ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Aadhya

Registered No litigation declared Residential / Group Housing project

Aadhya

By Gagangiri Construction

RG-MH-30800 · RERA P51800079135 · Last updated on MahaRERA portal: 25 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 40%
49 of 82Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

Aadhya is a Residential / Group Housing project by Gagangiri Construction in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800079135 on 10 Feb 2025. Possession is promised by 31 Dec 2029. 33 of the 82 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameAadhya
  • TypeResidential / Group Housing
  • Location
    • RDP Road No 8
    • Mumbai
    • Kandivali
    • Borivali
    • Mumbai Suburban
    • 400067
  • Pincode400067
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800079135
  • ReraGenie IDRG-MH-30800

Builder

  • NameGagangiri Construction
  • Entity typePartnership
  • GSTIN27AAXFG0140Q1ZT
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredFeb 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Feb 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed62 files

Current status

40%33 of 82 units booked
25.0%Work done, per cost certificate

Figures as on 25 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AadhyaNA181879382

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 40%.

Aadhya: 33% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered51

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area752 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Oct 2025
LandownerVillageDistrict
G.I.C. Employee's Charkop Sea Rock CHS LTD.KandivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMaharashtra Housing and Area Development Authority
Permissible FSI7094.31
Proposed, not sanctioned5,537 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Mona Building 2, J. P. Road, Next To Navrang Cinema, Andheri W, Mumbai.400058
Estimated costRs 22.23 cr
Cost incurredRs 5.56 cr
Work done25.0%
BuildingWingEstimatedIncurred
AadhyaNARs 22.23 crRs 5.56 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMs HRJ Architect & PMC
EngineerSihavat Consultancy Services
EngineerSanjay Rane & Associates
Chartered AccountantP V Dalal & Co
Chartered AccountantJignesh shah & Co
Chartered AccountantHarshada & Associates
PartnerRole in project
Gagangiri Construction-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jan 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 May 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Signed Searock Form-5.pdf25 May 2026
Commencement certificateFile: CC 15537_furthercc_signed (2).pdf2 May 2026
Withdrawal Update Form 1File: Signed Withdrawal Application Form1.pdf2 May 2026
Withdrawal Update Form 2File: Signed Form-2.pdf2 May 2026
Withdrawal Update Form 3File: Signed Form 3.pdf2 May 2026
Withdrawal Update Form 1File: scanned form -1 Searock.pdf6 Jan 2026
Withdrawal Update Form 2File: Scanned Form-2 Searock.pdf6 Jan 2026
Withdrawal Update Form 3File: Scanned Form-3 Searock with sign.pdf6 Jan 2026
Withdrawal Update Form 1File: Annexure A Form 1 Architect Certificate Sea Rock.pdf27 Oct 2025
Withdrawal Update Form 2File: Annexure B Form 2 Engineers Certificate Sea Rock.pdf27 Oct 2025
Withdrawal Update Form 3File: Withdrawal Scan Form 3.pdf27 Oct 2025
Withdrawal Update Form 1File: Scaned Form 1 Architects Certificate.pdf15 Oct 2025
Withdrawal Update Form 1File: Scaned Form 1 Architects Certificate.pdf15 Oct 2025
Withdrawal Update Form 2File: Form 2 Sea Rock.pdf15 Oct 2025
Withdrawal Update Form 2File: Form 2 Sea Rock.pdf15 Oct 2025
Withdrawal Update Form 3File: Form 3 Aadhya.pdf15 Oct 2025
Withdrawal Update Form 3File: Form 3 Aadhya.pdf15 Oct 2025
Other - TechnicalFile: SEAROCK MAIL CC from MHADA.pdf3 Feb 2025
Other - TechnicalFile: Annexure A Dec for Multiple Project.pdf31 Jan 2025
Details of encumbrances concerned to FinanceFile: Non- Encumbrances Certificate Financial.pdf29 Jan 2025
Declaration in FORM BFile: Declaration in Form B - society notary.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Undertaking Commercial Unit.pdf29 Jan 2025
Details of encumbrances concerned to LegalFile: Non- Encumbrances Certificate Financial.pdf29 Jan 2025
Other - TechnicalFile: Sea Rock DA 106 160.pdf29 Jan 2025
Other - TechnicalFile: Sea Rock DA 230 277.pdf29 Jan 2025
Other - TechnicalFile: Sea Rock DA 161 230.pdf29 Jan 2025
Other - TechnicalFile: Sea Rock DA 56 105.pdf29 Jan 2025
Other - TechnicalFile: Sea Rock DA 1 55.pdf29 Jan 2025
Other - TechnicalFile: Sea Rock POA.pdf29 Jan 2025
Other - TechnicalFile: Lease Deed with MHADA Sign.pdf29 Jan 2025
Layout approvalFile: CHARKOP NEW APPROVED LAYOUT PLANS.pdf20 Jan 2025
Building plan approvalFile: IOA.pdf20 Jan 2025
Building plan approvalFile: IOA Plan 1.pdf20 Jan 2025
Building plan approvalFile: IOA Plan 2.pdf20 Jan 2025
Building plan approvalFile: IOA Plan 3.pdf20 Jan 2025
PAN CardFile: Gagangiri Construction PAN.pdf20 Jan 2025
Copy of the legal title reportFile: Title Report.pdf20 Jan 2025
Details of encumbrances concerned to FinanceFile: Non- Encumbrance Certificate.pdf20 Jan 2025
Copy of Layout Approval (in case of layout)File: CHARKOP NEW APPROVED LAYOUT PLANS.pdf20 Jan 2025
Proforma of Allotment letterFile: Allotment Letter final from Sohan.pdf20 Jan 2025
Declaration in FORM BFile: Declaration of Form B Notary.pdf20 Jan 2025
Declaration in FORM BFile: Declaration for authorised signatory.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sea Rock.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sea Rock.pdf20 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Plint CC 16012025.pdf20 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf20 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: IOA Plan 1.pdf20 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: IOA Plan 2.pdf20 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: IOA Plan 3.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory List.pdf20 Jan 2025
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf20 Jan 2025
CERSAI detailsFile: Cersai Undertaking.pdf20 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Rera Designated Bank Account.pdf20 Jan 2025
Deviation Report with respect to Allotment letterFile: Deviation Report.pdf20 Jan 2025
Details of encumbrances concerned to LegalFile: Non- Encumbrance Certificate.pdf20 Jan 2025
Other - TechnicalFile: Undertaking cum Declaration of Co- promoter.pdf20 Jan 2025
Deviation Report with respect to model copy of AgreementFile: Deviation Report compressed.pdf20 Jan 2025
Proforma of Agreement for saleFile: Draft AFS.pdf20 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure on interest in other real estate organisations merged.pdf20 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B opening iof Rera bank ac.pdf20 Jan 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured finance availed for the project.pdf20 Jan 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Gagan-138Sarita vidya mahal CHS LTD Nehru Nagar Kurla East Mumbai 400024142CompletedDec 2025Sep 2024
AerovistaThe Sahar CHSL parsiwada Sahar Road Chakala Andheri East Mumbai 400099209OngoingDec 2025Dec 2025

How this compares with Mumbai Suburban

40%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aadhya on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai6,700+ in Mumbai Suburban

2 kmAadhyaCompleted 119Lapsed / revoked 73Other 140Dot size: filed unitsN

Filed coordinates, straight-line distance. 332 registered projects within 2 km.

Builder: Gagangiri Construction

Gagangiri Construction has 5 registrations on MahaRERA, including AEROVISTA and Gagan 138. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Aadhya is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aadhya?

The registered promoter entity is Gagangiri Construction, a partnership as per the filing. Its GSTIN 27AAXFG0140Q1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aadhya?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aadhya?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aadhya?

The professionals named in the filing: Architect: Ms HRJ Architect & PMC; Engineer: Sihavat Consultancy Services; Engineer: Sanjay Rane & Associates; Chartered Accountant: P V Dalal & Co; Chartered Accountant: Jignesh shah & Co; Chartered Accountant: Harshada & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aadhya?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aadhya. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aadhya to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.