Completed No litigation declared Residential / Group Housing project

AAMOD

By TODAY GLOBAL REALTORS

RG-MH-60205 · RERA P52000030717 · Last updated on MahaRERA portal: 26 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
28 of 55Construction stages doneacross 5 buildings; furthest along: Internal walls, 90%
80 of 275Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

AAMOD is a Residential / Group Housing project by TODAY GLOBAL REALTORS in Raigarh, Maharashtra, registered with MahaRERA as P52000030717 on 8 Sep 2021. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 12 months from the original filing. 195 of the 275 units on this registration are recorded sold or booked, and 28 of 55 construction stages are filed complete.

At a glance

Project

  • NameAAMOD
  • TypeResidential / Group Housing
  • Location
    • NANDGAON
    • PANVEL
    • Raigarh
    • 410221
  • Pincode410221
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000030717
  • ReraGenie IDRG-MH-60205

Builder

  • NameTODAY GLOBAL REALTORS
  • Entity typePartnership
  • PartnersBHADRESH RAJESH SHAH, RAJESH BHOGILAL SHAH, GANESHLAL BADICHAND RAJAVAT, JAYANTILAL LAXMICHAND DOSHI, KANAIYALAL GURMUKHDAS KHANEJA, SARITA VIKAS GUPTA, MAMTA ROSHANLAL JAIN, RATAN RAJESH GUPTA, MOHNISH VIKAS GUPTA

Key dates

this monthRegisteredSep 2021First promiseDec 2024Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Sep 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings5 building records
  • Documents filed92 files

Current status

71%195 of 275 units booked

Figures as on 26 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO - A1NA9860969
BUILDING NO - A2NA9860969
BUILDING NO - B - EWS AND SALENA6524024
BUILDING NO - CNA9877077
BUILDING NO - D EWSNA6536036

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 26 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 90%.

BUILDING NO - A172%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO - A266%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO - B - EWS AND SALE60%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO - C53%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO - D EWS73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 26 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered4
BuildingClosed/CoveredTotal
BUILDING NO - A111
BUILDING NO - A211
BUILDING NO - B - EWS AND SALE11
BUILDING NO - D EWS11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area10,840 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Jul 2025

Approvals and building plan

Sanctioning authorityCIDCO NAINA
Permissible FSI12726.27
Proposed, not sanctioned12,726 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSANPADA

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectACUBE ARCHITECTS
EngineerSANGHAVI AND ASSOCIATES CONSULTANTS PVT LTD
Engineeraadesh shah shah
Chartered AccountantMAIDAWAT AND ASSOCIATES
Chartered AccountantSwati Sudhendu Patel
PartnerRole in project
TODAY GLOBAL REALTORS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000026002Dec 2024 → Dec 2025

Reason as filed by the promoterShortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized trades. The COVID-19 pandemic has resulted in the migration of a large proportion of the labor force, particularly migrant workers, back to their native regions due to lockdowns, health concerns, and other social and economic factors. As a consequence, a substantial number of workers previously engaged on-site have been unable to return, thereby halting criti

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: 2666_001.pdf26 Jun 2026
Form 5 (FY 2024-2025)File: Scan Form-5 TGR-0717.pdf9 Oct 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory Aamod.pdf21 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Q4.pdf21 Apr 2025
Declaration in FORM BFile: P52000030717_FileName_5.pdf22 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: bank.pdf22 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: merge (1)_compressed.pdf22 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: 1 Details of encumbrances.pdf22 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: merge (1)_compressed.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: AAAMOD - SOLD UNSOLD_compressed.pdf15 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Today Global Realtors_0001 (1).pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-1.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3-2.pdf14 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FOMR 2.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1.pdf11 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_compressed.pdf11 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf11 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Inventory Aamod.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AMOD.pdf1 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf1 Jan 2025
CERSAI detailsFile: 1 Details of encumbrances.pdf1 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Details of encumbrances.pdf1 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a.pdf1 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 05.pdf1 Jan 2025
Disclosure of sold/ booked inventoryFile: TGR.pdf9 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM- 01.pdf30 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Aamod.pdf30 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Aamod.pdf30 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Aamod.pdf30 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 02.pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 03_compressed.pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE WORK.pdf10 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: TODAY GLOBAL REALTORS FORM 2_11zon.pdf27 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: TODAY GLOBAL REALTORS FORM 2 A.pdf27 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: TODAY GLOBAL REALTORS FORM 3_11zon.pdf27 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AamodARCHITECT CERTIFICATE.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate aamod.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Aamod.pdf16 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: TGR FORM 5.pdf11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineers Certificate.pdf14 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf14 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf14 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 03 - ARCHITECT CERTIFICATE- WORK STATUS TILL 06-07-23_Aamod.pdf7 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-02-30-06-2023_Compressed_11zon.pdf7 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 03 30-06-2023.pdf7 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AAMOD- ARCHITECT'S CETIFICATE- WORK STATUS TILL 31-10-2021_11zon.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AAMOD- ARCHITECT'S CETIFICATE- WORK STATUS TILL 12-04-23_11zon.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AAMOD- ARCHITECT'S CETIFICATE- WORK STATUS TILL 11-07-2022_11zon.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AAMOD- ARCHITECT'S CETIFICATE- WORK STATUS TILL 06-01-23_11zon.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AAMOD- ARCHITECT'S CETIFICATE- WORK STATUS TILL 05-05-2022_11zon.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AAMOD- ARCHITECT'S CETIFICATE- WORK STATUS TILL 01-10-2022_11zon.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 02 31-12-2021.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 02 31-03-2023.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 02 31-03-2022.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 02 30-09-2022.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 30-06-2022_11zon.pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02 31-12-2022_11zon.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 03 31-12-2021.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 03 31-03-2023.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 2 30-09-2022.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 03 30-09-2022.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 31-12-2022.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 03 30-06-2022.pdf17 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 03 31-03-2022.pdf17 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aamod RERA certificate 12-04-23.pdf14 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: aamod form 2a 31-03-2023.pdf7 Apr 2023
Details of encumbrances concerned to FinanceFile: hero mortgage deed.pdf27 Mar 2023
Details of encumbrances concerned to LegalFile: hero mortgage deed.pdf27 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY NAME RESEERVATION LETTER.pdf18 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: tgr rera form 5.pdf3 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Today global Realtors Form 2A.pdf1 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: TGR.pdf14 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: TGR.pdf14 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: TGR 31.pdf14 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: aamod rera architect certificate.pdf11 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: TGR P1.pdf9 Oct 2021
Copy of the legal title reportFile: LEGAL TITLE REPORT - TODAY GLOBAL REALTORS.pdf23 Aug 2021

How this compares with Raigarh

71%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 12 months
26%of Raigarh registrations have lapsed or been cancelledthis one is completed

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AAMOD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PANVEL5,900+ in Raigarh

Builder: TODAY GLOBAL REALTORS

TODAY GLOBAL REALTORS has 1 registration on MahaRERA, including AAMOD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if AAMOD is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AAMOD?

The registered promoter entity is TODAY GLOBAL REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AAMOD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AAMOD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AAMOD?

The professionals named in the filing: Architect: ACUBE ARCHITECTS; Engineer: SANGHAVI AND ASSOCIATES CONSULTANTS PVT LTD; Engineer: aadesh shah shah; Chartered Accountant: MAIDAWAT AND ASSOCIATES; Chartered Accountant: Swati Sudhendu Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAMOD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAMOD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAMOD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.