Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 3 completed earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Staircases, 80%
13 of 23Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

AASAMANTA LAXMI NARAYAN is a Others project by Aasamanta Realty in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800056447 on 31 May 2024. Possession is promised by 31 Mar 2028. 10 of the 23 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameAASAMANTA LAXMI NARAYAN
  • TypeOthers
  • Location
    • JAI PRAKASH NAGAR ROAD NO 2 AND 4
    • GOREGAON EAST
    • Goregaon
    • Borivali
    • Mumbai Suburban
    • 400063
  • Pincode400063
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800056447
  • ReraGenie IDRG-MH-18256

Builder

  • NameAasamanta Realty
  • Entity typePartnership
  • PartnerRUTA ABHIJEET SAMANT
  • Other registrations3 more →
  • Completed2 of 4
  • Declared earlier projects8 →

Key dates

this monthRegisteredMay 2024PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 May 2024
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed82 files

Current status

43%10 of 23 units booked
69.0%Work done, per cost certificate

Figures as on 15 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LAXMI NARAYAN NIWASNA151520323

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

LAXMI NARAYAN NIWAS: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed38

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots38
Closed/Covered38

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area733 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on31 Aug 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2295.31
Proposed, not sanctioned2,295 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR ACCORD COMMERCIAL NEXT TO VODAFONE GALLERY GOREGAON EAST MUMBAI 400063
Estimated costRs 33.46 cr
Cost incurredRs 23.09 cr
Work done69.02%
BuildingWingEstimatedIncurred
LAXMI NARAYAN NIWASNARs 33.46 crRs 23.09 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCORD ARCHITECTS & DESIGNERS
EngineerCHAKOR RAUL
EngineerChakor R Raul
Chartered AccountantPRAKASH A RAJBHOJ & COMPANY
Chartered AccountantDesai & Khanolkar
Chartered AccountantPrakash A Rajbhoj & Co.
PartnerRole in project
AASAMANTA REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 ALN Mar 2026.pdf15 Apr 2026
Withdrawal Update Form 2File: Form 2 ALN Mar 2026.pdf15 Apr 2026
Withdrawal Update Form 3File: Form 3 ALN Mar 2026.pdf15 Apr 2026
Withdrawal Update Form 1File: Form 1 Architect Cert ALN.pdf12 Jan 2026
Withdrawal Update Form 2File: Form 2 Eng Cert ALN.pdf12 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate ALN Dec 2025.pdf12 Jan 2026
Withdrawal Update Form 1File: 9-Architect certificate.pdf9 Nov 2025
Withdrawal Update Form 1File: 9-Architect certificate.pdf9 Nov 2025
Withdrawal Update Form 1File: 9-Architect certificate.pdf9 Nov 2025
Withdrawal Update Form 1File: 9-Architect certificate.pdf9 Nov 2025
Withdrawal Update Form 2File: Form 2 ALN.pdf9 Nov 2025
Withdrawal Update Form 2File: Form 2 ALN.pdf9 Nov 2025
Withdrawal Update Form 2File: Form 2 ALN.pdf9 Nov 2025
Withdrawal Update Form 2File: Form 2 ALN.pdf9 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate sept 25.pdf9 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate sept 25.pdf9 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate sept 25.pdf9 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate sept 25.pdf9 Nov 2025
Form 1File: Form 1 Architect Certificate ALN.pdf30 Aug 2025
Form 2File: Form 2 Site Engineer Certificate ALN.pdf30 Aug 2025
Form 3File: Form 3 CA Certificate ALN.pdf30 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold june 24.pdf30 Aug 2025
Form 1File: Form 1 Architect Certificate.pdf30 Aug 2025
Form 2File: Form 2 LN Q Sept 2024.pdf30 Aug 2025
Form 3File: Form 3 CA Certificate Sept 24.pdf30 Aug 2025
Disclosure of Sold and Booked InventoryFile: Dis Sold unsold sept 24.pdf30 Aug 2025
Form 1File: Form 1 ALN 310325.pdf30 Aug 2025
Form 2File: Form 2 ALN 310325.pdf30 Aug 2025
Form 3File: Form 3 ALN 310325.pdf30 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold.pdf30 Aug 2025
Form 1File: Form 1 Arch Certificate.pdf10 Jul 2025
Form 2File: Form 2 Engineers Certificate.pdf10 Jul 2025
Form 3File: Form 3 CA Cert Laxmi Narayan.pdf10 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold and unsold.pdf10 Jul 2025
Form 1File: Form 1 Architect Certificate ALN.pdf10 Jul 2025
Form 2File: Fom - 2 Engineer Certificate ALN.pdf10 Jul 2025
Form 3File: Form 3 CA Certificate ALN.pdf10 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold.pdf10 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ALN 310325.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 ALN 310325.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ALN 310325.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Cert Laxmi Narayan.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 LN Q Sept 2024.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold and unsold.pdf28 Jan 2025
Declaration about Commencement CertificateFile: Diclaration of CC.pdf28 Jan 2025
Building plan approvalFile: Amended IOD.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf20 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf20 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Amended IOD.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate ALN.pdf24 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Site Engineer Certificate ALN.pdf24 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate ALN.pdf24 Jul 2024
Proforma of Agreement for saleFile: Model form of Agreement.pdf15 May 2024
Other - TechnicalFile: Declaration cum undertaking.pdf5 May 2024
Layout approvalFile: IOD 1.pdf30 Apr 2024
Building plan approvalFile: IOD 1.pdf30 Apr 2024
Building plan approvalFile: IOD 2.pdf30 Apr 2024
Building plan approvalFile: IOD 3.pdf30 Apr 2024
Details of encumbrances concerned to FinanceFile: Declaration for no encumbrances.pdf30 Apr 2024
Details of encumbrances concerned to LegalFile: Declaration for no encumbrances.pdf30 Apr 2024
Copy of Layout Approval (in case of layout)File: IOD 1.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD 1.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD 2.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD 3.pdf30 Apr 2024
Declaration in FORM BFile: Form B Owner cum Developer.pdf30 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf30 Apr 2024
Proforma of Allotment letterFile: Draft Allotment letter.pdf30 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Seperate Bank Accounts Details.pdf30 Apr 2024
Deviation Report with respect to Allotment letterFile: Letter for deviation report for AL and AFS.pdf30 Apr 2024
Deviation Report with respect to model copy of AgreementFile: Letter for deviation report for AL and AFS.pdf30 Apr 2024
Building plan approvalFile: IOD LAXMI NARAYAN.pdf29 Apr 2024
PAN CardFile: Aasamanta PAN Card.pdf29 Apr 2024
Copy of the legal title reportFile: Format A legal title report.pdf29 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD LAXMI NARAYAN.pdf29 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: First CC Laxmi.pdf29 Apr 2024
Declaration about Commencement CertificateFile: Declaration about CC.pdf29 Apr 2024
CERSAI detailsFile: CERSAI Search Report 28042024.pdf29 Apr 2024

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise1 under way, not due yet
ProjectLocationRegisteredStatusPromisedDelivered
Aasamanta White Housep51800080224409, Plot No 24 of Jai Prakash Nagar Junction of Jai Prakash Road No 3 and 4, Goregaon East, Goregaon, Borivali, Mumbai Suburban, 400063, MAHARASHTRA-OngoingMar 2028Not due yet
RBI EMPLOYEES SANDESH CHSLP51800045386GOREGAON EAST, Mumbai SuburbanMay 2022CompletedMar 2025Mar 2025
KRUPAP51800032389GOREGAON EAST, Mumbai SuburbanJan 2022CompletedMar 2024Mar 2024
AMAR PRABHAPLOT NO 25 JAYPRAKASH NAGAR GOREGAON EAST MUMBAI-CompletedJul 2017Jul 2017

How this compares with Mumbai Suburban

43%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AASAMANTA LAXMI NARAYAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GOREGAON EAST6,700+ in Mumbai Suburban

2 kmAASAMANTA LAXMI NARAYANCompleted 142Lapsed / revoked 71Other 135Dot size: filed unitsN

Filed coordinates, straight-line distance. 348 registered projects within 2 km.

Builder: Aasamanta Realty

AASAMANTA REALTY has 4 registrations on MahaRERA, including KRUPA and RBI EMPLOYEES SANDESH CHSL. Its filings disclose 8 earlier MahaRERA projects: declares 6 of 7 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AASAMANTA LAXMI NARAYAN is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AASAMANTA LAXMI NARAYAN?

The registered promoter entity is Aasamanta Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AASAMANTA LAXMI NARAYAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AASAMANTA LAXMI NARAYAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AASAMANTA LAXMI NARAYAN?

The professionals named in the filing: Architect: ARCORD ARCHITECTS & DESIGNERS; Engineer: CHAKOR RAUL; Engineer: Chakor R Raul; Chartered Accountant: PRAKASH A RAJBHOJ & COMPANY; Chartered Accountant: Desai & Khanolkar; Chartered Accountant: Prakash A Rajbhoj & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AASAMANTA LAXMI NARAYAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AASAMANTA LAXMI NARAYAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AASAMANTA LAXMI NARAYAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.