Home / Browse projects / Satara, Maharashtra / AAPLA GHAR SHIRWAL PHASE 2

De-registered No litigation declared Residential / Group Housing project

AAPLA GHAR SHIRWAL PHASE 2

By BLUE LADDER ESTATES PVT LTD

RG-MH-27332 · RERA P52700033164 · Last updated on MahaRERA portal: 3 Feb 2026

Source: official MahaRERA filing

Red flags

  • De-registered
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 24 months from the original
4 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 75%
2 of 2Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

AAPLA GHAR SHIRWAL PHASE 2 is a Residential / Group Housing project by BLUE LADDER ESTATES PVT LTD in Satara, Maharashtra, registered with MahaRERA as P52700033164 on 9 Feb 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 0 of the 2 units on this registration are recorded sold or booked, and 4 of 22 construction stages are filed complete.

At a glance

Project

  • NameAAPLA GHAR SHIRWAL PHASE 2
  • TypeResidential / Group Housing
  • Location
    • OFF PUNE SATARA ROAD
    • SHIRWAL
    • Dhangarwadi
    • Khandala
    • Satara
    • 415521
  • Pincode415521
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700033164
  • ReraGenie IDRG-MH-27332

Builder

  • NameBLUE LADDER ESTATES PVT LTD
  • Entity typeCompany
  • Managing DirectorSACHIN ASHOK AGARWAL
  • DirectorNITIN BIPIN SHAH

Key dates

this monthRegisteredFeb 2022First promiseDec 2025Revised toDec 2027

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on9 Feb 2022
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed96 files

Current status

0%0 of 2 units booked
29.2%Work done, per cost certificate

Figures as on 3 Feb 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C-05NA42101
C-10NA42101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 3 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 75%.

C-0536%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C-1023%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes25%
Storm Water DrainsYes25%
Landscaping & Tree PlantingYes15%
Street LightingYes25%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
C-0511
C-1011

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area291 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Sep 2025

Approvals and building plan

Sanctioning authorityTown Planning Satara
Permissible FSI288.79
Proposed, not sanctioned289 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFC ROAD PUNE
Estimated costRs 24.25 cr
Cost incurredRs 7.09 cr
Work done29.24%
BuildingWingEstimatedIncurred
-NARs 23.50 crRs 6.75 cr
C-05NARs 37.50 lakhRs 22.50 lakh
C-10NARs 37.50 lakhRs 11.50 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNavin Agarwal
EngineerRajesh Choudhari
Chartered AccountantKrishnaKant Agarwal
PartnerRole in project
BLUE LADDER ESTATES PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA03102518008Dec 2025 → Dec 2027

Reason as filed by the promoterSupply chain disruptions and increased lead times for the delivery of essential construction materials, such as cement, steel, and other building components, have caused delays in the construction schedule. The scarcity of these materials in the local market and price volatility have further compounded the problem, leading to intermittent halts in construction activities. Additionally, there has been a marked shortage of both skilled and unskilled labour in the construction sector, adversely affecting the developer's capacity to sustain the required workforce levels necessary for the continuou

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Form 1.pdf3 Feb 2026
Withdrawal Update Form 1File: Architect Form 1.pdf3 Feb 2026
Withdrawal Update Form 2File: Engineer Form 2-Final.pdf3 Feb 2026
Withdrawal Update Form 2File: Engineer Form 2-Final.pdf3 Feb 2026
Withdrawal Update Form 3File: FORM 3 MENLO FRONT YARD.pdf3 Feb 2026
Withdrawal Update Form 3File: FORM 3 MENLO FRONT YARD.pdf3 Feb 2026
Withdrawal Update Form 1File: Architect Certificate Q3.pdf19 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate Apla ghar shirwal phase 2.pdf19 Jan 2026
Withdrawal Update Form 3File: SHIWAL FORM 3 Q3-25-26.pdf19 Jan 2026
Withdrawal Update Form 1File: Architect Certificate Apla Ghar Shirwal 2.pdf14 Oct 2025
Withdrawal Update Form 2File: Engineer Certificate 30092025.pdf14 Oct 2025
Withdrawal Update Form 3File: SHIWAL FORM 3 Q2-25-26.pdf14 Oct 2025
Form 5 (FY 2021-2022)File: 2021-22.pdf18 Sep 2025
Form 5 (FY 2022-2023)File: 2022-23.pdf18 Sep 2025
Form 5 (FY 2023-2024)File: 2023-24.pdf18 Sep 2025
Form 5 (FY 2024-2025)File: 2024-25.pdf18 Sep 2025
Form 2A (FY 2023-2024)File: Shirwal 2023-2024.pdf13 Sep 2025
Form 2A (FY 2024-2025)File: Sirwal 2024-2025.pdf13 Sep 2025
Form 2A (FY 2021-2022)File: Shirwal -2021-2022.pdf11 Sep 2025
Form 2A (FY 2022-2023)File: Shirwal -2022-2023.pdf11 Sep 2025
Form 1File: Architect Form 300622.pdf10 Sep 2025
Form 2File: ENGForm 300622.pdf10 Sep 2025
Form 3File: Form3 300622.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD30062022.pdf10 Sep 2025
Form 1File: Architect Form 300622.pdf10 Sep 2025
Form 2File: ENGForm 300622.pdf10 Sep 2025
Form 3File: Form3 300622.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD30062022.pdf10 Sep 2025
Form 1File: Architect Form 311222.pdf10 Sep 2025
Form 2File: ENG Form 311222.pdf10 Sep 2025
Form 3File: form3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form 31323.pdf10 Sep 2025
Form 2File: ENG Form 31323.pdf10 Sep 2025
Form 3File: Form3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form 30623.pdf10 Sep 2025
Form 2File: Eng Form 30623.pdf10 Sep 2025
Form 3File: Form 3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form 30923.pdf10 Sep 2025
Form 2File: Eng Form 30923.pdf10 Sep 2025
Form 3File: Form3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form 311223.pdf10 Sep 2025
Form 2File: Eng Form 311223.pdf10 Sep 2025
Form 3File: Form3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form 31324.pdf10 Sep 2025
Form 2File: Eng Form 31324.pdf10 Sep 2025
Form 3File: Form 3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form 30624.pdf10 Sep 2025
Form 2File: eng Form 30624.pdf10 Sep 2025
Form 3File: Form3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form30924.pdf10 Sep 2025
Form 2File: Engineer Form 2- 3009.pdf10 Sep 2025
Form 3File: form3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form 311224.pdf10 Sep 2025
Form 2File: Eng Form 311224.pdf10 Sep 2025
Form 3File: Form3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Form 1File: Architect Form 31325.pdf10 Sep 2025
Form 2File: Engineer Form 2- 31032025.pdf10 Sep 2025
Form 3File: Form3.pdf10 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf10 Sep 2025
Withdrawal Update Form 1File: BlueLadder Architect Certificate.pdf10 Sep 2025
Withdrawal Update Form 2File: Engineer Form300625.pdf10 Sep 2025
Withdrawal Update Form 3File: form3.pdf10 Sep 2025
Form 1File: Architect Form 31322.pdf2 Sep 2025
Form 2File: ENG Form 31322.pdf2 Sep 2025
Form 3File: Form 3 old.pdf2 Sep 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD.pdf2 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: BlueLadder Architect Certificate.pdf28 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Blueladder Engineer Certificate.pdf28 Oct 2023
Disclosure of sold/ booked inventoryFile: sold unsold.pdf28 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1- Shirwal.pdf21 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2-Final-Shirwal.pdf21 Feb 2023

How this compares with Satara

0%of this project is bookeddistrict median 15%
16%of Satara projects moved their completion datethis one moved by 24 months
35%of Satara registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep AAPLA GHAR SHIRWAL PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHIRWAL1,100+ in Satara

2 kmAAPLA GHAR SHIRWAL PHASECompleted 1Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: BLUE LADDER ESTATES PVT LTD

BLUE LADDER ESTATES PVT LTD has 1 registration on MahaRERA, including AAPLA GHAR SHIRWAL PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What does it mean that AAPLA GHAR SHIRWAL PHASE 2 shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AAPLA GHAR SHIRWAL PHASE 2 is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AAPLA GHAR SHIRWAL PHASE 2?

The registered promoter entity is BLUE LADDER ESTATES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AAPLA GHAR SHIRWAL PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AAPLA GHAR SHIRWAL PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AAPLA GHAR SHIRWAL PHASE 2?

The professionals named in the filing: Architect: Navin Agarwal; Engineer: Rajesh Choudhari; Chartered Accountant: KrishnaKant Agarwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAPLA GHAR SHIRWAL PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAPLA GHAR SHIRWAL PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAPLA GHAR SHIRWAL PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.