementFile: Atri Deviation AFS.pdf | 10 Dec 2022 |
| Deviation Report with respect to model copy of AgreementFile: Navin Deviation AFS.pdf | 10 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 12 Nov 2022 |
| Building plan approvalFile: Corporation Drawing 1.pdf | 13 Oct 2022 |
| Building plan approvalFile: Corporation Drawing 2.pdf | 13 Oct 2022 |
| Building plan approvalFile: Corporation Drawing 3.pdf | 13 Oct 2022 |
| Copy of the legal title reportFile: Legal Title Report Format A.pdf | 13 Oct 2022 |
| Copy of the legal title reportFile: Legal Title Report_compressed.pdf | 13 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Corporation Drawing 1.pdf | 13 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Corporation Drawing 2.pdf | 13 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: Corporation Drawing 3.pdf | 13 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate From 1.pdf | 13 Oct 2022 |
| Layout approvalFile: Layout Plan_compressed.pdf | 12 Oct 2022 |
| PAN CardFile: ABD PAN CARD (1).pdf | 12 Oct 2022 |
| Details of encumbrances concerned to FinanceFile: Non-Encumbrance Concerned to Finance.pdf | 12 Oct 2022 |
| Details of encumbrances concerned to LegalFile: Non-Encumbrance Concerned to Legal.pdf | 12 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: Layout Plan_compressed.pdf | 12 Oct 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: ABD Pride Commencement Certificate_compressed.pdf | 12 Oct 2022 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate (1).pdf | 12 Oct 2022 |
| Declaration in FORM BFile: From B ABD_compressed.pdf | 12 Oct 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about seperate bank account (1).pdf | 12 Oct 2022 |
| Deviation Report with respect to Allotment letterFile: Deviation Report For Allotment Letter.pdf | 12 Oct 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement to Sale.pdf | 12 Oct 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 72 filed documents as one ZIP, foldered, with a manifest
Keep ABD PRIDE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR RTO OFFICE4,100+ in Nashik
Filed coordinates, straight-line distance. 130 registered projects within 2 km.
GLOBAL VILLE
SHRADDHA INFRA
PEACOCK HILLS
PEACOCK HILLS BUILDTECH LLP
The Northland by Madhu Vitthal
Northland Realty
ANANDGRAM
MAP INFRA
RAMCHANDRA NAGAR
DESHPANDE CONSTRUCTIONS & LAND DEVELOPERS
KRISHNA PRANIT APARTMENT
BODKE BUILDCON
See every Nashik project, with the district possession charts
Builder: ANUP BUILDERS & DEVELOPERS
ANUP BUILDERS & DEVELOPERS has 2 registrations on MahaRERA, including ABD PRIDE and GURU TIRTH APARTMENT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if ABD PRIDE is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ABD PRIDE?
The registered promoter entity is ANUP BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ABD PRIDE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ABD PRIDE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ABD PRIDE?
The professionals named in the filing: Architect: SURESH N PATEL; Engineer: KISHOR CHOPDA; Chartered Accountant: ADARSH A PATEL & CO; Chartered Accountant: YASH SUNIL SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ABD PRIDE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback