Home / Browse projects / Mumbai Suburban, Maharashtra / AASHIRWAD RESIDENCY WING D

Completed No litigation declared Residential / Group Housing project

AASHIRWAD RESIDENCY WING D

By CREATIVE BUILDERS

RG-MH-29931 · RERA P51800029769 · Last updated on MahaRERA portal: 27 May 2024

Source: official MahaRERA filing

Red flags

  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

AASHIRWAD RESIDENCY WING D is a Residential / Group Housing project by CREATIVE BUILDERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029769 on 29 Jun 2021. The registration is recorded completed; possession was promised by 31 Dec 2021.

At a glance

Project

  • NameAASHIRWAD RESIDENCY WING D
  • TypeResidential / Group Housing
  • Location
    • CHANDAVARKAR ROAD
    • BORIVALI WEST
    • Borivali
    • Mumbai Suburban
    • 400092
  • Pincode400092
  • RERA no.P51800029769
  • ReraGenie IDRG-MH-29931

Builder

  • NameCREATIVE BUILDERS
  • Entity typePartnership
  • PartnersANIL PRAVINCHANDRA VORA, PARUL ANIL VORA, KEERTIKUMAR POPATLAL VORA
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2021PromisedDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jun 2021
  • Promised completion31 Dec 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AASHIRWAD RESIDENCY WING DNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

AASHIRWAD RESIDENCY WING D: 55% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed6

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots6
Closed/Covered6

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,311 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/S LEENA SHEKAR WAGH-Mumbai City

Approvals and building plan

Permissible FSI1302.77
Proposed, not sanctioned1,303 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBORIVALI WEST BRANCH

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHUL Y PANCHAL
EngineerJohan Parmar
Chartered AccountantPUNIT B GUPTA & ASSOCIATES
PartnerRole in project
CREATIVE BUILDERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013854Dec 2021 → Dec 2023

Reason as filed by the promoterWe are going to apply for the occupancy and expect the same before 31.12.2023

EXT51800012018Dec 2021 → Dec 2022

Reason as filed by the promoterDUE TO SHORTAGE OF RAW MATERIALS AND LABOURS AND ALSO ISSUE WAS FACED TO DUE ACCESS ROAD. WE WOULD REQUEST THE AUTHORITY TO GRANT US THE EXTENSION TILL 3.12.2022

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 May 2024

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate_Aashirwad Residency (2).pdf27 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - CA Certificate_Aashirwad Residency.pdf27 May 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Architect Certificate_Aashirwad Residency (1).pdf27 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Site Supervision Certificate_Aashirwad Residency.pdf25 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory_Aashirwad Residency.pdf25 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory(all sold)_Aashirwad Residency.pdf25 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A_Aashirwad Residency.pdf25 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 2A - Site Supervision Certificate_Aashirwad Residency.pdf25 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupation Certificate_Aashirwad Residency.pdf25 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Final.pdf10 Feb 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrance_Final.pdf3 Feb 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrance_Final.pdf3 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA Bank Letter_Final.pdf3 Feb 2023
CERSAI detailsFile: CERSAI AASHIRWAD RESIDENCY.pdf17 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf14 Jun 2022
Declaration about Commencement CertificateFile: DECL CC.pdf10 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect.pdf10 Jun 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DEC.pdf10 Jun 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD MARCH.pdf10 Jun 2022
Declaration about Commencement CertificateFile: CC DECL.pdf8 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.pdf8 Oct 2021
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD UPLOAD.pdf8 Oct 2021
Copy of the legal title reportFile: TITLE REPORT NEW.pdf21 Jun 2021
Declaration about Commencement CertificateFile: DECL.pdf21 Jun 2021
Layout approvalFile: APPROVED PLANS.pdf14 Jun 2021
Copy of Layout Approval (in case of layout)File: APPROVED PLANS.pdf14 Jun 2021
Proforma of Allotment letterFile: AA VA.pdf10 Jun 2021
Building plan approvalFile: IOD VV FINAL.pdf9 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: IOD VV FINAL.pdf9 Jun 2021
Declaration in FORM BFile: Creative builders Declaration Affidavit.pdf9 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf8 Jun 2021
PAN CardFile: PAN - Creative Builders.pdf20 May 2021
Details of encumbrancesFile: NO ENCUMBRANCE.pdf20 May 2021
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf20 May 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AASHIRWAD RESIDENCY WING D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORIVALI WEST6,700+ in Mumbai Suburban

Builder: CREATIVE BUILDERS

CREATIVE BUILDERS has 3 registrations on MahaRERA, including ADITYA PLAZA and AASHIRWAD RESIDENCY WING D. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AASHIRWAD RESIDENCY WING D is delayed beyond 31 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AASHIRWAD RESIDENCY WING D?

The registered promoter entity is CREATIVE BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AASHIRWAD RESIDENCY WING D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AASHIRWAD RESIDENCY WING D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AASHIRWAD RESIDENCY WING D?

The professionals named in the filing: Architect: RAHUL Y PANCHAL; Engineer: Johan Parmar; Chartered Accountant: PUNIT B GUPTA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AASHIRWAD RESIDENCY WING D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AASHIRWAD RESIDENCY WING D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AASHIRWAD RESIDENCY WING D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.