ReraGenieLog inGet a buyer report

Home / Browse projects / Sangli, Maharashtra / AADI BHAGWANT

Registered No litigation declared Others project

AADI BHAGWANT

By AADI BHAGWANT DEVELOPERS

RG-MH-95293 · RERA P53100055077 · Last updated on MahaRERA portal: 27 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Sangli registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 70%
66 of 68Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

AADI BHAGWANT is a Others project by AADI BHAGWANT DEVELOPERS in Sangli, Maharashtra, registered with MahaRERA as P53100055077 on 29 Feb 2024. Possession is promised by 31 Dec 2027. 2 of the 68 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameAADI BHAGWANT
  • TypeOthers
  • Location
    • VISHRAMBAG
    • DATTA NAGAR
    • Sangli Miraj Kupwad (M Corp.)
    • Miraj
    • Sangli
    • 416416
  • Pincode416416
  • RERA no.P53100055077
  • ReraGenie IDRG-MH-95293

Builder

  • NameAADI BHAGWANT DEVELOPERS
  • Entity typePartnership
  • PartnersAJINKYA PRAKASH SHINDE, PRAKASH DATTATRAYA SHINDE, GIRISH SHANKARRAO YADAV, ANIRUDDHA MADHUKAR PATIL, ADITYARAJ PRAMOD SHINDE, PARAG BHANUDAS BAPAT, JAYNARAYAN TEXTILE LLP THRU NIKHIL NAWANDHAR

Key dates

this monthRegisteredFeb 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Feb 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed72 files

Current status

3%2 of 68 units booked
14.5%Work done, per cost certificate

Figures as on 27 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AADI BHAGWANT ANANDAMNA131360868

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 70%.

AADI BHAGWANT ANANDAM: 22% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth70%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed170

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots170
Closed/Covered170

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,948 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on26 Dec 2025

Approvals and building plan

Sanctioning authoritySMKC
Permissible FSI8114.52
Proposed, not sanctioned8,115 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTIMBER AREA SANGLI
Estimated costRs 18.00 cr
Cost incurredRs 2.61 cr
Work done14.5%
BuildingWingEstimatedIncurred
AADI BHAGWANT ANANDAMNARs 15.00 crRs 2.61 cr
-NARs 3.00 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectABHISHEK VORA
EngineerRIYAZ A Faras
Chartered AccountantMORESHWAR G DESHPANDE
Chartered Accountantmegha mahesh jadhav
PartnerRole in project
AADI BHAGWANT DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 up to March 2026.pdf27 Jun 2026
Withdrawal Update Form 2File: Form 2 up to March 2026.pdf27 Jun 2026
Withdrawal Update Form 3File: Form 3 up to March 2026.pdf27 Jun 2026
Withdrawal Update Form 1File: Form 1 Up to Dec 2025.pdf12 Feb 2026
Withdrawal Update Form 2File: Form 2 Up to Dec 2025.pdf12 Feb 2026
Withdrawal Update Form 3File: Form 3 Up to Dec 2025.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1 Up to Jun 2025.pdf27 Jan 2026
Withdrawal Update Form 1File: Form 1 Up to Jun 2025.pdf27 Jan 2026
Withdrawal Update Form 1File: Form 1 Up to Sep 2025.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2 Up to Jun 2025.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2 Up to Jun 2025.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2 Up to Sep 2025.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3 Up to Jun 2025.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3 Up to Jun 2025.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3 Up to Sep 2025.pdf27 Jan 2026
Form 5 (FY 2023-2024)File: Form 5 23-24.pdf27 Dec 2025
Form 1File: Form 1 Up to Jun 2024.pdf26 Dec 2025
Form 2File: Form 2 Up to Jun 2024.pdf26 Dec 2025
Form 3File: Form 3 Up to Jun 2024.pdf26 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold up to Jun 2024.pdf26 Dec 2025
Form 1File: Form 1 Up to Sep 2024.pdf26 Dec 2025
Form 2File: Form 2 Up to Sep 2024.pdf26 Dec 2025
Form 3File: Form 3 Up to Sep 2024.pdf26 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold up to Sep 2024.pdf26 Dec 2025
Form 1File: Form 1 Up to December 2024.pdf26 Dec 2025
Form 2File: Form 2 Up to December 2024.pdf26 Dec 2025
Form 3File: Form 3 Up to December 2024.pdf26 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold up to Dec 2024.pdf26 Dec 2025
Form 1File: Form 1 up to March 2024.pdf26 Dec 2025
Form 2File: Form 2 up to March 2024.pdf26 Dec 2025
Form 3File: Form 3 up to March 2024.pdf26 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Summary up to March 24.pdf26 Dec 2025
Form 1File: Form 1.pdf1 Nov 2025
Form 2File: Form 2.pdf1 Nov 2025
Form 3File: Form 3.pdf1 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf1 Nov 2025
Form 5 (FY 2024-2025)File: FORM 5 2024-25.pdf11 Oct 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023 - 2024.pdf22 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2a 23-24.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf11 Apr 2025
Disclosure of sold/ booked inventoryFile: dec 2024.pdf11 Apr 2025
Disclosure of sold/ booked inventoryFile: mar 2025.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: UP TO JUN.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: UP TO SEP.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: 1ST SOLD .pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: 2ND SOLD.pdf18 Oct 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A.pdf26 Feb 2024
Other - TechnicalFile: smkc.pdf7 Feb 2024
Other - TechnicalFile: SMKC MAIL.pdf2 Feb 2024
Proforma of Agreement for saleFile: 6 Draft Model Agreement Annexure 'A' - MAHARERA Format (1).pdf11 Jan 2024
Other - LegalFile: SALE DEED.pdf11 Jan 2024
Copy of the legal title reportFile: SEARCH REPORT.pdf11 Dec 2023
Declaration about Commencement CertificateFile: format d aadi.pdf11 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca aadi bhawga.pdf11 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: aNNEXURE A.pdf11 Dec 2023
Deviation Report with respect to model copy of AgreementFile: agreement deviation.pdf11 Dec 2023
Building plan approvalFile: 1.pdf8 Dec 2023
Building plan approvalFile: 2.pdf8 Dec 2023
Layout approvalFile: LAY OUT AADI.pdf8 Dec 2023
PAN CardFile: pan card.pdf8 Dec 2023
Details of encumbrances concerned to FinanceFile: Finance Encumbrances.pdf8 Dec 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf8 Dec 2023
Details of encumbrances concerned to LegalFile: Finance Encumbrances.pdf8 Dec 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf8 Dec 2023
Copy of Layout Approval (in case of layout)File: LAY OUT AADI.pdf8 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf8 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf8 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: permission AAdi.pdf8 Dec 2023
Declaration in FORM BFile: Forn B.pdf8 Dec 2023
CERSAI detailsFile: Cersai.pdf8 Dec 2023
Proforma of Allotment letterFile: Allotment letter foramt.pdf8 Dec 2023
Deviation Report with respect to Allotment letterFile: Allotment Deviation.pdf8 Dec 2023

How this compares with Sangli

3%of this project is bookeddistrict median 16%
11%of Sangli projects moved their completion datethis one has not
29%of Sangli registrations have lapsed or been cancelledthis one is on the register

Computed across the 790+ Sangli projects on ReraGenie, from their own filings.

Keep AADI BHAGWANT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DATTA NAGAR790+ in Sangli

Builder: AADI BHAGWANT DEVELOPERS

AADI BHAGWANT DEVELOPERS has 1 registration on MahaRERA, including AADI BHAGWANT. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sangli district page.

Frequently asked questions

What are my rights if AADI BHAGWANT is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AADI BHAGWANT?

The registered promoter entity is AADI BHAGWANT DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AADI BHAGWANT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AADI BHAGWANT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AADI BHAGWANT?

The professionals named in the filing: Architect: ABHISHEK VORA; Engineer: RIYAZ A Faras; Chartered Accountant: MORESHWAR G DESHPANDE; Chartered Accountant: megha mahesh jadhav. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AADI BHAGWANT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AADI BHAGWANT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AADI BHAGWANT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.